( i ) that approval be given to the use of the former respite care centre at 1 Clement Close and adjacent lands, London NW6 7AL (the “Clement Close Site”) as adult social care provision for clients with learning disabilities; (ii) that approval be given to an exemption from the procurement requirements of Contract Standing Orders and the delegation of authority to the Operational Director of Property and Projects in consultation with the Director of Legal and Procurement to agree the terms and enter into a development agreement with Brent Housing Partnership to develop the Clement Close Site as detailed in the ‘development delivery’ section in the report; (iii) that approval be given the total scheme development costs within the range of £2,604,147 (10 homes) to £3,334,017 (14 home); (iv) that approval be given to capital funding comprising of grant funding contributions from the Greater London Authority Mayor’s Housing Covenant 2015-18 from £430,000 (10 homes) to £620,000 (14 homes), £510k from the Adults Social Care capital budget allocation of £1.8m and unsupported prudential borrowing of £1,664,147 (10 homes) to £2,204,017 (14 homes).
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1On 15th July 2013 the Executive approved that the former respite care centre at 1 Clement Close, together with adjacent lands, be considered for an ‘internal’ use such as general needs housing development under the housing revenue account (HRA) or adult social care (ASC) provision. It was agreed that if a transfer between portfolios was deemed necessary to facilitate this, then the district valuer be appointed to ascertain the appropriate transfer price.
1.2This report reviews the options for a use that supports the delivery of the Borough Plan and brings forward proposals for the subject site to be used as adult social care provision for clients with learning disabilities.
1.3This report seeks approval for an exemption to the tendering requirements of Contract Standing Orders and delegation of powers to officers to agree the terms and enter into a development agreement with Brent Housing Partnership (BHP) to develop the subject site.
Recommendations
The Cabinet:
2.1To agree to use the former respite care centre at 1 Clement Close and adjacent lands, London NW6 7AL (the “Clement Close Site”) as adult social care provision for clients with learning disabilities.
2.2To approve an exemption from the procurement requirements of Contract Standing Orders and delegate authority to the Operational Director of Property and Projects in consultation with the Director of Legal and Procurement to
Meeting Version no. Date Date agree the terms and enter into a development agreement with Brent Housing Partnership to develop the Clement Close Site as detailed in the ‘development delivery’ section in this report.
2.3To approve total scheme development costs within the range of £2,604,147 (10 homes) to £3,334,017 (14 home).
2.4To approve capital funding comprising of grant funding contributions from the Greater London Authority Mayor’s Housing Covenant 2015-18 from £430,000 (10 homes) to £620,000 (14 homes), £510k from the Adults Social Care capital budget allocation of £1.8m and unsupported prudential borrowing of £1,664,147 (10 homes) to £2,204,017 (14 homes).
3.0Detail
3.1The Clement Close site comprises the former Children’s Respite Care Centre and adjacent land at Clement Close, Willesden Green, NW6 7JL. Both parts of the Clement Close site are within the freehold ownership of the Council, with the adjacent land forming an under-utilised part of the Clement Close estate managed by BHP, (see Appendix 1 and 2).
3.2On 15th July 2013 the Executive approved that ‘provided the site is deemed suitable for affordable housing development by Brent Housing Partnership (under the Housing Revenue Account) or another internal use (such as social care – on a spend to save basis), then subject to further review of the powers under which the land is held, that the District Valuer be appointed to ascertain a transfer value, to the HRA or another portfolio as appropriate.’
3.3In 2013 marketing agents reported a £1.5m value which in June 2014 had increased to £1.8m, the figures quoted are far in excess of the £750,000 reported in Executive report in July 2013 which were based on an estimate by an internal Chartered Surveyor.
Corporate use options
3.4As per the decision made in July 2013, various corporate uses for the Clement Close site have been considered, in line with priorities set out in the Borough and Corporate Plan. The site is considered too small for a school use and so the main focus has been on considering the various residential options.
3.5Two broad options have been explored – utilising the site for general needs housing in line with the agreed (HRA) asset management strategy; and utilising the site for independent living for social care clients in line with the priorities set out in the Adult Social Care Market Position Statement 2014.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.