( i ) that provided the site is deemed suitable for affordable housing development by BHP or another internal use (such as social care – on a spend to save basis), then subject to further review of the powers under which the land is held, that the District Valuer be appointed to ascertain a transfer value, to the HRA or another portfolio as appropriate; (ii) that if an internal use cannot be identified, to agree that the site be prepared for disposal so marketing can start and therefore approve the disposal of the former Children’s Respite Care Centre and adjacent site at Clements Close, Willesden Green, NW6 7JL shown shaded red and verged blue on the site plan at Appendix 2, with access via Clement Close. The capital receipt estimate is in excess of £750,000+ or such transfer value as determined by the District Valuer ; (iii) that authority be delegated to the Operational Director Property and Projects, to agree the detailed terms of the transaction in conjunction with the Director of Finance and Corporate Services; (iv) t hat the capital receipt be apportioned between the two construction projects, previously identified, namely the Village School New Build and Ashley Gardens Refurbishment with any surplus capital being taken as a contribution toward the Council’s Capital Programme; (v) The porta -cabin located on the BHP managed part of the site will to be re-located elsewhere within the Clement Close estate following consultation with BHP and local residents.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The subject land comprises the former Children’s Respite Care Centre and adjacent site at Clements Close, Willesden Green, NW6 7JL. Both are owned freehold by the Council with the adjacent land forming an under–utilised part of the Clement Close estate managed by Brent Housing Partnership (BHP). See Appendix 1 for site photos.
1.2This report sets out proposals to offer a combined development site for disposal, recommending Executive approval to proposals.
1.3The capital receipt generated from the sale of the former Children’s Respite Care Centre of £410,000 is earmarked towards the Village School.
1.4As the proposal comprises an area managed by BHP the paper asks the Executive to note the reduction in that area and the relocation of the porta-cabin used by the local residents association elsewhere within the Clement Close estate.
1.5The Executive is requested to note the disposal of the area managed by BHP will fund the Ashley Gardens Pavilion refurbishment this is a variation to the capital programme amendment reported to the Executive on 11th February 2013.
1.6This report recommended the forward funding of enabling works up to £300,000 that would be funded by the disposal of the Douglas Avenue Resource Centre with anticipated receipts in the order of £400,000.
Meeting Version no. Date Date 1.7 Children and Families propose to use the Douglas Avenue Resource Centre for temporary classes from September 2013 and will be presenting a proposal recommending the same.
Recommendations
That the Executive approve:
2.1That provided the site is deemed suitable for affordable housing development by BHP or another internal use (such as social care – on a spend to save basis), then subject to further review of the powers under which the land is held, that the District Valuer be appointed to ascertain a transfer value, to the HRA or another portfolio as appropriate.
2.2That if an internal use cannot be identified, to agree that the site be prepared for disposal so marketing can start and therefore approve the disposal of the former Children’s Respite Care Centre and adjacent site at Clements Close, Willesden Green, NW6 7JL shown shaded red and verged blue on the site plan at Appendix 2, with access via Clement Close. The capital receipt estimate is in excess of £750,000+ or such transfer value as determined by the District Valuer.
2.3To provide delegated authority to the Operational Director Property and Projects, to agree the detailed terms of the transaction in conjunction with the Director of Finance and Corporate Services.
2.4That the capital receipt be apportioned between the two construction projects, previously identified, namely the Village School New Build and Ashley Gardens Refurbishment with any surplus capital being taken as a contribution toward the Council’s Capital Programme.
2.5The porta-cabin located on the BHP managed part of the site will to be re- located elsewhere within the Clement Close estate following consultation with BHP and local residents.
3.0Detail
Background
3.1The former Children’s Respite Care Centre is located to the rear of and serviced via the Clement Close estate situated to the south of the Borough in the relatively prosperous Brondesbury Park area and backs onto Queens Park Community School to the south.
3.2The property was decommissioned in January 2013 following relocation of services from what was a small Respite Centre to the recently completed purpose built Short-break Centre at the Village School, Grove Park which will allow the Council to support modern high quality service delivery. The property is currently vacant and secured by guardians at no net cost to the council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.