( i ) that the contract for the Supply of Electricity be awarded to Npower Limited and Kent County Council for four years from 1 October 2016 via a call-off from the LASER framework. (ii) that the contract for the Supply of Gas be awarded to Total Gas and Power Limited and Kent County Council for four years from 1 October 2016 via a call-off from the LASER framework.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests authority to award contracts as required by Contract Standing Order No 88. This report summarises the process undertaken in procuring these contracts and recommends to whom the contracts should be awarded.
Recommendations
2.1That Cabinet award the contract for the Supply of Electricity to Npower Limited and Kent County Council for four years from 1st October 2016 via a call-off from the LASER framework.
2.2That Cabinet award the contract for the Supply of Gas to Total Gas and Power Limited and Kent County Council for four years from 1st October 2016 via a call-off from the LASER framework.
3.0Detail
Background
3.1The council currently buys its gas and electricity through the “LASER” framework, established by Kent County Council. The current contracts commenced on 1st October 2012, and expire on 30th September 2016.
July 2014 Page 1 V5 London Borough Of Brent 3.2 The council’s corporate buildings, streetlighting, and housing properties are included in the contract. Many of Brent’s schools also opt in to the arrangement.
3.3The current spend per annum is shown in the table below:
Energy Annual Spend Brent buildings gas £733,000
Brent buildings electricity £1,003,000
Streetlighting electricity £1,314,000
Schools electricity £950,000
Schools gas £650,000
Housing electricity £841,000
Total £5,491,000
3.4There are currently 39 schools who buy gas through the council’s contract, and 51 who buy their electricity. Officers have presented to school bursars the benefits of using the council’s contract with LASER for their energy buying with the aim of encouraging further schools to opt in to the arrangements. The council charges an administration fee to the schools of approximately 1% of the consumption element of invoices. This equated to approximately £50,000 in 2013/2014.
3.5Given the expiry of exiting gas and electricity contracts in 2016, Officers have been considering procurement options available to the council. In selecting the procurement method for the council’s energy from 1st October 2016, the option of carrying out a stand alone procurement, either to contract directly with suppliers or through a broker was considered. It was decided that procuring through a framework agreement established by a Public Sector Buying Organisation (PSBO) would be preferable for the following reasons:
• PSBO frameworks are used by multiple organisations, and the aggregation of volumes enables:
July 2014 Page 2 V5 London Borough Of Brent o strong competition at the point of procurement due to the attractiveness of the large amount of business
o the elimination of “take or pay”1 clauses
o the appointed supplier to go to market frequently thereby taking advantage of falling prices and minimising the risk of increasing prices in a volatile market.
• PSBOs bring expertise to the process that is not available within the council. PSBOs have their own specialist buyers, and most offer flexible contracts.
• The costs to the council of the procurement process are minimised.
• The costs to the council of contract management are minimised.
• There is transparency around the activities of PSBOs. • PSBO frameworks are used by publicly funded organisations, and therefore the contracting arrangements have an appropriate level of risk for a local authority.
3.6There are several PSBOs that have and will continue to have frameworks in place for the purchasing of gas and electricity. These are:
CCS Crown Commercial Service (formerly Government Procurement Service GPS) ESPO Eastern Shires Purchasing Organisation LASER Kent County Council NEPO North Eastern Purchasing Organisation YPO Yorkshire Purchasing Organisation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.