Granted planning permission subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning or other duly authorised person to agree the exact terms thereof on advice from the Director of Legal Services and Procurement.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
This map is indicative only. RECEIVED: 6 March, 2013
WARD: Tokyngton
PLANNING AREA: Wembley Consultative Forum
LOCATION: PORTLAND HOUSE, 69-71 Wembley Hill Road, Wembley, HA9 8BE
PROPOSAL: Demolition of existing office building and the erection of a new part 4 and part 5-storey office building with associated off-street parking.
APPLICANT: Solai Services Ltd
CONTACT: Martin Robeson Planning Practice
PLAN NO'S: (See Condition 2 for the approved plans) __________________________________________________________ RECOMMENDATION Grant planning permission subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning or other duly authorised person to agree the exact terms thereof on advice from the Director of Legal Services and Procurement.
SECTION 106 DETAILS The application requires a Section 106 Agreement, in order to secure the following benefits:-
· Payment of the Council's legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance · A contribution of £24,750 for Sustainable Transportation in the local area, Environmental & Sports improvements in the local area (based on £25sqm and calculated on the net increase in floorspace). · Sustainability - submission and compliance with the TP6 Sustainability check-list to ensure a minimum score of 50%, and 1 month prior to a material start the submission of a detailed BREEAM assessment which demonstrates reasonable endeavours to achieve ‘Excellent’ rating, with compensation should either not be delivered. In addition to adhering to the Demolition Protocol. · No later than 1 month prior to a material start submission of a revised Energy Strategy to demonstrate that the maximum feasible carbon reduction target will be met on-site. Where it is clearly demonstrated that specific targets cannot be fully achieved on-site, any shortfall may be provided off-site, or an in lieu contribution to secure delivery of carbon dioxide savings elsewhere. · Join Considerate Constructors Scheme. · Upon first occupation to fully implement revised Travel Plan (draft5).
And, to authorise the Head of Area Planning, or other duly authorised person, to refuse planning permission if the applicant has failed to demonstrate the ability to provide for the above terms and meet the policies of the Unitary Development Plan and Section 106 Planning Obligations Supplementary Planning Document by concluding an appropriate agreement.
This application is liable for Community Infrastructure Levy.(CIL) . The Mayor's contribution would be £34,650.00.
EXISTING Portland House is a 3-storey rendered office building, situated on a corner plot at the junction of Dagmar Avenue and Wembley Hill Road. It comprises 463sqm of floorspace. Neighbouring buildings to the north and west of the site are residential, and south of the site on the opposite corner of Dagmar Avenue and Wembley Hill Road is a near identical office building. It would appear these office buildings were built as a pair.
Vehicle access to two separate parking levels to the rear of the building is gained via Dagmar Avenue. These two parking areas are separated by a single storey garage building.
The site is within the identified Wembley Growth Area, and the area which is designated by the Wembley Area Action Plan (WAAP). It is mixed in character being situated at the interface of commercial buildings along Wembley Hill Road and residential dwellings.
Public realm improvements have recently been carried out to the front of the site as part of the works that have replaced the Wembley Hill Road gyratory system with a roundabout. This has created a new civic green, public space.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.