( i ) that the Finance and Performance information contained in the from the Directors of Strategy, Performance and Improvement and Finance and Corporate Services report be noted and agreement given to remedial actions as necessary; (ii) that the current and future strategic risks associated with the information provided be noted and agreement given to the remedial actions as appropriate; (iii) that progress with responsible officers be challenged necessary; (iv) that agreement be given to the budget virements contained in the report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Report from Director of Strategy, Partnerships and Improvement and Director of Finance and Corporate Services Wards Affected: ALL
Performance and Finance Review, Quarter 2, 2011-12
1.0Introduction
Brent’s Borough Plan ‘Brent our Future’ is a four year strategy document which sets out the Administration’s priorities over the coming years. These priorities form the core of our Corporate Planning Framework, which is broadly based around three overarching strategic objectives:
1. To create a sustainable built environment that drives economic regeneration and reduces poverty, inequality and exclusion. 2. To provide excellent public services which enable people to achieve their full potential, promote community cohesion and improve our quality of life. 3. To improve services for residents by working with our partners to deliver local priorities more effectively and achieve greater value for money from public resources.
The unprecedented 28% reduction in central government funding over the next four years continues to intensify pressure on Council services, and difficult economic conditions have directly affected levels of employment across the borough. The scale and pace of national policy changes, particularly in relation to Housing Benefits and the implementation of the new Universal Credit, is expected to fuel increased demand for services, which will have an enduring effect on the borough. However despite these challenges, the Council remains committed to preserving services and protecting the most vulnerable residents.
The purpose of this report is to provide Members with a corporate overview of Finance and Performance information to support informed decision-making and manage performance effectively.
Page 1 of 4 2.0 Recommendations
The Executive is asked to:
a. Note the Finance and Performance information contained in this report and agree remedial actions as necessary. b. Consider the current and future strategic risks associated with the information provided and agree remedial actions as appropriate. c. Challenge progress with responsible officers as necessary. d. Agree the budget virements contained in the report.
3.0Executive Summary - FINANCE
3.1The Council’s revenue budget position for the quarter 2 is as follows:
Forecast Item Budget Outturn Variance £000 £000 £000 Adult Social Services 91,973 92,471 498 Children & Families 56,724 56,840 116 Environment & Neighbourhood 39,953 40,135 182 Services Regeneration & Major Projects 26,579 26,578 (1) Finance & Corporate Services / 28,207 28,694 487 Central Services Service Area Total 243,436 244,718 1,282 Central Items 21,953 22,448 495 Total Council Budget 265,389 267,166 1,777
• The Council is currently forecasting an over-spend of £1.777m an increase of £483k from the quarter 1 figure of £1.294, primarily due to emerging pressures in two areas.
• Environment Neighbourhood Services are now forecasting an overspend of £182k as a result of pressures on the library budget which will be exacerbated by the delays in the library closure programme from the judicial review and appeal court hearing. Shortfalls of income over a number of services are also contributing to the overspend.
• Central Services are now forecasting an overspend of £487k due to income shortfalls from design work and payroll services to schools, as well as additional pressures on the Procurement Team.
• Overall the main overspending pressures remain with adult social care transitions (£900k), children’s social care legal costs (£830k) and the temporary accommodation budget (£1m).
• The majority of these demand costs are currently being met by a centrally held provision of £2m although potential claims currently exceed this by £500k. Page 2 of 4 • Service areas are currently in the process of putting together plans to eliminate their current overspends by the end of the year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.