( i ) that the current and future demand for secondary school places as set out in paragraphs 5.8 to 5.13 of the report from the Directors of Regeneration and Major Projects and of Children and Families be noted; (ii) that approval be given to the strategy for the delivery of secondary school places as set out in paragraphs 5.15 to 5.29 of the report, subject to availability of funds.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1In August 2012 the Executive approved the strategy for a primary school expansion programme 2012-16. This report sets out the strategy for meeting the projected shortfall of secondary school places in Brent from September 2014. It also includes an update on meeting the demand for SEN provision.
1.2As detailed in the August 2012 report, a shortfall in funding of £82m for providing new school places has been identified. This report reviews the options available to Brent to meet the budget deficit.
1.3According to the current roll projections, by 2020-21 Brent would require 21FE additional primary places, up to 19FE secondary places and 192 new SEN places. A portfolio review of Brent’s secondary estate has been completed, which underpins the Council’s strategy for developing new secondary provision. A report on SEN regarding the development of new SEN provision will follow in February 2013.
Recommendations
The Executive is requested to:
2.1Note the current and future demand for secondary school places as set out in paragraphs 5.8 to 5.13 of this report.
2.2Agree the strategy for the delivery of secondary school places as set out in paragraphs 5.15 to 5.29 of this report, subject to availability of funds.
3.0Background and purpose
1 3.1 In August 2012, the Executive agreed the expansion strategy to meet the need for primary schools places in Brent. The report also highlighted a need for up to19FE secondary provision commencing September 2014/15 academic year.
3.2As stated in the primary report, the Council has developed a four year strategy under the School Expansion Programme 2012-16 taking into account the supply and demand mismatch, and the limited resource envelope available to the Council. This includes:
• delivering the permanent expansion schemes currently underway through the rebuild of the Crest Boys’ Academy and Crest Girls’ Academy
• initiating a programme of temporary provision to increase secondary capacity from September 2014
• as is the case with the primary programme, adopting a ‘rolling programme’ approach to secondary school expansion based on corresponding demand underpinned by innovation, streamlining construction cost and improved project management
• continuing to lobby government for the additional resources required to meet our statutory obligations.
4.0Capital Allocation
4.1In August 2012, we reported that the Council had received three allocations totalling £79.7m. The total uncommitted main capital allocation, including that which will be available to spend by the end of 2015-16 on new school places, is £85.16m, (including new and balance of prior year grant allocations.) In addition, the Section 106 contribution by end of 2014/15 will equal £7.14m. The total combined capital available for school places is expected to be £92.3m, which has in principal been allocated to the primary school expansion programme. The funding position as stated in the August 2012 Executive report is listed in Appendix 1.
4.2The above allocations are insufficient to meet the entire need for school places. In total, the Council would require £174.31m based on the current cost of school expansion projects if it is to meet in full the current demand until 2020-21. With a forecast budget of £92.3m, this would indicate a net capital deficit of £82.0m. The Education Funding Agency is expected to make the announcement on the grant allocation for the financial year 2013-14 in January 2013.
4.3The Council has maintained an on-going lobbying campaign, in conjunction with London Councils, to highlight the school places pressure across London and those particular to Brent; although it is highly unlikely that the next round of allocations will meet the Council’s forecast shortfall in funding. We have also noted that there is a lag between the availability of new funding and the building of new school provision.
Alternative Routes of Funding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.