Resolved
that the Design and Build Contract for the main works for The Village School be awarded to JB Leadbitter & Co Ltd, trading as Leadbitters , in the sum of £18,856,721.00.
Executive decided this item on Monday 23 May 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Design and Build Contract for the main works for The Village School be awarded to JB Leadbitter & Co Ltd, trading as Leadbitters , in the sum of £18,856,721.00.
1.1This report summarises the procurement process undertaken by the Council to procure a Design & Build contractor for the temporary accommodation at The Village School and provides an update on the award of the contract for the appointment of a Design & Build contractor for that temporary accommodation.
1.2This report also summarises the procurement process undertaken by the Council to procure a Design & Build contractor for the main works contract for The Village School and requests authority to award the contract for the appointment of a Design & Build contractor for this scheme.
1.3Finally a general update and overview of the project is provided which shows that all pieces are now in place to hand over a new Village School in September 2013.
2.1That the Executive awards the Design & Build Contract for the main works for The Village School to JB Leadbitter & Co Ltd, trading as Leadbitters, in the sum of £18,856,721.00.
Executive Meeting Version no.4 The Village School Date: 23 May 2011 Final draft: Date 12/05/11 3. Background
3.1The Executive, at their meeting of 15th March 2010, agreed to proposals to reorganise the hitherto separate Hay Lane and Grove Park special schools as one school with effect from 1st September 2010, to be known as The Village School.
3.2On 12 April 2010 the Executive approved the rebuilding of The Village School incorporating the existing recently completed 16+ Centre, a new Short Break Centre on site and the provision of the necessary temporary accommodation during the construction period on the site of adjacent Kingsbury High School. This decision was taken in part because of the poor condition of the former Hay Lane and Grove Park buildings and because rebuilding the schools as one school had been shown in the 26 May 2009 report to the Executive to be the most cost effective option for their improvement.
3.3The Village School is an all age special school located in Grove Park off Stag Lane in Kingsbury. The school caters for a wide range of special educational needs including profound and multiple learning difficulties, severe learning difficulties, autism with associated learning and behavioural difficulties and physical disabilities.
3.4The existing school buildings are facing major suitability and condition problems. Given the current state of the buildings it is becoming increasingly difficult for the Council to meet its statutory obligations towards these children.
3.5Due to the condition of the existing buildings The Village School will be unable to remain open on this site after July 2011 without significant upgrading (with the exception of the recently built post 16 building).
3.6On 12 April 2010 the Executive received a report from Children and Families requesting authority to procure a Design & Build contractor for two schemes:
3.6.1. Constructing the new Village School on the site of Hay Lane and Grove Park including a new Short Break Centre on the site and enabling works to the existing 16+ block so it can remain occupied during the works (The Village School – Main Scheme).
3.6.2. Constructing temporary accommodation for the Village School on the site of Kingsbury High School including a legacy for Kingsbury High School consisting of a new games area and a new classroom block (The Village School - Decant and Legacy Scheme).
3.7The Executive accordingly gave approval to proceed with two separate procurement processes for a Design & Build contractor for the main works contract and a separate Design & Build contractor for
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Development of SEN Provision at Hay Lane and Grove Park Sites -The Village School including award of Design and Build contractReport | 105 KB | DownloadRead as text |
PDF |
tvs-app1Report | 26 KB | Download |
PDF |
tvs-app2Report | 66 KB | Download |
PDF |
tvs-app5Report | 21 KB | Download |
PDF |
tvs-app6Report | 2.3 MB | Download |
Follow Executive at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2014 | Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... | Approved | Open |
| 16 Jun 2014 | Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... | Approved | Open |
| 16 Jun 2014 | Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... | Noted | Open |
| 16 Jun 2014 | Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... | Agreed | Open |
| 16 Jun 2014 | Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.