CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council
Cabinet, Tuesday 14 July 2026 at 6.30pm

Casualty Insurance Tender Strategic Procurement Plan

Approved Executive 1 paper

AI summaryBracknell Forest Cabinet approves plan to retender casualty insurance, with new contract starting 1 April 2027 and award delegated to the Executive Director for Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAward and extensions delegated to Executive Director
Money£1.429m current contract valueNew costs to be set in 2027/28 budget
What happens nextFurther competition via YPO frameworkContract award expected February 2027
Who it affectsCouncil insurance cover from April 2027Recharges to all council services

What was decided

Cabinet approved the Strategic Procurement Plan for retendering the casualty insurance provider and associated claims handling. Report 3.1, 1.1

Authority to approve the contract award and permitted extensions was delegated to the Executive Director for Resources, in consultation with the Cabinet Member for Transformation and Finance. Report 3.2

Why

All current contract extensions have been used, so the existing arrangement cannot continue beyond 31 March 2027. Report 5.1, 1.1

Insurance is needed to meet Financial Regulations and protect the council against catastrophic losses and personal injury claims. Report 2.1, 4.2

The public sector insurance market has few suppliers, so a framework-based further competition is expected to attract more bidders than an open process. Report 5.3, 6.1, 7.7

What happens next

A supplier engagement day is planned for September 2026, with further competition documents issued in October 2026 and responses due in December 2026. Report 6.2

The contract is scheduled to be awarded in February 2027, with mobilisation in March 2027 and a start date of 1 April 2027. Report 6.2

The procurement outcome will be considered as part of the 2027/28 budget-setting process. Report 7.4

The money

  • £1.429m Current contract value over its full term including extensions Report 7.4

Options considered

  • Rejected: Extend the existing casualty insurance contract. All available extensions under the current contract have been used Report 5.1
  • Rejected: Do nothing and let the current contract end on 31 March 2027. The council would have no liability cover, breach Financial Regulations, and lose financial resilience Report 5.2
  • Rejected: Run a fully open tender procedure. Few insurers respond to open tenders with extra contract terms, reducing competition compared with a framework Report 5.3
  • Chosen: Use the YPO Insurance Placement II Dynamic Purchasing System via further competition. Compliant route giving access to pre-qualified insurers under established terms, expected to improve response and reduce procurement risk Report 6.1, 7.1, 7.7

Implications

  • Financial: Annual premiums are paid from the central insurance budget and recharged to services, with new costs to be set through the 2027/28 budget. Report 7.4
  • Legal: The procurement will follow the Public Contracts Regulations 2015 as the YPO framework was established under those rules; no legal barriers identified. Report 7.1, 7.2, 7.3
  • Risk: Insurance is a key control against catastrophic losses and multiple personal injury claims where the council may be legally liable. Report 7.7
  • Equalities: An initial screening found that a full Equality Impact Assessment was not required. Report 7.6
  • Climate: The procurement is expected to have no impact on CO2 emissions as it covers insurance and claims handling only. Report 7.8, 7.9
  • Other: Indirect health and wellbeing benefit through better managed liability claims and maintained financial resilience. Report 7.10

Who and where

  • Bracknell Forest Council services, which are recharged for insurance costs Report 7.4
  • Insurers and brokers participating in the YPO further competition Report 6.1, 6.4
  • Residents and claimants whose liability claims would be handled under the new contract Report 7.10

Timeline

  • September 2026: Supplier engagement day Report 6.2
  • October 2026: Further competition documents issued via Procontract Report 6.2
  • December 2026: Deadline for responses from bidders Report 6.2
  • February 2027: Contract award Report 6.2
  • March 2027: Mobilisation period Report 6.2
  • 31 March 2027: Current contract ends Report 5.1, 5.2
  • 1 April 2027: New contract start date Report 1.1, 6.2

Plain English for the jargon

  • Casualty insurance: Insurance cover for liabilities such as injury, damage or loss, including personal injury claims against the council.
  • YPO Insurance Placement II Dynamic Purchasing System: A public sector procurement framework set up by YPO after an OJEU tender, used to run further competitions with pre-qualified insurers.
  • Further competition: A mini-tender run among suppliers already admitted to a framework, rather than a fully open public tender.
  • Strategic Procurement Plan: The council's approved plan setting out how a specific procurement will be run, including route to market, timescales and evaluation approach.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item119

Resolved

RESOLVED that the Cabinet: · Approve the Strategic Procurement Plan for the procurement of a Casualty Insurance provider. · Delegates authority to approve the contract award and permitted contract extensions to the Executive Director - Resources in consultation with the Cabinet Member Transformation and Finance
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To seek approval of the Strategic Procurement Plan for the retendering of the casualty insurance provider with associated claims handling services. The new contract is scheduled to commence on 1st April 2027 and will have a total potential duration of up to seven years. This will comprise an initial term of three years, with the option to extend for a further two years, followed by an additional extension of up to two years (3 + 2 + 2 years).

2. Cabinet member for (portfolio) Introduction

2.1As part of the Strategic Procurement Plan I support the recommendation for the timely procurement of a Casualty Insurance provider. Section 4.2 of the Financial Regulations state the Cabinet is responsible for ensuring that the Council has proper insurance. The Council’s risk programme relies on proper insurance to cover against serious and potentially catastrophic loss. I am confident the recommended insurance procurement process as set out in this paper will result in the Council’s needs for risk abatement, insurance, and financial control to be met.

2.2Borough priorities: Thriving and Connected Ecomony

3. Recommendation(s)

Cabinet is asked to:

3.1Approve the Strategic Procurement Plan for the procurement of a Casualty Insurance provider.

3.2Delegate authority to approve the contract award and permitted contract extensions to the Executive Director - Resources in consultation with the Cabinet Member Transformation and Finance

4. Reasons for recommendation(s)

4.1To enable the Council to procure new insurance policies for casualty insurances and associated claims handling services.

4.2The purpose of insurance is to provide financial protection against specified contingencies such as injury, damage or loss. Section 4.2 of the Financial Regulations state the Cabinet is responsible for ensuring that proper insurance exists where appropriate. 4.3. Insurance cover is an essential element of the Council’s risk programme, particularly as a means of providing against catastrophic losses or multiple personal injury claims being brought against the Council if one of our services was legally responsible for the particular incident occurring

Alternative options considered

5.1Extending - Extending the existing arrangements is not possible; all possible extensions within the current contract have been utilised.

5.2Do nothing and the current contract ceases on 31st March 2027 - Current insurance provision will lapse and the Council will have no insurance protection in place for any liability related incidents occurring after 31st March 2027. The Council would not be able to meet its obligations under the Financial Regulations, or maintain financial resilience in the event of claims and catastrophic losses. Finally it would not be able to provide assurance to Members, officers and service areas that key liabilities are appropriately managed.

5.3Alternative tendering routes - The use of a a fully advertised process using the open procedure was considered however a number of insurers have not responded to tenders where there are additional contract terms in place. This would limit the competition and result in a lower level of response than through a framework agreement.

6. Supporting information

6.1The project will cover the requirement for Casualty Insurance Services with effect from the 1st April 2027. The evaluation team intends to ensure value for money by utilising the YPO Insurance Placement II Dynamic Purchasing System. This was created by a full OJEU advertised tender and awarded on 21st May 2024. Those providers already appointed by YPO will be invited to participate in a Further Competition. This will enable the project team to ensure the new contract is in place by 1st April 2027. The Dynamic Purchasing System provides a compliant and efficient route to market with pre-qualified insurers and pre-agreed contract terms reducing time and resource requirements compared to running an open process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Casualty Insurance Tender Strategic Procurement PlanDecisions 76 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
HP
Councillor Helen Purnell LABChair, present
GG
Councillor Guy Gillbe LABCommittee Member, present
PB
Councillor Paul Bidwell LABVice-Chair, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, apologies
MW
Councillor Megan Wright LABCommittee Member, apologies
GP
Councillor Georgia Pickering LABCommittee Member, present
RF
Councillor Ryan Frost LABCommittee Member, present
SO
Councillor Stephen O'Regan LABCommittee Member, present, as expected, virtual
JB
Jamie BeardsmoreClerk, present

On this subject at Bracknell Forest

Search all
  1. Casualty Insurance Tender Strategic Procurement PlanThis decision
  2. Casualty Insurance and Claims Handling Service TenderDecided

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Council Plan Overview Report - Q1RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in... Decided Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open
22 Sep 2026 Procurement for GP LARC and NHS Health Check ServicesRESOLVED that Cabinet · APPROVES the strategic procurement plan for GP LARC and NHS Health Checks across Berkshire Ea... Approved Open