( i ) that approval be given to the award of the contract for Emergency Response to the Barnet Group for an initial contract period of two (2) years with the option to extend for a further period of one (1) plus one (1) years; (ii) that it be noted that the value of the contract for the provision of Emergency Response Service is estimated to be circa £100,000 per annum for the contract period stated at paragraph ( i ) above.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report seeks the approval of the Executive to award a contract for the provision of Supporting People - Emergency Response as required by Standing Order 88(c). This report summarises the results of the procurement process undertaken by Brent officers and following completion of the evaluation, recommends a provider for award of the proposed contract. The report also sets out the financial implications and other benefits associated with the contract.
Recommendations
2.1That the Executive approve the award of the contract for Emergency Response to the Barnet Group for an initial contract period of two (2) years with the option to extend for a further period of one (1) plus one (1) years.
2.2That the Executive note that the value of the contract for the provision of Emergency Response Service is estimated to be circa £100,000 per annum for the contract period stated at paragraph 2.1 above.
3.0Detail
3.1Overview
3.1.1 An approval to the pre - tender considerations and criteria for the new procurement exercise was reported at the Executive meeting in June 2013. This report now provides the outcome of the procurement and the resulting recommendation for award of contract.
3.2.2 The Emergency Response service is part of the current Sheltered Housing Contract, which is also part of the portfolio of services commissioned within the Supporting People programme. This contract expired on 31st March 2013; however the services continue to be provided by Willow Housing on a spot purchase basis. This contract is for services targeted at older people and is comprised of 4 elements:
• housing-related support for people living in sheltered housing, • scheme management for people living in extra care schemes, • emergency response for out of hours support, and • activities co-ordination to enable older people to participate in meaningful activities during the day.
3.2.3 Responsibility for the commissioning of these services is with Brent Council’s Adult Social Care (ASC) department and the budget is held by Regeneration and Growth. Governance of this service area is maintained jointly by the ASC Departmental Management Team and the One Council Supporting People Project Board.
3.3Procurement Process
3.31 Emergency Response Service is defined as Part B services under the Public Contract Regulations 2006 (as amended) (“the Regulations”).
3.3.2 The Open tender process under the Regulations was followed for this tender. Whereby providers’ bids were evaluated in a one-stage approach, covering pre- selection and qualitative criteria.
3.3.3 In order to adhere to the Council’s Contract Standing Orders, the Treaty on the Functioning of the European Union (EU Treaty Principles) and achieve best value; the Council carried out a competitive tender process in an open, fair and transparent manner with full advertising of the requirements in the London Tenders Portal, Brent local Newspaper and on the Community Care place website and compliance when inviting and evaluating tenders to ensure Value for Money for the Council in the delivery of the Emergency Response Contract.
4.0The Tender Process and Council’s Contract Standing Orders
4.1The tendering process was undertaken in one stage (open tender process) in accordance with the Council’s Standing Orders 96 (b) and via the Council’s eTendering system (Due North).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies