( i ) that approval be given to award a support and maintenance contract in respect of frameworki to Corelogic Ltd for a term of five year with an optional two year extension from 1 June 2011; (ii) that approval be given to tenders not being invited in accordance with Contract Standing Order 86 (e) ( i ) for the reasons detailed in paragraph 3.7 of the report from the Director of Housing and Community Care.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests authority to award a support and maintenance contract in respect of “frameworki", the Council’s Adult and Children Social Care Case Management IT System and seeks approval not to invite tenders in accordance with Contract Standing Order 86 (e)(i).
Recommendations
2.1The Executive award a support and maintenance contract in respect of frameworki to Corelogic Ltd for a term of five (5) year with an optional two (2) year extension from 1 June 2011.
2.2The Executive give approval to tenders not being invited in accordance with Contract Standing Order 86 (e) (i) for the reasons detailed in paragraph 3.7
3.0Detail
3.1The frameworki system (“framework”) is the Case/Care Management and Workflow Database IT System used by both Adult Social Care and Children Social Care in both the Housing & Community Care and Children & Families Departments respectively.
3.2Frameworki was procured via an EU compliant tender process. The contract for the supply, the implementation of the software and the ongoing support and maintenance was awarded to Corelogic Ltd (“Corelogic”) on 1st April 2003. The contract period was for an initial five (5) years plus optional three (3) years. In the event the contract was extended for the optional 3 years and therefore the support and maintenance element of the contract ended on the 31st March 2011.
3.4Officers consider the benefits to Brent of continuing to use the frameworki system are:
• The System meets current Social Care business requirements • The System’s future system software functionality roadmap has been developed in partnership with the National User Group of which Brent is a member. • Continuity with no disruption or training to 400 staff (bringing in a new system would be extremely disruptive to staff and costly to the Council particularly when it is not required). • The Council is currently in the process of implementing new functionality within frameworki which is part of a One Council Tranche 1 Project (Adult Social care Transformation – Customer Journey)to commence from 1st April 2011. Any change of system would seriously undermine the success of this One Council project. • There are financial advantages in maintaining frameworki – the avoidance of cost, both in terms of cash and officer resource time. Costs can be excessive and include the cost of the tendering process as well as the cost to build or set up a new system, which could be £500,000 as well as costs for implementation, training and migration costs for which there is no identified budget.
3.5Having determined that it is not in the Council’s interests to replace the existing frameworki system, Officers considered whether the existing system could be adequately maintained and supported by other organisations as Brent Council have a non-exclusive license to use frameworki in perpetuity under the terms and conditions of the original contract entered into on April 1st 2003.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.