London Borough of Brent
Cabinet, Monday 21 July 2014 at 2.00pm

Brent RE:FIT Programme Report – authority to proceed to Call-Off Contract Phase 2

Approved Executive 1 paper

Cabinet approved this item on Monday 21 July 2014. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

( i ) that approval be given to a ward an Energy Performance Contract (EPC) under the Framework Agreement provided by the GLA RE:FIT programme to install energy conservation measures (ECMs) in selected Brent Corporate Public buildings and a number of Brent schools within the Schools Expansion Programme for the contract value of £941,980 to Imtech Technical Services Ltd ( Imtech ); (ii) that approval to fund the proposed Brent REFIT schemes from a combination of unsupported borrowing, corporate reserves and individual school balances to the value of £674,230 and from Salix Funding for the amount of £267,750; (iii) that approval be given to the appointment of the Building Research Establishment (BRE) to provide continued support and technical expertise through to completion of Call-Off Contract Phase 2 REFIT Programme (ECM Installation) at a cost of £35,152 (excl. VAT & expenses) from existing Property and Projects budgets.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Summary

1.1Brent REFIT is a programme designed to deliver energy savings for existing corporate buildings and schools using the GLA REFIT Framework Agreement. This is an “Invest to Save” scheme with guaranteed returns over the agreed payback period.

1.2This programme aims to contribute to reducing energy consumption and its associated costs in addition to mitigating CO2 emissions with the installation of Energy Conservation Measures (ECMs) in Brent Council buildings and schools.

1.3An investment of £941,980 will deliver guaranteed energy savings of 2,158MWh worth £110,376 per annum at current prices giving a simple payback of 8.5 years equating to 25.3% energy savings against baseline (CO2 reduction against baseline equal to 26.1%).

Recommendations

2.1Approval to award an Energy Performance Contract (EPC) under the Framework Agreement provided by the GLA RE:FIT programme to install energy conservation measures (ECMs) in selected Brent Corporate Public buildings and a number of Brent schools within the Schools Expansion Programme for the contract value of £941,980 to Imtech Technical Services Ltd (Imtech).

2.2Approval to fund the proposed Brent REFIT schemes from a combination of unsupported borrowing, corporate reserves and individual school balances to the value of £674,230 and from Salix Funding for the amount of £267,750.

2.3Approval to appoint the Building Research Establishment (BRE) to provide continued support and technical expertise through to completion of Call-Off Contract Phase 2 REFIT Programme (ECM Installation) at a cost of £35,152 (excl. VAT & expenses) from existing Property & Projects budgets.

3.0Detail

3.1In July 2013, Brent Council issued an Invitation to Tender (ITT) under the GLA REFIT Framework Agreement to procure an Energy Performance Contract with energy savings backed by a performance guarantee over the duration of an agreed payback period.

3.2In November 2013 Imtech UK Technical Services Ltd (Imtech) was awarded the GLA Framework Agreement Phase 1 - Call-Off Contract to produce an Investment Grade Proposal (IGP) for selected corporate buildings and schools.

3.3The IGP by Imtech issued as Appendix 1 to this report identifies a number of ECMs to be implemented across the 15 sites. The ECMs will use a design and build contract approach, bespoke for each site. Once installed the ECMs will provide energy savings which will be guaranteed against an agreed energy consumption baseline.

3.4Energy performance against an agreed baseline is the fundamental purpose of the contract and this is reflected in the terms and conditions of the GLA Framework Agreement.

3.5Approval to proceed to the next stage, Phase 2 – Call-Off Contract, will allow the project to proceed to installation of the ECMs at each site. A fast track programme is planned requiring coordination with the school expansion programme and Brent FM to ensure minimal disruption during occupancy hours.

3.6Imtech will install 16 types of ECMs (53 no. in total across 15 sites) to provide 2,158 MWh of energy savings worth £110,376 per annum at current prices giving a simple payback of 8.5 years for the whole programme.

3.7The Brent REFIT Programme will contribute to meeting the Council’s Carbon Reduction Targets (CO2) at Local, Regional, National and EU levels:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brent RE:FIT Programme Report: authority to proceed to Call-Off Contract Phase 2Report 147 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
MB
Councillor Muhammed ButtChair, present
MP
Councillor Michael PaveyVice-Chair, present
JD
Councillor James DenselowCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
RM
Councillor Roxanne MashariCommittee Member, present
MM
Councillor Margaret McLennanCommittee Member, present
RM
Councillor Ruth MoherCommittee Member, present
KP
Councillor Keith PerrinCommittee Member, present
SC
Councillor Shafique ChoudharyCommittee Member, in attendance
BC
Councillor Bernard Collier MBA, DMS, BA (Hons)Committee Member, in attendance
HF
Councillor Harbi FarahCommittee Member, in attendance
DF
Councillor Dan FilsonCommittee Member, in attendance

All 17 on the meeting page

On this subject at Brent

Search all
  1. Brent RE:FIT Programme Report – authority to proceed to Call-Off Contract Phase 2This decision
  2. Impact of the Overall Benefit Cap in BrentNoted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies