DECISION: (a) Delegated authority to the Director of Planning to determine this planning application and to grant planning permission subject to the completion of a satisfactory Section 106 agreement on the heads of terms as set out below (or amended heads of terms as agreed by the Director of Environment and Culture or duly authorised person), the exact terms thereof agreed by the Director of Planning on advice from the Interim Borough Solicitor; but (b) if the legal agreement has not been entered into by the application’s statutory expiry date of 06/04/10, to delegate authority to the Director of Environment and Culture, or other duly authorised person, to refuse planning permission; and (c) if the application is refused or withdrawn for the reason in b) above to delegate authority to the Director of Environment and Culture, or other duly authorised person to grant permission in respect of a further application which is either identical to the current one, or in his opinion is not materially different, provided that a satisfactory section 106 has been entered into, on advice from the Borough Solicitor.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
PROPOSAL: Demolition of existing buildings and erection of a 3-, 4- and 5-storey building, comprising 2 commercial units (Use Classes A1, A2, A3 or A4) at ground-floor and ancillary basement level and 30 self-contained flats (one 1-bed, nineteen 2-beds and ten 3-bedroomed units,) at upper-floor levels, a car-free development with formation of new vehicular and pedestrian accesses, cycle and refuse stores to side and communal amenity space to rear
APPLICANT: Botwellears Ltd and Network Housing Group
CONTACT: Forge Architects
PLAN NO'S: Please refer to condition 2 __________________________________________________________
RECOMMENDATION (a) To delegate authority to the Director of Planning to determine this planning application and to grant planning permission subject to the completion of a satisfactory Section 106 agreement on the heads of terms as set out below (or amended heads of terms as agreed by the Director of Environment and Culture or duly authorised person), the exact terms thereof agreed by the Director of Planning on advice from the Borough Solicitor; but (b) if the legal agreement has not been entered into by the application’s statutory expiry date of 06/04/10, to delegate authority to the Director of Environment and Culture, or other duly authorised person, to refuse planning permission; and (c) if the application is refused or withdrawn for the reason in b) above to delegate authority to the Director of Environment and Culture, or other duly authorised person to grant permission in respect of a further application which is either identical to the current one, or in his opinion is not materially different, provided that a satisfactory section 106 has been entered into.
SECTION 106 DETAILS The application requires a Section 106 Agreement, in order to secure the following benefits:-
1. Payment of the Council's legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance
2. Affordable Housing – 100% to be agreed with the council
3. A reduced RSL contribution of £2400 per bedroom index-linked from the date of committee
Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version for Education, Sustainable Transportation, including Car Clubs, Air Quality and Open Space & Sports in the local area.
4. Car Free, the residents can not apply for residents' parking permits.
5. Sustainability - submission and compliance with the Sustainability check-list ensuring a minimum of 50% score is achieved, Code for Sustainable Homes Level 3 and BREEAM Very Good, with compensation should it not be delivered. In addition to adhering to the Demolition Protocol.
6. Offset 20% of the site's carbon emissions through onsite renewable generation. If proven to the Council's satisfaction that this is unfeasible, provide it off site through an in-lieu payment to the council who will provide that level of offset renewable generation.
7. A contribution of £20,000, index-linked from the date of committee for improvements to local play and public amenity areas
8. Join and adhere to the Considerate Contractors scheme.
And to authorise the Director of Environment and Culture, or other duly authorised person, to refuse planning permission by the end of the 13-week application process or by another date if agreed in writing with the Local Planning Authority, if the applicant has failed to demonstrate the ability to provide for the above terms and meet the policies of the Unitary Development Plan and Section 106 Planning Obligations Supplementary Planning Document by concluding an appropriate agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.