Electrical Safety System Services and Maintenance Contract Renewal

Approved Executive 1 paper

Cabinet approved this item on Tuesday 18 March 2025. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

RESOLVED that Cabinet I. approves the Strategic Procurement Plan (Exempt Appendix A) to tender the services for a single organisation to carry out the routine servicing and maintenance of all planned preventative, responsive maintenance and servicing of the electrical systems across the portfolio of buildings in Bracknell. II. approves a contractual term of ten years with an initial period of 3 years and a further 7 years of optional extensions (2+2+2+1). The contract is based on a total contract term of 10 years with the first three years to be at a fixed cost to enable stability for the council. Subsequent years cost increases to be based on an average annual CPI index, agreed by both parties (as per contract renewal date). III. delegates authority to the Executive Director: Place in consultation with the Cabinet Member for Economy and Regeneration to accept the evaluated and preferred provider’s tendered price and award the contract, to the provider to meet the requirements of this proposed contract.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

To: CABINET 18 March 2025

Electrical Safety System Services and Maintenance Contract Renewal Executive Director: Place

1. Purpose of Report 1.1. To approve the strategic procurement plan attached in Exempt Appendix A to commission a Term Service Contractor to provide planned preventative and responsive maintenance and servicing of the electrical safety systems services across the Bracknell Forest Council’s portfolio of buildings.

2. Cabinet member for Economy and Regeneration Introduction 2.1 Approval of this Procurement Plan and proposed delegation supports the corporate priority to be an ambitious, resilient and sustainable organisation.

3. Recommendations 3.1 Cabinet Approves the Strategic Procurement Plan (Exempt Appendix A) to tender the services for a single organisation to carry out the routine servicing and maintenance of all planned preventative, responsive maintenance and servicing of the electrical systems across the portfolio of buildings in Bracknell.

3.2That Cabinet approves a contractual term of ten years with an initial period of 3 years and a further 7 years of optional extensions (2+2+2+1). The contract is based on a total contract term of 10 years with the first three years to be at a fixed cost to enable stability for the council. Subsequent years cost increases to be based on an average annual CPI index, agreed by both parties (as per contract renewal date).

3.3That Cabinet delegates authority to the Executive Director: Place in consultation with the Cabinet Member for Economy and Regeneration to accept the evaluated and preferred provider’s tendered price and award the contract, to the provider to meet the requirements of this proposed contract.

4. Reasons for Recommendations 4.1. The proposed contract is a public services contract for the purposes of the Public Contracts Regulations (“PCR 2015”). The relevant threshold for the application of the PCR is £177,897.50 (excluding VAT). The contract will exceed such threshold and therefore the Council will need to advertise on the Find a Tender Services. This contract will be procured using the restricted procedure in accordance with the applicable rules set out in the PCR 2015.

4.2Statutory building compliance is a critical element for Bracknell Forest Council. Ensuring our building/s are safe for all our users and is crucial to prevent loss of life and legal repercussions.

1 4.3. Electrical Installation Condition Report (EICR) & Electrical Equipment Testing (EET) testing legislation was put into effect to ensure that all companies conform to the Health and Safety at Work Act of 1974, Electricity at Work Regulations of 1989, Provision and Use of Work Equipment regulations of 1998 and the Management of Health and Safety at Work regulations of 1999.

4.4To ensure that the Council has an effective and reliable contractor in place to deal with Planned and Responsive maintenance issues that may arise, with potential for additional projects works, to ensure that the health and safety of occupants is maintained by this vital service.

4.5Failure to do so, could result in costly implications for the Council, and could also impact on the services we are able to offer individuals within the Borough. A large number of schools have bought into the Service Level Agreement (SLA) provided by the Construction and Maintenance team within property services. They are therefore benefiting from the planned and reactive maintenance, as well as a potential for additional projects work and services arising from this award. This links to Priority Four of the Council’s Medium Term objectives which seeks to ensure that the people within the Borough are always safe.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electrical Safety System Services and Maintenance Contract RenewalReport 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
MT
Councillor Mary Temperton LABChair, present
HP
Councillor Helen Purnell LABVice-Chair, present
RB
Councillor Roy Bailey LABCommittee Member, present
PB
Councillor Paul Bidwell LABCommittee Member, present
GG
Councillor Guy Gillbe LABCommittee Member, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, present
KN
Councillor Kathryn Neil LABCommittee Member, present, as expected, virtual
MW
Councillor Megan Wright LABCommittee Member, apologies

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in... Decided Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open
22 Sep 2026 Procurement for GP LARC and NHS Health Check ServicesRESOLVED that Cabinet · APPROVES the strategic procurement plan for GP LARC and NHS Health Checks across Berkshire Ea... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies