Housing Private Finance Initiative project agreement revisions

Agreed Executive 4 papers

Cabinet agreed this item on Monday 10 November 2014. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

( i ) that the proposed revisions to the Project Agreement (and related documents) as set out in paragraphs 4.1 to 4.15 of this report be noted and authority to agree of the final terms of revision to the Project Agreement (and related documents) contract be delegated to the Strategic Director for Regeneration and Growth in consultation with the Chief Finance Officer and the Borough Solicitor; (ii) that authority be authority to the Strategic Director for Regeneration and Growth, in consultation with the Chief Finance Officer and the Borough Solicitor, to agree the variation to the PFI Project Agreement and all other related documents, in order to enable the contract revisions to be properly documented; (iii) that the Borough Solicitor, or an authorised delegate acting on her behalf, be authorised to execute all of the legal agreements, contracts and other documents on behalf of the council and such other legal agreements and documentation which may be necessary to give full effect to the variation to the PFI Project Agreement, subject to her receiving confirmation of continuing credit approval from the Department for Communities and Local Government, through the Homes and Communities Agency (HCA) or, executing such contracts and other documentation with a pre-condition that they shall only come into full effect upon the issuing of such PFI credit approval by the HCA/DCLG; (iv) that the Chief Finance Officer can issue, on behalf of the council, such certificate or certificates under the Local Government (Contracts) Act 1997 to: a. Brent Co-Efficient in respect of the Deed of Amendment (or such other document) to give effect to the variations to the PFI Project Agreement; b. Brent Co- Efficient's funders in respect of any the Direct Agreement Amendment Deed (or such other document) to give effect to the variations to the Direct Agreement entered into between the council, such the funders and Brent Co-Efficient; and c. Hyde Housing Association and the Brent Co- Efficient’s funders in respect of a the Residual Value Amendment Deed (or such other document) to give effect to the revised Residual Value Deed to be entered into between the council, Hyde Housing Association and the funders. (v) Agree that the Chief Finance Officer will be fully indemnified by the council in the event of any claim against him arising from the provision of any Certificate he may issue in accordance with recommendations/decisions in (iv) above.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Summary

1.1As a result of a number of external factors the Council’s Housing Private Finance Initiative (PFI) project currently faces considerable financial challenges and a projected deficit which falls on the Local Authority.

1.2This report proposes a number of contractual revisions to provide the Council with flexibility in order to improve the financial performance of the project and substantially reduce the prospective deficit. These have been arrived at following a period of negotiation with the Council’s PFI contract partner, Brent Co-Efficient (BCE) and following consultation with the Homes and Communities Agency (HCA) the Department for Communities and Local Government (DCLG).

Recommendations

Cabinet is asked to:

2.1Note and approve the proposed revisions to the Project Agreement (and related documents) as set out in paragraphs 4.1 to 4.15 of this report and to delegate agreement of the final terms of revision to the Project Agreement (and related documents) contract to the Strategic Director for Regeneration and Growth in consultation with the Chief Finance Officer and the Borough Solicitor.

Meeting Cabinet Version no. 3 th Date 10 November 2014 Date: 15/10/14 2.2 Delegate authority to the Strategic Director for Regeneration and Growth, in consultation with the Chief Finance Officer and the Borough Solicitor, to agree the variation to the PFI Project Agreement and all other related documents, in order to enable the contract revisions to be properly documented.

2.4Authorise the Borough Solicitor, or authorised delegate on her behalf, to execute all of the legal agreements, contracts and other documents on behalf of the council and such other legal agreements and documentation which may be necessary to give full effect to the variation to the PFI Project Agreement, subject to her receiving confirmation of continuing credit approval from the Department for Communities and Local Government, through the Homes and Communities Agency (HCA) or, executing such contracts and other documentation with a pre-condition that they shall only come into full effect upon the issuing of such PFI credit approval by the HCA/DCLG.

2.5Agree that the Chief Finance Officer can issue, on behalf of the council, such certificate or certificates under the Local Government (Contracts) Act 1997 to:

a. Brent Co-Efficient in respect of the Deed of Amendment (or such other document) to give effect to the variations to the PFI Project Agreement;

b. Brent Co-Efficient's funders in respect of any the Direct Agreement Amendment Deed (or such other document) to give effect to the variations to the Direct Agreement entered into between the council, such the funders and Brent Co-Efficient; and

c. Hyde Housing Association and the Brent Co-Efficient’s funders in respect of a the Residual Value Amendment Deed (or such other document) to give effect to the revised Residual Value Deed to be entered into between the council, Hyde Housing Association and the funders.

2.6Agree that the Chief Finance Officer will be fully indemnified by the council in the event of any claim against him arising from the provision of any Certificate he may issue in accordance with recommendations/decisions in 2.5 above.

Background

3.1The PFI contract was entered into between the Council and Brent Coefficient Limited (BCE), a subsidiary of Hyde Housing Group (Hyde), on 19 December 2008 for Phase 1 which was extended in July 2010 to include Phase 2 and the contract ends on 18 December 2028. The project provided for the construction between 2010 and 2012 of 364 units of accommodation by BCE, and an additional 20 units of residential care accommodation which are owned by the Council. All units have been constructed and the project is in its service operational phase.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Private Finance Initiative project agreement revisionsReport 136 KB DownloadRead as text
PDF
rg-housing-pfi-app1Report 183 KB Download
PDF
rg-housing-pfi-app2-summary-financial-resultsReport 169 KB Download
PDF
rg-housing-pfi-project-eiaReport 344 KB Download

At this meeting

Whole meeting

Who was there

7 of 12 attended
MB
Councillor Muhammed ButtChair, present
MP
Councillor Michael PaveyVice-Chair, present
GC
Councillor George CraneCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
RM
Councillor Roxanne MashariCommittee Member, present
MM
Councillor Margaret McLennanCommittee Member, present
RM
Councillor Ruth MoherCommittee Member, present
JD
Councillor James DenselowCommittee Member, apologies
DF
Councillor Dan FilsonCommittee Member, in attendance
JL
Councillor Janice LongCommittee Member, in attendance
AM
Councillor Arshad MahmoodCommittee Member, in attendance
KP
Councillor Keith PerrinCommittee Member, in attendance

On this subject at Brent

Search all
  1. Housing Private Finance Initiative project agreement revisionsThis decision
  2. Private Sector Housing Strategy 2024-2029Noted
  3. Private Housing - HMO and Selective Licensing Fee Structure (verbal update)Noted
  4. Private Housing Assistance Policy AmendmentsApproved

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open