( i ) that the T f L capital allocation of £3,591,000 for the financial year 2011/12 be noted; (ii) that the Head of Transportation be instructed to implement the schemes and initiatives set out in the report and ensure their delivery using the allocated budget resources; (iii) that the Head of Transportation be authorised to undertake any necessary non-statutory and statutory consultation, to consider any objections or representations and to implement the necessary Traffic Management Orders if there are no objections or representations, or if the Head Transportation considers the objections or representations are groundless or insignificant and otherwise to refer objections or representations to the Committee for further consideration.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Appendix 1: Provisional LIP (11/12) TfL Capital Funding Notification Paper
5 May 2010.
Highways Committee 9 February 2011.
Transportation Local Implementation Plan:
Transportation Capital Allocation 2011-2012. LOCAL IMPLEMENTATION PLAN FUNDING FOR 2011/12
1.0Background and key issues
1.1The Guidance on Developing the Second Local Implementation Plans (May 2010) sets out the requirements and available support for London boroughs producing their second Local Implementation Plans (LIPs). It also provides the framework for the required Annual Spending Submission. Accordingly, the LIP Guidance should be the starting point for London boroughs when determining their proposed programmes of work. The purpose of this note is to confirm the available LIP funding from 2011/12 to 2013/14 and to provide specific information on issues of relevance to the 2011/12 Annual Spending Submission. The key points to note are as follows: • The Corridors and Neighbourhoods programmes have been combined into a single programme resulting in four main1 LIP programmes (Corridors & Neighbourhoods, Smarter Travel, Maintenance and Major Schemes) • Funding for the second LIP period (2011/12 to 2013/14) is allocated for Corridors & Neighbourhoods and Smarter Travel using a needs based formula, details of which can be found in section 4 (Funding and approvals) of the LIPs Guidance (May 2010) • The £100k per annum per borough for use on Local Transport Projects has been retained • As a result of a review of LIP funded partnerships conducted in 2009/10, the number of partnerships in receipt of LIP funding has been reduced from 14 to 6 (five new sub-regional partnerships and one pan London partnership2), with the consequent savings re-cycled into the needs-based formula funding for 2011/12. • There are no changes to the way in which Maintenance and Major Schemes funding is allocated, other than the fact that Major Schemes submissions will only normally now be considered for projects costing more than £1m in total over the whole life of the project. Notes: (1) funding is also provided for signal modernisation work and an amount is top-sliced to support partnerships and other matters (2) £1.5m has also been allocated to the Strategic Walks Network in 2011/12 to enable completion of the Network.
2.0Breakdown of LIP funding
2.1Appendix 1 sets out the key variables used in determining the available funding to be allocated for those programmes funded through the needs based formula. The formula is unchanged from that developed for the transition year (2010/11), with the same indicators and weightings applied. However, the borough specific data has been updated to reflect the most recent information available. Details of these changes were sent to borough LIP contacts earlier this year.
2.2Appendix 2 provides a breakdown of the top-slicing of the formula allocated budget.
3.0Reforms to LIP support for partnerships
3.1In 2009/10 a review of LIP funded partnerships was undertaken, led by the Partnerships Review Team (PRT), which included representatives from the boroughs, London Councils, existing partnerships, GLA and TfL. The outcomes of this work were the formation of five new sub-regional partnerships (aligned to MTS sub-regions), a framework for governance and hosting requirements, funding information and suggested functions. Details on the partnership review can be found on the Borough Extranet: http://boroughs.tfl.gov.uk/partnership_forums.aspx
3.2Funding has been determined for the new sub-regions on the basis of a fixed amount for each sub-region (£80k), with an additional amount per borough (£13k), based on core constituent boroughs within each sub-region, as set out in MTS. Note: funding is dependent upon sub-regional partnerships operating fuzzy boundaries (i.e. other boroughs can join), but this will not change the available funding allocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.