( i ) that the current and future demand for primary school places as set out in Section 3 of the report from the Directors of Regeneration and Major Projects and Children and Families be noted; (ii) that approval be given to the allocation of £1.35m from the Council’s Main Capital Programme for providing additional primary ‘bulge’ classes places across Brent schools from September 2012; (iii) that approval be given to the list of school and non-school based schemes listed in Appendix 1 of the report for providing temporary primary provision, subject to due diligence completed by the Council and agreement with the school; (iv) that agreement be given to the prioritised use of properties listed under Table 9 in Appendix 1 for the purpose of providing temporary primary provision. (v) that authority be delegated to the Director of Regeneration and Major Projects and Director of Children and Families in conjunction with the Lead Member of Regeneration and Major Projects to substitute a scheme with another if any of the proposed schemes in Appendix 1 are not feasible, subject to due diligence completed by the Council and agreement with the school. (vi) that authority be delegated to the Director of Regeneration and Major Projects to appoint one or more works contractors using existing construction frameworks, for the recommended temporary school expansion schemes referred to in paragraph (iii) above.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1Demand for primary school places has been exceeding the supply of places over each of the last three years, and this gap is forecast to widen over the next ten years. The forecast shortage reported to Executive in August 2011 is equivalent to 15 new forms of entry. On the basis of GLA projections, a requirement for 4,224 reception places by 2020 is estimated, leading to a shortage of 692 reception places (or 23 new forms of entry) over the entire period. All this demand in the primary sector is forecast to lead to increased pressures on secondary school capacity from 2014/15.
1.2The Council has a limited budget which is not sufficient to meet the total demand for primary school places. In 2009 the government allocated Brent Council £14.766m toward construction of new primary places, which has been spent on schemes such as, Preston Manor Lower School (2FE), Brentfield Primary (1FE), Newfield Primary (1FE), Park Lane (1FE), Byron Court (0.3FE).
1.3In October 2011, the Department for Education (DfE) allocated Brent Council a one off allocation of £24.815m in recognition of the urgent need for school places, plus a Basic Need Allocation for 2012/13 of £24.092m. There is also funding available from section 106 contributions.
1.4The August 2011 Executive report has already allocated a total of £15.507m (subject to Executive and Full Council approval) in the capital programme for the Provision of School Expansions in 2012/13 to meet the costs of the next phase of expansion schemes. This includes a sum of £2.440m for temporary expansions.
1 1.5 Despite the levels of funding available, there is still a considerable mismatch between these sums and the funding required to deliver the additional school places. The council is actively engaged in lobbying the government for additional resources. There are additional resources available to new free schools and academies over and above the resources given to Councils.
1.6This report considers approaches to reducing the supply and demand mismatch in relation to school places, sets out ways of maximising investment into the school portfolio from 2013/14 to address this issue, and proposes specific schools and sites for investment to meet demand from the beginning of the 2012/13 academic year.
Recommendations
The Executive is requested to:
2.1Note the current and future demand for primary school places as set out in Section 3 of this report.
2.2To approve the allocation of £1.35m from the Council’s Main Capital Programme for providing additional primary ‘bulge’ classes places across Brent schools from September 2012.
2.3To approve the list of school and non-school based schemes listed in Appendix 1 of this report for providing temporary primary provision, subject to due diligence completed by the Council and agreement with the school.
2.4To allow prioritised use of properties listed under Table 9 in Appendix 1for the purpose of providing temporary primary provision.
2.5To delegate authority to the Director of Regeneration and Major Projects and Director of Children and Families in conjunction with the Lead Member of Regeneration and Major Projects to substitute a scheme with another if any of the proposed schemes in Appendix 1 are not feasible, subject to due diligence completed by the Council and agreement with the school.
2.6To delegate authority to the Director of Regeneration and Major Projects to appoint one or more works contractors using existing construction frameworks, for the recommended temporary school expansion schemes referred to in paragraph 2.3.
3.0Demand Analysis
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.