( i ) that approval be given to the pre-tender considerations and the criteria to be used to evaluate tenders for the Furniture, Furnishings and Equipment for the Civic Centre as set out in paragraph 3.5 of the report from the Chief Executive; (ii) that officers to invite tenders for the Furniture, Furnishings and Equipment in accordance with European procurement regulations using the Restricted Procedure and evaluate them on the basis and in accordance with the approved evaluation criteria referred to in paragraph 3.5 of the Director’s report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report follows the report to Executive in October 2010 where Members agreed to award the contract for the Design & Build contractor for the Civic Centre. As previously reported to Executive in October 2009, the contracts for the construction and fit out of the Civic Centre would remain separate. This report now requests approval to tender for the Furniture, Furnishings and Equipment (FFE) for the Civic Centre.
Recommendations
2.1The Executive to give approval to the pre-tender considerations and the criteria to be used to evaluate tenders for the Furniture, Furnishings and Equipment for the Civic Centre as set out in paragraph 3.5.
2.2The Executive to give approval to officers to invite tenders for the Furniture, Furnishings and Equipment in accordance with European procurement regulations using the Restricted Procedure and to evaluate them on the basis and in accordance with the approved evaluation criteria referred to in paragraph 3.5.
3.0Detail
3.1Following the approval from Executive in October 2009 to procure the design and build contractor for the Civic Centre, Skanska Construction UK were
Meeting Version no. Date Date appointed. Construction started in November 2010 and practical completion and handover of the building is on programme for December 2012. On handover, there will be a three month fit out period before occupation. Fit out will encompass furniture delivery, assembly and installation of all items described in paragraph 3.5.
3.2Sufficient FFE will be procured to enable 2300 people to work from the Civic Centre. The FFE will allow the council to run the range of activities in all the public and democratic areas to meet service needs but also cater for a significant number of community and corporate events.
3.3The FFE for the building will be procured using the EU restricted procurement route, following a two stage process. Some specialist joinery items will be procured separately due to the specialist nature of the products.
3.4An ergonomist has been appointed to provide support to the procurement process to ensure national ergonomic standards are met.
3.5In accordance with Contract Standing Orders 88 and 89, pre-tender considerations have been set out below for the approval of the Executive.
Ref. Requirement Response (i) The nature of the Furniture, Furnishings & Equipment contracts for the fit service. out of the Civic Centre. Lot 1: Workstation Desks, Storage and Lockers Lot 2: Loose Furniture for Administration Areas Lot 3: Loose Furniture for Public and Democratic Areas Lot 4: Specialist Furniture for Conference Rooms and Civic Hall Lot 5: Workstation Chairs (ii) The estimated £2.4m - £3m value. (iii) The contract • Appointment and manufacture prior to practical term. completion of the building • Fit out • End date: July 2013 (iv) The tender EU Restricted Procedure. The lots will be advertised procedure to be under one notice which will allow potential tenderers to adopted bid for one or more lots. Consortia bids will be allowed. Tenderers will be required to submit a fixed price based on schedule of quantities. (v) The procurement Indicative dates are: timetable. Trade adverts and OJEU contract notice April 2012 placed
Expressions of interest returned May 2012
Shortlist drawn up in accordance with June 2012
Meeting Version no. Date Date the Council’s approved criteria
Invite to tender June 2012
Deadline for tender submissions July 2012
Panel evaluation and interviews July/August 2012
Conclusion of Panel assessment August 2012
Executive approval to award contract September/ October 2012
Mandatory minimum 10 calendar day September/ standstill period – notification issued to October all tenderers and additional debriefing of 2012 unsuccessful tenderers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.