South Kilburn Regeneration Decentralised Energy Project

Noted Executive 4 papers

Executive noted this item on Monday 11 November 2013. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

( i ) that the progress made on the South Kilburn Decentralised Energy System Project be noted; (ii) that approval be given tp the Strategic Director of Regeneration and Growth to undertake a competitive procurement procedure (similar to the Competitive Dialogue procedure (as set out in the Public Contracts Regulations 2006) to procure an Energy Supply Company (‘ ESCo ’) to deliver the Project; (iii) that approval be given to the evaluation criteria as set out in this report which will form the basis for evaluation of the bids and the ultimate selection of the ESCo to deliver the Project. Further, that the Executive approves the Strategic Director of Regeneration and Growth to develop the detailed evaluation methodology and respective weightings to be applied to the evaluation criteria, within the parameters of the evaluation criteria set out in this report, prior to recommencement of the procurement process. (iv) that a consultancy contract be awarded to to Parsons Brinckerhoff Ltd to project manage the delivery of the project, advise on and provide commercial and strategic financial advice in respect of the project.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Executive

Summary

1.1This report concerns the proposed procurement of an Energy Supply Company (‘ESCo’) to deliver the South Kilburn decentralised energy system to install, manage and maintain the system and deliver heat to all properties developed as part of the regeneration of South Kilburn (referred to as ‘the Project’).

1.2This report seeks Executive’s approval to alter the procurement process in respect of the Project as required by Contract Standing Orders 88 and 89 and seeks approval to procure an ESCo to deliver the Project through a competitive procedure similar to the Competitive Dialogue procedure (as set out in the Public Contracts Regulations 2006).

1.3The report also seeks Executive approval to award a consultancy contract to Parsons Brinckerhoff Ltd to project manage the delivery of the project, advise on and provide commercial and strategic financial advice in respect of the Project.

Recommendations

2.1That the Executive note progress made on the South Kilburn Decentralised Energy System Project.

2.2That the Executive approve the Strategic Director of Regeneration and Growth to undertake a competitive procurement procedure (similar to the Competitive Dialogue procedure (as set out in the Public Contracts Regulations 2006) to procure an Energy Supply Company (‘ESCo’) to deliver the Project.

2.3That the Executive approve the evaluation criteria as set out in this report which will form the basis for evaluation of the bids and the ultimate selection of the ESCo to deliver the Project. Further, that the Executive approves the Strategic Director of Regeneration and Growth to develop the detailed evaluation methodology and respective weightings to be applied to the evaluation criteria, within the parameters of the evaluation criteria set out in this report, prior to recommencement of the procurement process.

1 2.4 That the Executive award a consultancy contract to Parsons Brinckerhoff Ltd to project manage the delivery of the project, advise on and provide commercial and strategic financial advice in respect of the project.

3. Project Background

3.1The delivery of the South Kilburn Regeneration Programme needs to, in accordance with The Greater London Authority (GLA) London Plan and Building Control Regulations, deliver a localised sustainability strategy, to ensure new and future developments achieve a 40% carbon reduction by 2013 and potentially zero carbon by 2016.

3.2The GLA has actively encouraged the development of an estate wide energy centre. The decentralised energy scheme will incorporate one energy centre generating heat through a district-wide combined heat and power (CHP) plant. Electricity is also generated through capturing usable heat that is produced in this process. To meet heating demand at peak times especially in winter, centralised boilers are also installed in the energy centre. The hot water generated is pumped through pipes in the ground to each building (this is referred to as the primary heat network). Heat exchange units are also installed within the buildings to enable the heat to be taken from the network. Each property drawing heat from the heat pipe is metered for heat consumption (for hot water and central heating) and the occupant pays for this heat accordingly.

3.3As part of the decentralised energy supply scheme, an ESCo will be formed to install, manage and maintain the system and deliver heat to all the properties developed by the Council as part of the regeneration of South Kilburn. The ESCo will deal with billing and collection of payments from residents. The Council will procure an ESCo which will be operated by a private company.

3.4It is envisaged the Project will deliver;

a) Lower energy costs for residents (based on average consumption use)

b) A district heating solution that is no more costly to developers than individual block heating solutions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
South Kilburn Regeneration Decentralised Energy ProjectReport 176 KB DownloadRead as text
PDF
rg-sk-energy-app2Report 92 KB Download
PDF
rg-sk-energy-app4Report 94 KB Download
PDF
rg-sk-energy-app5Report 682 KB Download

At this meeting

Whole meeting

Who was there

9 of 14 attended
MB
Councillor Muhammed ButtChair, present
RM
Councillor Ruth MoherVice-Chair, present
MA
Councillor M Aslam ChoudryCommittee Member, present
GC
Councillor George CraneCommittee Member, present
JD
Councillor James DenselowCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
RM
Councillor Roxanne MashariCommittee Member, present
MM
Councillor Margaret McLennanCommittee Member, present
JM
Councillor Jim MoherCommittee Member, apologies
MP
Councillor Michael PaveyCommittee Member, present
AA
Councillor Abdi AdenCommittee Member, in attendance
BC
Councillor Bhagwanji ChohanCommittee Member, in attendance

All 14 on the meeting page

On this subject at Brent

Search all
  1. South Kilburn Regeneration Decentralised Energy ProjectThis decision
  2. Authority to award a contract for a Single Delivery Partner for the South Kilburn Regeneration ProgrammeDecided
  3. South Kilburn District Heat Network - Tender Outcome & Financial Model ReportApproved
  4. Request for Strategic Community Infrastructure Levy Allocation for the South Kilburn Primary School and South Kilburn Urban ParkDecided
  5. South Kilburn - Authority to Tender for a Single Delivery PartnerDecided
  6. South Kilburn medical centre additional SCIL contributionAgreed

More from Brent Executive

All decisions
MeetingDecisionOutcome
16 Jun 2014 Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... Approved Open
16 Jun 2014 Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... Approved Open
16 Jun 2014 Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... Noted Open
16 Jun 2014 Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... Agreed Open
16 Jun 2014 Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies