Public Protection Partnership Shared Service Arrangements
ApprovedExecutive1 paper
AI summaryBracknell Forest Cabinet approved a new shared Public Protection Partnership arrangement with West Berkshire and Wokingham until 31 March 2029, keeping West Berkshire as host and adding Wokingham to the joint committee.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedThree authority agreement with West Berkshire and Wokingham
MoneyNo direct financial implicationsAim is to contain cost within existing budgets
What happens nextFull Council asked to extend delegationsUntil 31st March 2029
Who it affectsThree councils and their residentsBracknell Forest, West Berkshire, Wokingham Borough
What was decided
Bracknell Forest will enter a new three authority agreement with West Berkshire and Wokingham Borough Councils until 31st March 2029, with a twelve month notice exit clause. Report P2, P3
Cabinet agreed to extend the delegation of Executive Functions undertaken by the Public Protection Service to the Joint Public Protection Committee until 31st March 2029. Report P4
Wokingham Borough Council becomes a full Member of the Joint Public Protection Committee under the original 2017 governance arrangements, and partners will move to the new arrangement as soon as practical rather than wait for current agreements to expire. Report P7, P8
Why
A peer review between October 2024 and January 2025 found the service is focussed and effective and that the shared model delivers efficiencies and greater resilience than individual authorities could achieve. Report 6.8, 6.9
The shared service secures around £400K per annum in grant funding and benefits from critical mass, shared management costs, shared ICT and legal subscriptions, and access to specialist functions. Report 5.2, 6.4
Ending the partnership would require an estimated £250-£300K to re-instate a stand alone in house service, a protracted HR and TUPE process, and a high risk of staff loss. Report 5.3, 5.4
What happens next
All three councils will consider the new agreement at their Executive, Cabinet and full Council meetings between October and December 2025. Report 6.14
Wokingham will rejoin the Joint Public Protection Committee at its December 2025 meeting. Report 6.14
An annual performance and service update report will be considered by the Communities and Environment Scrutiny Panel, and the in house legal team will carry out due diligence before the agreement is signed. Report P6, 7.1
The money
around £400K per annum Grant funding currently accessed by the shared service Report 5.2
around £250-£300K Estimated cost to re-instate a stand alone in-house service if disaggregated Report 5.3
around £200K Management costs within the disaggregation estimate, including re-instating the Head of Service role Report 5.3
around £50K ICT and other licensing costs within the disaggregation estimate Report 5.3
Options considered
Chosen: Enter a new three authority agreement until 31st March 2029 with revised governance. Retains efficiencies, grant income and resilience while allowing for clarity on local government reorganisation Report 6.13, P9
Rejected: Not to renew the partnership and let existing arrangements expire in January 2027. Would lose efficiencies and service resilience and would incur significant reinstating and TUPE costs Report P9, 5.3, 5.4
Implications
Financial: There are no direct financial implications in the report, but disaggregation would create significant costs above current budget levels. Report 7.2, P32, P40
Staffing: Disaggregation would require a protracted HR process, TUPE transfer and is likely to lead to staff losses, potentially affecting Bracknell Forest staff twice in quick succession. Report 5.4, P41
Legal: In-house legal team will carry out due diligence before the new Inter Authority Agreement is signed, broadly returning to the 2017 framework. Report 7.1, P30
Equalities: The earlier Equalities Impact Assessment remains valid for the new arrangement. Report 7.4, P36
Risk: Peer review provided assurance on quality of the shared service, but uncertainty from local government reorganisation and a separate West Berkshire merger proposal is a background factor. Report 7.5, P38, 6.12
Climate: Recommendations are not expected to have an impact on CO2 emissions. Report 7.6, P42
Other: Recommendations are expected to have a positive impact on health and wellbeing of customers and staff. Report 7.7, P44
Who and where
Residents of Bracknell Forest, West Berkshire and Wokingham Borough who receive environmental health, licensing and trading standards services Report 6.1
Public Protection Partnership staff across all three councils Report 5.4, P41
Joint Public Protection Committee members from the three partner councils Report 6.7, 6.10
Timeline
6th January 2017: Original inter-authority agreement underpinning the shared service Report P8, 6.4
October 2024 to January 2025: Peer review of the Public Protection Partnership conducted Report 6.8, P9
October to December 2025: All three councils to consider the new agreement at Executive, Cabinet and full Council meetings Report 6.14
December 2025: Wokingham Borough Council to rejoin the Joint Public Protection Committee Report 6.14
8th January 2027: Existing shared service and 2022 Wokingham commissioned services agreements are due to end Report 6.6
31st March 2029: New three authority agreement would run until this date Report P2, 6.13
Plain English for the jargon
PPP: Public Protection Partnership, the shared service delivering Environmental Health, Licensing and Trading Standards for the partner councils.
JPPC: Joint Public Protection Committee, the strategic oversight body for the shared service.
IAA: Inter Authority Agreement, the contractual document underpinning the shared service between councils.
TUPE: Transfer of Undertakings (Protection of Employment) regulations, governing staff transfer in service reorganisations.
EQiA: Equalities Impact Assessment, an assessment of how a proposal affects people with protected characteristics.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37
Resolved
RESOLVED that the Cabinet approves the following recommendations following the peer review: a. Bracknell Forest Council enter into a new three authority agreement with West Berkshire Council and Wokingham Borough Council until the 31st March 2029. b. That the agreement includes an exit clause based on a minimum of twelve months’ notice. c. The Cabinet agrees to extend the delegation of the Executive Functions undertaken by the Public Protection Service to the Joint Public Protection Committee until 31st March 2029. d. That in line with the recommendations of the peer review the host authority should remain West Berkshire Council to avoid significant short-term disruption. e. That an annual performance and service update report for the Service be considered by the Communities and Environment Scrutiny Panel. f. That the partners should not wait for the expiry of the existing agreements but enter into the new arrangement as soon as practically possible. g. That Wokingham Borough Council becomes a full Member of the Joint Public Protection Committee in line with the governance arrangements set out in the original inter-authority agreement of the 6th January 2017.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
3.1That the Cabinet approves the following recommendations following the peer review:
a) Bracknell Forest Council enter into a new three authority agreement with West Berkshire Council and Wokingham Borough Council until the 31st March 2029.
b) That the agreement includes an exit clause based on a minimum of twelve months’ notice.
c) The Cabinet Agree to extend the delegation of the Executive Functions undertaken by the Public Protection Service to the Joint Public Protection Committee until 31st March 2029.
d) That in line with the recommendations of the peer review the host authority should remain West Berkshire Council to avoid significant short-term disruption.
e) That an annual performance and service update report for the Service be considered by the Communities and Environment Scrutiny Panel.
f) That the partners should not wait for the expiry of the existing agreements but enter into the new arrangement as soon as practically possible.
g) That Wokingham Borough Council becomes a full Member of the Joint Public Protection Committee in line with the governance arrangements set out in the original inter-authority agreement of the 6th January 2017. 4 Reasons for recommendations 4.1 A peer review of the existing Public Protect Partnership arrangements was conducted between October 2024 and January 2025. The review team concluded that the Service is focussed and effective in providing statutory regulatory services to protect residents. It also concluded that as a shared service it is delivering efficiencies and greater service resilience than individual authorities would be able to achieve. The review made a series of recommendations for all three partner authorities (Bracknell Forest, West Berkshire and Wokingham Borough Councils) to consider. A full summary of the findings of the review can be found here: Peer Review Recommendations
5 Alternative options considered 5.1 Not to renew the partnership. This was discounted given the efficiencies and greater service resilience resulting from being in the partnership.
5.2The savings from shared services arise from sharing the costs of management as well as systems such as ICT and subscriptions such as legal subscriptions etc. In addition, the critical mass that the shared service provides allows for it to access significant amounts of grant funding (currently around £400K per annum) as well as share cost bases with other authorities outside of the PPP e.g. financial investigation work, complex investigations, case management functions and other specialist functions such as animal feeding stuffs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.