( i ) that approval be given to the draft Final Business Case (FBC) for the rebuild of the Crest Girls’ and Crest Boys’ Academies in the form annexed as Appendix 1 and delegate to the Director of Regeneration and Major Projects in consultation with the Director of Finance and Corporate Services authority to approve the FBC and to submit it to Partnerships for Schools ( PfS ); (ii) that approval be given to award the Design and Build Contract to Wates Construction Ltd for the rebuild of the Crest Girls’ and Crest Boys’ Academies subject to approval of the FBC from PfS and the Council entering into a Development Agreement with the Sponsor; (iii) that approval be given to the Council entering into a Development Agreement in connection with the rebuild of the Crest Girls’ and Crest Boys’ Academies with the Sponsor; (iv) that the financial implications for the Council (as detailed in paragraphs 4.1 – 4.13 and Appendices 3 and 4) of the report from the Director of Regeneration and Major Projects be noted; (v) that the arrangements for project management and technical advice for this project (as detailed in paragraphs 3.6 – 3.8) of the Director's report be noted; (vi) that the risks attached to this project and the strategy outlined for managing risk (as detailed in paragraphs 3.34 – 3.36) of the Director's report be noted. (vii) that officers’ intention to appoint Wates Construction Ltd to undertake additional works outside of the Design and Build Contract (as detailed in paragraph 3.37) of Director's report be noted.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report seeks authority to award the Design and Build Contract to completely rebuild the Crest Girls’ and Crest Boys’ Academies. The report outlines the project background and the procurement process undertaken. It also seeks approval to enter into a Development Agreement with the Academies’ sponsors and approval to submit the Final Business Case to Partnerships for Schools in order to subsequently award the Design and Build contract.
Recommendations
The Executive is recommended to:
2.1Approve the draft Final Business Case (FBC) for the rebuild of the Crest Girls’ and Crest Boys’ Academies in the form annexed as Appendix 1 and delegate to the Director of Regeneration and Major Projects in consultation with the Director of Finance and Corporate Services authority to approve the FBC and to submit it to Partnerships for Schools (PfS).
2.2Award the Design and Build Contract to Wates Construction Ltd for the rebuild of the Crest Girls’ and Crest Boys’ Academies subject to approval of
Meeting: Executive Version no: v1.1 Date: 14 November 2011 Date: 3 November 2011 the FBC from PfS and the Council entering into a Development Agreement with the Sponsor. 2.3 Approve the Council entering into a Development Agreement in connection with the rebuild of the Crest Girls’ and Crest Boys’ Academies with the Sponsor.
2.4Note the financial implications for the Council (as detailed in paragraphs 4.1 – 4.13 and Appendices 3 and 4).
2.5Note the arrangements for project management and technical advice for this project (as detailed in paragraphs 3.6 – 3.8).
2.6Note the risks attached to this project and the strategy outlined for managing risk (as detailed in paragraphs 3.34 – 3.36).
2.7Note Officers’ intention to appoint Wates Construction Ltd to undertake additional works outside of the Design and Build Contract (as detailed in paragraph 3.37).
3.0Detail
Project Background
3.1This is a single procurement project of the Crest Girls’ and Crest Boys’ Academies; two separate Academies sharing one site in the Dollis Hill ward. The Crest Girls’ and Crest Boys’ Academies (the Academies) were formerly the John Kelly Boys and John Kelly Girls Technology Colleges before becoming academies in September 2009 (see minutes of Executive meeting of June 2009 for further details). The existing Academies buildings are in very poor condition and have exceeded their lifespan. This project, funded by the Governments Academies Programme through Partnerships for Schools (PfS) will see both Academies totally rebuilt on the existing site whilst the current Academies remain in operation.
3.2In February 2010 the Executive gave approval to a number of recommendations for this project, including the submission of the Outline Business Case (OBC) to PfS. A technical amendment report was required in April 2011 as the minutes of the February meeting had not recorded decisions on all recommendations. This report will outline the progress made to action those recommendations prior to the submission of this report and will highlight any areas where the recommendation was implemented differently to that originally envisaged.
3.3Since February 2010 officers have completed the following instructions from the Executive committee: • Submitted and gained approval to the OBC from PfS • Undertaken the procurement of a design and build contractor in line with the PfS Contractors’ Framework (see paragraphs 3.12 – 3.19 for further detail).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.