Core Azure Hosting Procurement

Decided Executive 1 paper

Cabinet decided this item on Tuesday 10 December 2024. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

RESOLVED that i. a Microsoft Azure hosting service be procured to ensure continued server hosting in our current Microsoft Azure cloud environment. Supported and managed by in house ICT teams. ii. the procurement is undertaken using the Crown Commercial Services G-Cloud 14 (RM1557.14) framework, via requirements search, to direct award in line with the framework terms.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

To: Cabinet 10 December 2024

Strategic Procurement Plan for Azure hosting – Cloud Solution Provider Executive Director: Communities

1 Purpose of report 1.1 To seek approval to enter a procurement and award a 4-year contract for use of the Microsoft Azure Cloud infrastructure to host our datacentre and associated services, moving from an external fully managed service to management by Bracknell Forest Council ICT teams.

2 Cabinet member for (portfolio) Introduction 2.1 I am pleased to present the Strategic Procurement Plan for the Azure hosting – Cloud Solution Provider service. The primary objective of this procurement is to bring control of the Azure environment back in-house, thereby providing the organisation with greater flexibility for continued optimisation and control over scalability for services hosted in the environment. This procurement supports the ongoing delivery of the ‘Collaborative working’, ‘Location independent working’, ‘Cloud computing’, ‘Information assets and data’ and ‘Robust and Reliable IT’ strategic themes laid out in the current Digital and IT Strategy.

2.2Borough priorities: This procurement is an underpinning strategic activity that supports the identified priorities of the Council Plan.

3 Recommendation(s) 3.1 To procure a Microsoft Azure hosting service to ensure continued server hosting in our current Microsoft Azure cloud environment. Supported and managed by in house ICT teams.

3.2That the procurement is undertaken using the Crown Commercial Services G-Cloud 14 (RM1557.14) framework, via requirements search, to direct award in line with the framework terms.

4 Reasons for recommendation(s) 4.1 Our Microsoft Azure hosting is a key platform that would effectively prevent the access and use of multiple business and ICT systems (including line of business applications) if it were not available.

4.2The pricing model for this solution is consumption based, i.e., the Council pays only for the services which are actively used at any time. We can put services into ‘standby’ when they are not actively being used, which means the Council does not pay for services when not required. Managing this service in house means we can react to organisational requirements and changes quicker, without having to engage a third-party vendor we currently must.

4.3G-Cloud 14 offers a compliant procurement route to market. .

5 Alternative options considered 5.1 The option of doing nothing would result in loss of the organisations cloud infrastructure and all applications and their data that are hosted in that environment. This would include, but is not limited to, social care case management systems, highways and planning systems as well as some payment and library services.

5.2Consideration was given to continuing with a fully managed hosted solution via a new procurement at the end of the current contract. This was discounted due to availability of skilled staff in house and because it provides an additional layer of necessary approval and delay for any change requirements for organisational operational activity. It reduces our ability to optimise the environment directly reducing potential financial benefits to the organisation.

5.2Undertaking procurement via an alternative framework would not add commercial value or streamline any timeframes so was not considered further.

6 Supporting information 6.1 Microsoft Azure is the cloud-based data centre technology used by the Council. The Council migrated to a cloud infrastructure in 2020 following a decision not to retain end of life on premises servers in a physical data centre.

6.2Bracknell Forest Council are currently in a contract with a cloud service provider via a G-Cloud 12 framework agreement. This contract expires in March 2025. The current vendor was successful following a competitive tender process for the provision of:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Core Azure Hosting ProcurementDecisions 110 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
MT
Councillor Mary Temperton LABChair, present
HP
Councillor Helen Purnell LABVice-Chair, apologies
RB
Councillor Roy Bailey LABCommittee Member, present
PB
Councillor Paul Bidwell LABCommittee Member, present
GG
Councillor Guy Gillbe LABCommittee Member, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, present
KN
Councillor Kathryn Neil LABCommittee Member, present
MW
Councillor Megan Wright LABCommittee Member, present

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in... Decided Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open
22 Sep 2026 Procurement for GP LARC and NHS Health Check ServicesRESOLVED that Cabinet · APPROVES the strategic procurement plan for GP LARC and NHS Health Checks across Berkshire Ea... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies