( i ) Noted the contents of this report (ii) Approved in principal the proposed route through Brent subject to consultation by Transport for London with assistance from Brent. (iii) Delegated authority to the Head of Transportation to implement the scheme through Brent subject to the outcomes of the consultation and funding being secured.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The aim of this report is to introduce members to the proposed cycle route in Brent developed by WestTrans from Stanmore to Thames (Kew Bridge).
1.2WestTrans is coordinating planning for this route as it stretches across four boroughs (Harrow, Brent, Ealing and Hounslow). Stanmore to Thames Cycle Route is being developed using the Mayor of London’s Quietway principals.
1.3Following approval of this report, Transport for London (TfL) will commence detailed design work and apply for funding under the Quietways programme.
1.4Funding has not yet been secured from TfL for implementation.
Recommendations
2.1That the Committee:
2.1.1. Notes the contents of this report
2.1.2. Approve in principal the proposed route through Brent subject to consultation by Transport for London with assistance from Brent.
2.1.3. Delegates authority to the Head of Transportation to implement the scheme through Brent subject to the outcomes of the consultation and funding being secured.
20 October 2014 Version 1.7 Date: 19/09/2014 3.0 Background
3.1Quietways are part of the Mayor of London’s Cycling Vision to provide a network of routes on safer, lower-traffic back streets, aimed at new and less confident cyclists. They will be routes where people will want to cycle, by providing direct and comfortable journeys to key destinations across London, using parks and green spaces where suitable.
3.2Brent has been working with the London Boroughs of Harrow, Ealing and Hounslow (through the WestTrans partnership of West London boroughs) to develop a sub-regional cycling route from Stanmore to the River Thames since 2010. The four boroughs have now agreed a route in principle to be submitted to TfL for detailed design, followed by applications to the GLA for funding in the next tranche of the Quietways programme.
3.3The Quietways qualifying criteria defined by TfL and the Mayor of London’s Cycling Commissioner include: • Directness and cohesion • Attractiveness to users • Traffic composition and impact to other users • Buildability • Political support • Network priority
3.4Officers believe that the proposed route meets all of the above criteria and provides a critical network function in the context of providing a high quality network of cycle routes across the borough linking growth areas, public transport and activity centres, including key growth areas at Wembley Central and Alperton.
3.5WestTrans will submit the plan to TfL for detailed design and apply for funding under the Quietway programme.
4.0Stanmore to Thames Cycle Route
4.1The proposed cycle route through Brent, shown in Appendix A, starts at Stanmore in Harrow, proceeding generally south to enter Brent at Kenton (crossing the A4006 from Elmwood Avenue to Churchill Avenue). The route continues through Northwick Park, North Wembley, Sudbury, Wembley and Alperton, before leaving the borough at Perivale.
4.2As part of the detailed design of the scheme, interventions will be developed at a number of junctions and conflict points along the route, subject to public consultation, which Brent will be a key consultee, and final GLA and TfL approval. These may include, but are not limited to: • Junction remodelling and reconstruction
20 October 2014 Version 1.7 Date: 19/09/2014 • Changes to junction operation including addition, modification or removal of signals • Vertical or horizontal deflection (including raised tables or chicanes) • Changes to speed limits • Modal filters (e.g. Closure of road to vehicular traffic) • Changes to width of carriageway or pathways (including widening or narrowing) • Segregation between road users
4.3Signage will also be provided at key locations (such as intersections) and at regular intervals along the route to ensure legibility for riders. A signage standard for all Quietways is currently being developed by TfL which will be adopted for this cycle route.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.