Electric Vehicle Chargepoints - Strategic Procurement Plan

Approved Executive 2 papers

Cabinet approved this item on Tuesday 24 June 2025. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED that Cabinet approve the Strategic Procurement Plan (CONFIDENTIAL ANNEX A) for a 15-year concession contract to install, manage and maintain EV charge points with the option to extend for a further three periods of 5 years each.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

To: Cabinet 24 June 2025

Local Electric Vehicle Infrastructure (LEVI) concession contract – Strategic Procurement Plan

Executive Director: Place

1 Purpose of report 1.1 To approve the strategic procurement plan for a concession contract to supply, install, manage and maintain electric vehicle (EV) charge points at no cost to the council, in return for the right to earn revenue from charge point use.

2 Cabinet member for Planning, Transport and Countryside Introduction 2.1 The Council is seeking to achieve as close to net zero emissions as possible by 2030. Decarbonising the transport sector will play a key part in achieving this aim. A transition to electric vehicles is one of the main levers of decarbonisation and so the ability of residents to charge their vehicles will be crucial.

2.2Analysis suggests up to 40% of residents do not have access to off-street parking at home and so will be reliant on a publicly available charge point network. Provision of on-street charging facilities for these residents is seen as essential, as detailed in the council’s electric vehicle charging strategy.

2.3Borough priorities: Green and sustainable environment.

3 Recommendation 3.1 That Cabinet approve the attached Strategic Procurement Plan (CONFIDENTIAL ANNEX A) for a 15-year concession contract to install, manage and maintain EV charge points with the option to extend for a further three periods of 5 years each.

4 Reasons for recommendation 4.1 The council currently provides 52 publicly available charging sockets, mainly in council- owned car parks. This new contract aims to provide a minimum of 400 charging sockets in residential streets within the borough, to help meet the expected demand for charging from EV owners without private off-street parking.

4.2The government Office for Zero Emission Vehicles (OZEV) has provided £326,000 funding towards the overall costs of the BFC scheme to help attract a supplier.

4.3The council does not have sufficient budget to purchase and manage charge points at scale, or the necessary expertise. Therefore, a concession contract for this provision is considered the most appropriate solution and this approach is being adopted nationally by local authorities. 5 Alternative options considered 5.1 The alternative options considered are:

• To purchase EV charging points and take the revenue from users to pay for their on-going maintenance – this is rejected as there is no budget available for the excessive up-front capital costs (400 sockets could cost in the region of £4million to purchase and install).

• Not to provide EV charging points – this was rejected as it would harm the ability to deliver the council’s net zero aims and objectives of the Local Transport Plan.

6 Supporting information 6.1 There is no current contract in place for the provision of electric vehicle charge points in a residential setting. The council does have several agreements in place with charge point operators for infrastructure within council-owned car parks and facilities, but these agreements cannot be used to provide the scale of charge point installation required by this OZEV-funded LEVI project.

6.2A significant proportion of housing within Bracknell Forest features dwellings clustered away from the public highway and served by separate parking courts or garage blocks. Therefore, solutions such as cross-pavement cable channels are not feasible for many residents.

6.3Lamp column charging, popular in some other local authority areas, is discounted as the majority of the lamp columns within the borough are positioned at the rear of the footway - meaning cables would have to trail across the footway to reach the vehicle. Furthermore, the underlying street lighting cable infrastructure does not have sufficient capacity to accommodate vehicle charging.

6.4The provision of dedicated charge points in practical locations is therefore considered the most appropriate solution.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electric Vehicle Chargepoints: Strategic Procurement PlanDecisions 77 KB DownloadRead as text
PDF
LEVI Annex BAppendix 126 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
MT
Councillor Mary Temperton LABChair, apologies
HP
Councillor Helen Purnell LABVice-Chair, in the Chair, present
RB
Councillor Roy Bailey LABCommittee Member, present
PB
Councillor Paul Bidwell LABCommittee Member, present
GG
Councillor Guy Gillbe LABCommittee Member, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, apologies
KN
Councillor Kathryn Neil LABCommittee Member, apologies
MW
Councillor Megan Wright LABCommittee Member, present

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in... Decided Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open
22 Sep 2026 Procurement for GP LARC and NHS Health Check ServicesRESOLVED that Cabinet · APPROVES the strategic procurement plan for GP LARC and NHS Health Checks across Berkshire Ea... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies