Resolved
RESOLVED that The Committee review and agree the updated Risk Management Strategy.
Governance & Audit Committee agreed this item on Wednesday 27 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that The Committee review and agree the updated Risk Management Strategy.
1.1This report presents the updated Risk Management Strategy to the Governance and Audit Committee for approval.
2 RECOMMENDATION 2.1 The Committee is asked to review and agree the updated Risk Management Strategy at Appendix 1.
3 REASONS FOR RECOMMENDATION 3.1 To ensure that the Risk Management Strategy is consistent with current procedures and focuses on the relevant priorities for risk management.
4 ALTERNATIVE OPTIONS CONSIDERED 4.1 The decision could be taken to not update the Strategy but it would then not reflect progress made in embedding risk management, would be inconsistent with current procedures for managing risk and would not include the present risk management priorities.
5 SUPPORTING INFORMATION Risk Management Strategy 5.1 The Risk Management Strategy was last approved by the Governance and Audit Committee in June 2017. It has now been reviewed to reflect the latest Council Plan, clarify responsibilities, include a worked example for the scoring methodology and RAG rating and update the priorities for risk management at the Council. The current priorities as set out in the updated Strategy can be summarised as follows:
1 Developing strategies to address key risks to reaching financial sustainably for the longer term. 2 Monitoring the impact of Brexit for the Council 3 Developing a pandemic recovery strategy, encompassing a long-term delivery and operational model for the Council post Covid. 4 Reviewing the Council’s resilience and mitigation strategies in response to increasing cyber threats 5 Revisiting risk appetite in relation to the insurance strategy for insurable risks within the financial constraints of the Council.
January 2021 1 6 Mapping climate change risks including identifying the specific risks to the Council’s goals for protecting and enhancing the environment.
5.2Feedback was sought on the updated Strategy from the Strategic Risk Management Group (SRMG) and the Corporate Management Team (CMT). All comments received have been incorporated in the updated Strategy attached at Appendix 1 for the Governance and Audit Committee to review and approve. Changes made as part of the update are marked as tracked changes.
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS Legal Advice 6.1 There are no specific legal implications arising from this report. However effective risk management helps to ensure compliance with legal and regulatory obligations. Financial Advice 6.2 There are no direct financial implications arising from this report. The proposal can, however, assist the Council’s financial situation by helping ensure that financial risks are understood and considered appropriately as part of an overall framework for managing overall risks. Equalities Impact Assessment 6.3 Not applicable. Strategic Risk Management Issues 6.4 An up to date Risk Management Strategy setting out the current priorities for embedding risk management is essential for setting out the direction for effective risk management at the Council.
7 CONSULTATION Principal Groups Consulted 7.1 The principal groups consulted were CMT and SRMG.
Method of Consultation 7.2 The draft updated Risk Management Strategy was reviewed by SRMG and e CMT on 12th November and 9th December respectively. All amendments suggested have been included in the Strategy attached at Appendix 1.
Contact for further information
Sally Hendrick – 01344 352092 [email protected]
Doc. Ref Risk Management Strategy
January 2021 2 BRACKNELL FOREST BOROUGH COUNCIL
RISK MANAGEMENT STRATEGY The Framework for Managing Opportunity and Risk
VERSION DATE APPROVED BY Version 1 29/11/2011 Governance and Audit Committee Version 2 1/4/2014 Governance and Audit Committee Version 3 June 2017 Governance and Audit Committee Version 4 January 2021
January 2021 3 CONTENTS Page
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management StrategyReport | 615 KB | DownloadRead as text |
Follow Governance & Audit Committee at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of previous meetingRESOLVED that, the minutes of the meeting of the committee held on the 17 June 2026 be approved as a correct record, ... | Approved | Open |
| 16 Sep 2026 | External Audit Update 2025/26 Financial StatementsThat the update be noted. | Noted | Open |
| 17 Jun 2026 | Minutes of previous meetingRESOLVED that, subject to the amendments above, the minutes of the meeting of the committee held on the 18 March 2026... | Approved | Open |
| 17 Jun 2026 | Annual Governance Statement 2026RESOLVED that the draft Annual Governance Statement (“AGS”) and Action plan appended to this report be approved. | Approved | Open |
| 17 Jun 2026 | Annual Standards Report 2025-2026RESOLVED that the Standards outputs in 2025/26 as set out in Appendix B be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.