( i ) that the Furniture, Furnishings & Equipment contracts to the organisations named in Appendix 2 for the following Lots be awarded as follows: Lot 1: Workstation Desks, Storage and Lockers Lot 2: Loose Furniture for Administration Areas Lot 3: Loose Furniture for Public and Democratic Areas Lot 4: Specialist Furniture for Conference Rooms and Civic Hall Lot 5: Workstation Chairs (ii) that the Assistant Director Major Projects and Civic Centre with the Director of Legal and Procurement be authorised to finalise the terms of appointment.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests authority to award contracts as required by Contracts Standing Order 88. This report summarises the procurement process undertaken by the Council to procure the Furniture, Furnishings & Equipment (FFE) for the new Civic Centre and recommends to whom contracts should be awarded.
Recommendations
2.1That the Executive awards the Furniture, Furnishings & Equipment contracts to the organisations named in Appendix 2 for the following Lots:
Lot 1: Workstation Desks, Storage and Lockers
Lot 2: Loose Furniture for Administration Areas
Lot 3: Loose Furniture for Public and Democratic Areas
Lot 4: Specialist Furniture for Conference Rooms and Civic Hall
Lot 5: Workstation Chairs
2.2That the Assistant Director Major Projects & Civic Centre with the Director of Legal and Procurement be authorised to finalise the terms of appointment. 3.0 Background
3.1On 23 April 2012 the Executive received a report from the Chief Executive requesting authority to procure the Furniture, Furnishings & Equipment (FFE). The Executive accordingly gave approval to procure the FFE and approved pre-tender issues as required by the Council’s Contract Standing Orders 88 and 89, including the evaluation criteria.
The Tender Process and Council’s Contract Standing Orders
3.2The FFE has been procured using the Restricted Procedure in accordance with the EC Directive 2004/18 (the Classic Directive), the Public Contracts Regulations 2006 (the Regulations) and the Council's Contract Standing Orders and Financial Regulations.
Stage One - Pre – Qualifying Stage
3.3On 27 April 2012 the contract notice was placed in the Official Journal of the European Union (OJEU) to seek initial expressions of interest. The notice specified the Council’s requirement to procure a range of furniture types for the Civic Centre under 5 different Lots detailed at paragraph 2.1.
3.4Tenderers were advised variant tenders would not be accepted.
3.5Seventy-two organisations expressed an interest in response to the OJEU notice and they were issued with an information pack and pre- qualification questionnaire (PQQ) to complete by 12 noon on 24 May 2012. Thirty PQQs were returned in accordance with the deadline.
3.6The following assessment process was followed to decide pre- qualification:
Stage 1: All applicants were initially assessed against the PASS/ FAIL criteria to filter out non-compliant tenders. These were agreed at a joint workshop with procurement adviser present.
Stage 2: Individual scoring on the relevant sections of the PQQ was undertaken by the assessment team.
Stage 3: This involved a group review of the collated scores. The final score for each prospective bidder was achieved by consensus with procurement adviser present.
Stage 4: A recommendation on the short listed prospective bidders was prepared for approval by the Civic Centre Programme Board. It had been determined that for Lot 1, the top 6 scoring providers would be invited to tender. For Lots 2-5, it was determined that the top 8 scoring providers would be invited to tender. 3.7 Due to a number of organisations tendering for more than 1 Lot, eleven different organisations that had scored the highest for the various Lots (in accordance with the methodology detailed at paragraph 3.6) out of the thirty organisations that had responded to the PQQ were then invited to tender.
Stage Two – Invitation to Tender
3.8An ITT pack was issued to the eleven organisations to invite them to tender. The tendering instructions stated that the contracts would be awarded on the basis of the most economically advantageous tender to the Council and that in evaluating the tenders the Council would use the evaluation criteria set out in the Evaluation Matrix at Appendix 1 of this report. Overall 50% of the marks were awarded for price and 50% for quality.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.