South Kilburn Regeneration Programme - Carlton & Granville Centres Site - Development Options

Agreed Executive 3 papers

Cabinet agreed this item on Tuesday 15 November 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

- i. Cabinet agreed to the Phase 1 of the Carlton and Granville Centres site redevelopment being the refurbishment and reconfiguration of the Granville Centre to allow for an interim Enterprise Hub to be established. ii. Cabinet delegated authority to Head of Estates Regeneration in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to enter into all agreements with the Greater London Authority in respect for the funding for the refurbishment of the Granville Centre. iii. Cabinet delegated authority to the Chief Executive in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to enter into legal agreements, including any lease with the South Kilburn Trust (SKT) and also with the GLA to secure their funding contribution in return for project delivery of the interim Enterprise Hub by March 2018. iv. Cabinet delegated authority to the Chief Executive in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to oversee scheme development through further viability testing, local consultation, and planning consent; v. Cabinet approved the procurement of an architecturally led multidisciplinary design team to develop a detailed planning application for redevelopment of Carlton and Granville Centres site as Phase 2 of the work by either: - calling off the Greater London Authority (GLA) and Transport for London ( TfL ) Architecture, Design and Urbanism Panel (ADUP) or such other appropriate OJEU compliant framework; and evaluating those tenders in accordance with the relevant Framework; or alternatively - carrying out an OJEU compliant procurement process and inviting tenders on the basis of the pre-tender considerations set out in paragraph 3.30 of this report and evaluating the tenders on the basis of the evaluation criteria set out in that paragraph - The cost of the design team and associated consultants is anticipated to be in the region of £1m. £350,000 has already been assigned to this project so the balance will be up to £650,000 to be funded “up-front” by the Council. vi. Cabinet noted that irrespective of which procurement option detailed in 2.5 above is selected, officers will report back to Cabinet to seek Members’ approval to award the proposed contract, once a preferred design team has been identified. - i. Cabinet agreed to the Phase 1 of the Carlton and Granville Centres site redevelopment being the refurbishment and reconfiguration of the Granville Centre to allow for an interim Enterprise Hub to be established. ii. Cabinet delegated authority to Head of Estates Regeneration in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to enter into all agreements with the Greater London Authority in respect for the funding for the refurbishment of the Granville Centre. iii. Cabinet delegated authority to the Chief Executive in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to enter into legal agreements, including any lease with the South Kilburn Trust (SKT) and also with the GLA to secure their funding contribution in return for project delivery of the interim Enterprise Hub by March 2018. iv. Cabinet delegated authority to the Chief Executive in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to oversee scheme development through further viability testing, local consultation, and planning consent; v. Cabinet approved the procurement of an architecturally led multidisciplinary design team to develop a detailed planning application for redevelopment of Carlton and Granville Centres site as Phase 2 of the work by either: - calling off the Greater London Authority (GLA) and Transport for London ( TfL ) ... view the full minutes text for item 9.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Appendix 2 Background Information on Granville Plus Nursery School

Granville Plus Nursery School is a Nursery School, Nursery Schools have a different distinction from a nursery. The Maintained nursery schools: the state of play report (March 2015, Early Education: The British Association for Early Childhood Education) identifies that “maintained nursery schools are local authority funded schools, with a headteacher and qualified teachers leading a team of specialist early years practitioners”, they also identify that just over 400 remain in England. Within Brent only a few Nursery Schools remain.

The latest Ofstead inspection report for the Nursery School (they are inspected under two separate Ofsted frameworks, in the Nursery School (including Horizon, their Additionally Resourced Provision for children with autism), and in their Rainbow provision), both received a “Good” from Ofsted. The Maintained nursery schools: hubs for quality in the early years (Early Education: The British Association for Early Childhood Education) report states that “Nursery Schools are inspected under the Ofsted criteria used for primary schools, rather than those used for early years settings in the private and voluntary sector, with inspections lasting two days rather than half a day.”

Council Officers visited with the Nursery School Headteacher on the 8 September and were shown around the building which includes a recent extension. Key points highlighted included the importance of the outdoor space as an educational tool and for children who live in the surrounding area which is predominantly flat accommodation. The Nursery School has an identified offer for children with Special Education Needs and Disabilities. Below is information provided from the Headteacher in regards to the Nursery School.

Officers also met with the parents and with the Governors on two separate events. Information from these meetings are imbedded into this report. From all three meeting the clear message was that they wish to stay on their current site and would not wish to be part of a nursery attached to another school (this is driven partly by not wishing to lose the status of being a Nursery School).

Information provided by the Headteacher:

 74% of the children are from NW6, with a further 14% from NW10 (Harlesden).  94% are from ethnic minorities, and 86% have English as an Additional Language.  17% of our children have significant Special Educational Needs and Disabilities (SEND), including 11 in our additionally resourced provision for children with autism, and a further 8 places for children with a range of significant needs including physical disabilities and medical needs.  The children with SEND are fully integrated within our mainstream environment, and our SEND provision, including the autistic provision, was judged outstanding in our latest Ofsted.  8% of places are for Children in Need (usually with social care needs, including child protection)  All these specialist places are allocated by a borough-wide panel.  We are open 8am to 6pm for 48 weeks of the year, with a flexible fees structure, to support parents back to work or college.  51% of places are babies and 2-3 year olds, with nearly all the 2-3 year olds funded by the "vulnerable 2 year olds" NEG2 funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09: c&g_appendices_2-6Report 85 KB DownloadRead as text
PDF
09: c&g_appendix1Appendix 9.2 MB Download
PDF
South Kilburn Regeneration Programme: Carlton & Granville Centres Site: Development OptionsReport 170 KB Download

At this meeting

Whole meeting

Who was there

8 of 16 attended
MB
Councillor Muhammed ButtChair, present
MM
Councillor Margaret McLennanVice-Chair, present
HF
Councillor Harbi FarahCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
RM
Councillor Roxanne MashariCommittee Member, present
TM
Councillor Tom MillerCommittee Member, present
WM
Councillor Wilhelmina Mitchell MurrayCommittee Member, present
ES
Councillor Eleanor SouthwoodCommittee Member, present
DV
David VealeCouncil Staff, expected
LJ
Councillor Lesley Jones MBE B.Ed MACouncillor, in attendance
KS
Councillor Ketan ShethCouncillor, in attendance
RC
Councillor Rita ConneelyCouncillor, in attendance

All 16 on the meeting page

On this subject at Brent

Search all
  1. South Kilburn Regeneration Programme - Carlton & Granville Centres Site - Development OptionsThis decision
  2. Authority to award a contract for a Single Delivery Partner for the South Kilburn Regeneration ProgrammeDecided
  3. South Kilburn District Heat Network - Tender Outcome & Financial Model ReportApproved
  4. Request for Strategic Community Infrastructure Levy Allocation for the South Kilburn Primary School and South Kilburn Urban ParkDecided
  5. South Kilburn - Authority to Tender for a Single Delivery PartnerDecided
  6. South Kilburn medical centre additional SCIL contributionAgreed

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies