Resolved
Grant consent subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning to agree the exact terms thereof on advice from the Director of Legal and Procurement.
Planning Committee agreed this item on Wednesday 6 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Grant consent subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning to agree the exact terms thereof on advice from the Director of Legal and Procurement.
Committee Report Planning Committee on 6 April, 2011 Case No. 11/0137 __________________________________________________ RECEIVED: 10 January, 2011
WARD: Alperton
PLANNING AREA: Wembley Consultative Forum
LOCATION: Chequers, Managers Flat and Store, 149 Ealing Road, Wembley, HA0 4BY
PROPOSAL: Minor material amendment to planning permission 09/3013 granted 06/04/10 for the Demolition of existing buildings and erection of a 3-, 4- and 5-storey building, comprising 2 commercial units (Use Classes A1, A2, A3 or A4) at ground-floor and ancillary basement level and 30 self-contained flats (one 1-bedroom, nineteen 2-bedroom and ten 3-bedroom units,) at upper-floor levels, a car-free development with formation of new vehicular and pedestrian accesses, cycle and refuse stores to side and communal amenity space to rear and subject to a Deed of Agreement dated 6th April 2010 under Section 106 of the Town and Country Planning Act 1990, as amended. The ammendment is for:
• The insertion of 2 obscured glazed windows within eastern elevation facing 2 Stanley Avenue.
APPLICANT: Network Housing Group
CONTACT: Forge Architects
PLAN NO'S: Please refer to condition 2 __________________________________________________________
RECOMMENDATION Grant consent subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning to agree the exact terms thereof on advice from the Borough Solicitor
SECTION 106 DETAILS The application requires a Section 106 Agreement, in order to secure the following benefits:-
1. Payment of the Council's legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance
2. Affordable Housing – 100% to be agreed with the council
3. A reduced RSL contribution of £2400 per bedroom index-linked from the date of committee for Education, Sustainable Transportation, including Car Clubs, Air Quality and Open Space & Sports in the local area. 4. Car Free, the residents can not apply for residents' parking permits.
5. Sustainability - submission and compliance with the Sustainability check-list ensuring a minimum of 50% score is achieved, Code for Sustainable Homes Level 3 and BREEAM Very Good, with compensation should it not be delivered. In addition to adhering to the Demolition Protocol.
6. Offset 20% of the site's carbon emissions through onsite renewable generation. If proven to the Council's satisfaction that this is unfeasible, provide it off site through an in-lieu payment to the council who will provide that level of offset renewable generation.
7. A contribution of £20,000, index-linked from the date of committee for improvements to local play and public amenity areas
8. Join and adhere to the Considerate Contractors scheme.
And to authorise the Head of Area Planning, or other duly authorised person, to refuse planning permission by the end of the 13-week application process or by another date if agreed in writing with the Local Planning Authority, if the applicant has failed to demonstrate the ability to provide for the above terms and meet the policies of the Unitary Development Plan and Section 106 Planning Obligations Supplementary Planning Document by concluding an appropriate agreement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Chequers, Managers Flat and Store, 149 Ealing Road, (Ref. 11/0137)Report | 461 KB | DownloadRead as text |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.