Authority to allocate Main Capital Programme Funding for the expansion of Vicar's Green Primary School

Approved Executive 1 paper

Executive approved this item on Monday 14 January 2013. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

( i ) that approval be given to the funding by Brent Council of £2m, together with a contingency of £0.5m, towards London Borough of Ealing’s school expansion project at Vicar’s Green Primary School; (ii) that the comments from the Director of Legal and Procurement in Section 5 relating to the involvement with the neighbouring borough of Ealing be noted and authority be delegated to the Director of Regeneration and Major Projects in consultation with the Lead Member for Regeneration and Major Projects to approve the funding agreement with Ealing Council on finalisation of the terms for the expansion of Vicar’s Green Primary School from September 2014; (iii) that all Brent Council funding be subject to a legal agreement between the Council and Ealing Council setting out that: (a) The Council funding contributions can only be spent on legitimate education facilities, as defined in government guidance, and not on ancillary facilities that form part of the project; (b) Full and proper governance arrangements are established for the project to ensure it is delivered to time and budget, and providing for a senior Brent Council officer representation on the project board. (iv) that approval be given to the allocation of £2m from the main capital programme in line with the approved August 2012 Executive Report to fund fifty per cent of the cost of the school expansion project in partnership with Ealing Council; (v) that the contingency of £0.5m be maintained to cover unforeseen project costs since the design stage has not commenced and cost are an estimate at this stage.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Executive

Summary

1.1This report requests Executive approval to Brent Council providing funding to the London Borough of Ealing for the expansion of Vicar’s Green Primary school by 1 form of entry. 15 out of the 30 places in the new form of entry are expected to be taken up by Brent children. Accordingly, a consultation will commence in January 2013 to expand the catchment area for admissions to include Brent residential areas.

1.2Expansion of Vicar’s Green Primary School forms part of the School Expansion Programme 2012-16 report approved by the Executive in August 2012.

1.3The total project cost for the expansion is estimated at £4m including consultant fee of which Brent Council will contribute in equal proportion in partnership with Ealing Council.

1.4The building works contract will be between Ealing Council and the contractor, for which the procurement process will be completed by Ealing Council.

1.5Brent contribution totalling to £2m plus a contingency of £0.5m will be funded from the mainstream schools capital programme, which formed part of the August 2012 Executive report titled ‘School Expansion Programme 2012-16’.

Recommendations

The Executive is recommended:

2.1To approve the funding by Brent Council of £2m, together with a contingency of £0.5m, towards London Borough of Ealing’s school expansion project at Vicar’s Green Primary School. Page 1 of 16 2.2 To note the comments of the Director of Legal & Procurement in Section 5 and delegate authority to the Director of Regeneration & Major Projects in consultation with the Lead Member for Regeneration & Major Projects to approve the funding agreement with Ealing Council on finalisation of the terms for the expansion of Vicar’s Green Primary School from September 2014.

2.3To agree that all Brent Council funding is subject to a legal agreement between the Council and Ealing Council setting out that:

(i) The Council funding contributions can only be spent on legitimate education facilities, as defined in government guidance, and not on ancillary facilities that form part of the project; (ii) Full and proper governance arrangements are established for the project to ensure it is delivered to time and budget, and providing for a senior Brent Council officer representation on the project board.

2.4To approve the allocation of £2m from the main capital programme in line with the approved August 2012 Executive Report to fund fifty percent of the cost of the school expansion project in partnership with Ealing Council.

2.5To approve the contingency of £0.5m to be maintained to cover unforeseen project costs since the design stage has not commenced and cost are an estimate at this stage.

3.0Detail

Proposed Scheme

3.1In August 2012, Brent Council Executive approved the School Expansion Programme 2012-16, which included the proposed expansion of Vicar’s Green Primary School, located in Ealing near the Brent borough boundary (refer to Appendix 4 for a location map). The scheme is supported by the West London Alliance (WLA).

3.2During its last inspection in June 2008, Ofsted inspectors judged Vicar's Green Primary School to be good. The interim assessment carried out by Ofsted on 7 January 2011 noted that the school’s performance has been sustained. In the 2012 SATs 89% of pupils achieved level 4 or above in Maths and English. Ealing Council's school improvement team does not have any concerns about the school's standards or capacity for successful expansion.

‘Bulge’ Class

3.3As a proof of concept, both Council’s have successfully worked together in order to provide a ‘bulge’ Reception class from September 2012. The provision commenced on time for which the admission process was managed by Ealing Council. The number on roll at the commencement of term for the Reception class was 60, out of which 30 were Brent pupils.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Authority to allocate Main Capital Programme Funding for the expansion of Vicar's Green Primary SchoolReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
MB
Councillor Muhammed ButtChair, present
RM
Councillor Ruth MoherVice-Chair, present
MA
Councillor Mary ArnoldCommittee Member, present
LB
Councillor Lincoln Beswick MBECommittee Member, apologies
GC
Councillor George CraneCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present
JM
Councillor Jim MoherCommittee Member, present
JP
Councillor James PowneyCommittee Member, present
EA
Councillor Emad Al-EbadiCommittee Member, in attendance
BC
Councillor Barry CheeseCommittee Member, in attendance

All 21 on the meeting page

On this subject at Brent

Search all
  1. Authority to allocate Main Capital Programme Funding for the expansion of Vicar's Green Primary SchoolThis decision
  2. Authority to allocate primary capital programme funding and approve the award of a construction contract for the rebuild of Islamia Primary SchoolApproved

More from Brent Executive

All decisions
MeetingDecisionOutcome
16 Jun 2014 Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... Approved Open
16 Jun 2014 Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... Approved Open
16 Jun 2014 Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... Noted Open
16 Jun 2014 Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... Agreed Open
16 Jun 2014 Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies