( i ) that the progress being made on delivery of a successful Olympics in the Borough be noted; (ii) that agreement be given to Brent providing mutual aid as appropriate to other boroughs once position is clarified; (iii) that services work closely with Police and health professionals to deliver safe events within the borough; (iv) that it be noted that it has been agreed to allow staff affected by the 2012/13 leave restrictions, the ability to sell 10 days annual leave back to the council during 2012/13.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report provides an update on the 2012 Games and progress to date in ensuring successful delivery within Brent.
Recommendations
2.1The Executive are asked to note the progress being made on delivery of a successful Olympics in the Borough.
2.2To agree to Brent providing mutual aid as appropriate to other boroughs once position is clarified.
2.3To agree that services work closely with Police and health professionals to deliver safe events within the borough.
2.4To note that it has been agreed to allow staff affected by the 2012/13 leave restrictions, the ability to sell 10 days annual leave back to the council during 2012/13.
3.0Detail
Background
3.1The London 2012 Games will have a significant impact on Brent as Wembley Stadium will be hosting the women’s and men’s football semi finals and finals whilst Wembley Arena will be used as the venue for badminton and rhythmic gymnastics.
Executive Version No. 2 12 March 2012 29 February 2012 As such, Brent is a ‘host borough’ for London 2012 and is working closely with the London Organising Committee of the Olympic and Paralympic Games (LOCOG), the Olympic Delivery Authority (ODA), the Government Olympic Executive (GOE) and the Greater London Authority (GLA) to ensure the safe and successful delivery of the Games as well as encouraging community participation and a Games legacy.
3.2Events at the Stadium and Arena will take place from the 28 July to 12 August 2012 (Appendix 1 - event schedule). Brent will be operational as a host borough from May – September 2012 to coincide with the start of the Torch Relay in the UK and the closure of the Media Centre at the end of the Games period. Brent is not hosting any Paralympic sporting events.
Borough Operational Plan
3.3Being a host borough will bring significant opportunities for the Borough however, on an operational level it will have a considerable impact on a number of Council services. Brent has been successful in securing financial assistance (£700,000) from GOE towards the costs of services which are additional to usual service operations and which are critical to operating a safe and effective Olympic Games in Brent. These include: • waste management and street cleaning • event licensing/stadium safety certification • trading standards • environmental health • augmented safety advisory group development and delivery • emergency planning and control centre reporting • Borough Grouping Support Unit (BGSU) • communications with residents
3.4In order to secure the funding the Council had to first develop a Borough Operational Plan. The plan was developed by the 2012 Manager together with relevant service areas and details the operations above and financial expenditure against these. Brent Council’s performance will be monitored against this plan and grant payment will be linked to delivery.
3.5The updated version of the plan and financial profile was submitted to GLA (programme managers on behalf of GOE) on the 13 January 2012. Two instalments of the grant have already been paid with further payments due in April and December 2012. E&NS Strategic Finance and the 2012 Manager are working with all services to ensure there is a clear audit process.
City Operations
3.6City operations is the name used to describe borough-run essential public services which will have a significant impact on the successful delivery of the Games at a local level. The services are financially supported by the Borough Operational Plan detailed above. Paragraphs 3.7 to 3.36 outline the key work areas within the plan.
Executive Version No. 2 12 March 2012 29 February 2012 C3 Issues and BGSU
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.