( i ) that the concerns about the existing tendering timetable set out in paragraphs 3.3 and 3.4 of the report from the Director of Environment and Neighbourhood Services and the potential for securing a better outcome through collaboration with West London Alliance partners set out in paragraphs 3.5 to 3.7 be noted; (ii) that the legal advice about the risks associated with extending the existing contract set out in paragraphs 5.1 to 5.4 be noted; (iii) that agreement be given to the extension of the parking enforcement and notice processing contracts with APCOA for a period of twelve months and that authority be delegated to the Director of Environment and Neighbourhood Services in consultation with the Director of Finance and Corporate Services and the Director of Legal and Procurement to agree the final terms of the extension; (iv) that agreement in principle be given to the revised approach to tendering the contracts collaboratively set out in paragraph 3.9 and 3.11 of the Director's report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report sets out current plans for re-tendering of Brent’s contracts for parking enforcement and notice processing. In light of concerns about the timing of the new contracts in relation to the 2012 Olympic Games, and fresh opportunities for collaboration in retendering which have arisen, recommends that the existing contracts be extended for a twelve month period.
Recommendations
2.1That the Executive note the concerns about the existing tendering timetable set out in paragraphs 3.3 and 3.4 and the potential for securing a better outcome through collaboration with West London Alliance partners set out in paragraphs 3.5 to 3.7.
2.2That the Executive note the legal advice about the risks associated with extending the existing contract set out in paragraphs 5.1 to 5.7.
2.3That the Executive agree the extension of the parking enforcement and notice processing contracts with APCOA for a period of twelve months and that authority be delegated to the Director of Environment & Neighbourhood Services in consultation with the Director of Finance & Corporate Services and the Director of Legal and Procurement to agree the final terms of the extension.
Meeting: Executive Version no.2.0 Date: 12 December 2011 2.4 That the Executive agree in principle the revised approach to tendering the contracts collaboratively set out in paragraph 3.9 and 3.11.
3. Detail
Present Plans for Re-tendering Brent’s Parking Contracts
3.1Following approval from The Executive on 18th July 2011, arrangements are presently being made to let parking services via two contracts, for a four year period (with an option to extend for up to a further four years) in two lots:
a) On street enforcement operation, including moving traffic contraventions, bus lane, fixed and mobile CCTV enforcement as well as off street car park enforcement. b) A “back office” notice processing function to include including provision of a management information system, statutory documents processing, permit administration system etc.
Two aspects are being tendered as discretionary options:
c) vehicle removal and car pound operation – the costs of such an operation are high, and as the majority of London authorities do not remove any vehicles, we are more closely examining the obligations, economics and practicalities of removals; and d) processing of fixed penalty notices(FPN) not related to parking enforcement, to bring efficiencies of scale to other non-parking types of FPN across the Council, such as for dumped waste etc.
3.2The OJEU notice was published on 5th September 2011 and invitation to tender is planned for December 2011. The decision to award the contracts is planned for the 12 March 2012 Executive meeting, with the new contracts starting on 4 July 2012.
Risks Associated with the 2012 Olympics and the Contract Start Up
3.3Detailed consideration of the risks associated with the planned process has identified a particular problem around the start-up period. The contracts are planned to commence on 4 July 2012, just three weeks before the start of the Olympic competition. Any failure in the parking service at this period could cause reputational damage to the borough. Issues are arising now which require joint planning with the contractor for the effective operation of the parking service during the Olympic period. These issues include securing sufficient trained Civil Enforcement Officers, planning deployment of people and other resources, and mitigating the risk of loss of staff to other Boroughs during the expected period of intense competition for experienced staff. Leaving this planning until the appointment of the new contractor in March 2012 will not be acceptable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.