( i ) that the Director of Finance and the Director of Children and Families be authorised to submit the OBC to PfS in the form set out in Appendix 1 to the report from the Director of Children and Families with the detailed content completed by the Director of Children and Families, subject to the FAM allocation being increased to meet the Council’s estimate of costs as set out in Appendix 5 or the Director of Finance being satisfied that any costs over and above the FAM allocation can be met from an existing capital budget and upon approval to commence procurement via the PfS National Framework; (ii) that the Section 151 Officer be authorised to complete and issue the letter confirming the affordability of the scheme, subject to the FAM allocation being increased or the Director of Finance being satisfied as set out in paragraph 2.1 Template attached as Appendix 4 to the Director’s report; (iii) that the local authority’s commitment to the project as set out in Appendix 2 to the Director’s report be confirmed and approved given to the signing of the Memorandum of Understanding in the form set out in Appendix 3 or with such amendments as the Director of Children and Families, in consultation with the Borough Solicitor, considers to be appropriate.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Page 1 of 23 Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version Document Control
PfS and its advisers accept no liability whatsoever for any expense, liability, loss, claim or proceedings arising from reliance placed upon this Template Document for the Outline Business Case.
Document Properties Document Owner Academies Director Organisation Partnerships for Schools Title PfS Contractors Framework Template Document Outline Business Case Abstract This document provides guidance for the development of the Outline Business Case (OBC) for Academy Schemes being procured through the Partnerships for Schools (PfS) Contractors Framework.
For Academy Schemes being procured through Building Schools for the Future, the Local Authority (LA) should contact their PfS Project Director for guidance. For local BSF programmes of Primary Capital Programme schemes being delivered through the PfS Contractors Framework, separate OBC guidance is available for use and LAs should contact their PfS Project Director for further information.
The document outlines the requirements for submitting the OBC, which should set out the options appraisal, cost estimates, affordability assessment and procurement strategy for the school(s) in sufficient detail to allow capital funding to be confirmed and gain approval to proceed with the delivery of the school(s) via the PfS Contractors Framework.
Version History Date Editor Version Status Reason for change
11 Dec 09 KN 1.0 Draft First issue of document
TABLE OF CONTENTS
EXECUTIVE SUMMARY 4 Introduction 4 Overview and Commitment 4 Procurement Strategy 4 Design and Construction 4 ICT 5 Facilities Management 5
Page 2 of 23 Created by Neevia Document Converter trial version http://www.neevia.com Affordability 5 Readiness to Deliver 5 Moving Forward 5
Notes
1. Submission of OBC – All appendices should be separated from the main body of the OBC, must be named as indicated below and sent on a CD with the main body of the OBC for formal submission.
• [ ] Academy - Appendix 1C – Letter of Support from LA
Page 3 of 23 Created by Neevia Document Converter trial version http://www.neevia.com EXECUTIVE SUMMARY
Introduction The document outlines the options appraisal, cost estimates, affordability assessment and procurement strategy for the school(s) in sufficient detail to allow capital funding to be confirmed and gain approval to proceed with the delivery of the academies/school(s) via the PfS Contractors Framework.
Drafting Note: The summaries from each section within the OBC document should be brought forward and provided under each of the headings below as indicated.
Overview and Commitment Section 1 and Appendix 1 of this OBC describe the Scheme and confirm the commitment of all parties to the procurement process.
The Local Authority has confirmed that the Scheme fits with its local priorities.
The Scheme involves * school(s)
The Education Brief, including the curriculum model and accommodation schedule, has been developed and signed off by the Project Steering Group (PSG) and by the Department for Children, Schools and Families (DCSF). The accommodation schedule details a total area that is within the BB98 gross internal floor area stated in the Funding Allocation Model (FAM).
The Sponsor/Academy Trust and LA confirm their commitment to working together to procure the design and construction of the new Academy using the PfS Contractors Framework and confirm that they will follow established PfS procedures and utilise the standard suite of documents for procurement.
The Sponsor/Academy Trust has signed the Funding Agreement OR DCSF has endorsed the project to progress into procurement and engage with the Contractors Framework Panel Members.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.