14.1 Cabinet noted the actions and progress undertaken in connection with the Cycle Strategy Action Plan and Targets 2016/17 14.2 Cabinet approved the updated Cycle Strategy Action Plan for 2017/18 and revised Targets 14.3 Cabinet approved the intention to seek delegated approval from Cabinet to the Strategic Director Regeneration & Environment, in consultation with the Lead Member for Environment the final approval of content, including design, following any required changes to the updated Cycle Strategy Acton Plan for 2017/18 agreed by Cabinet. 14.1 Cabinet noted the actions and progress undertaken in connection with the Cycle Strategy Action Plan and Targets 2016/17. 14.2 Cabinet approved the updated Cycle Strategy Action Plan for 2017/18 and revised Targets. 14.3 Cabinet approved the intention to seek delegated approval from Cabinet to the Strategic Director Regeneration & Environment, in consultation with the Lead Member for Environment the final approval of content, including design, following any required changes to the updated Cycle Strategy Acton Plan for 2017/18 agreed by Cabinet.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The Brent Cycle Strategy was approved by Cabinet in January 2016 (the Strategy).
1.2The Strategy provides a transparent framework from which works to increase the number of people cycling are being implemented and investment for cycling throughout the borough is being prioritised.
1.3This report seeks to:
1.3.1. Inform on actions undertaken in 2016/17 and set out progress against the Strategy’s targets; and, 1.3.2. Update the Cycle Strategy Action Plan and Targets for 2017/18.
Recommendations
2.1That Cabinet note the actions and progress undertaken in connection with the Cycle Strategy Action Plan and Targets 2016/17;
2.2That Cabinet approve the updated Cycle Strategy Action Plan for 2017/18 and revised Targets;
2.3That Cabinet approve the intention to seek delegated approval from Cabinet to the Strategic Director Regeneration & Environment, in consultation with the Lead Member for Environment the final approval of content, including design, following any required changes to the updated Cycle Strategy Acton Plan for 2017/18 agreed by Cabinet.
1 Version 7.0 3. Actions and Target Achievements to Date
3.1Construction of the Brent section of the Quietway cycle route from Regent’s Park to Gladstone Park has been completed. Signage for the entire Quietway will be installed in April. This output will add an additional 3.5km of cycle route to Brent’s network. A further 840m of cycle route along Carlton Vale is due for completion in Spring 2017 resulting in Brent’s first lightly segregated cycle route. These schemes will increase the length of Brent’s cycle network in 2016/17 by 13.9%, greatly exceeding the Cycle Strategy’s 1% target.
3.2A revision of the Council’s procurement process has successfully ensured that all fleet operators working within contractual agreements with Brent Council have Fleet Operator Recognition Scheme (FORS) accreditation. The scheme promotes best practice for commercial vehicle operators in several measures including safety, whereby drivers must complete cycle safety training to recognise the causes and minimise the risk of collisions with cyclists.
3.3Similarly, freight safety is now a required element of planning applications for developments in Brent that are of strategic importance to London. In accordance with the London Plan, planning applications must be accompanied by a Delivery and Servicing Plan (DSP) that sets out how the impact of freight activity on the borough’s transport network will be managed. This includes measures to mitigate conflict with cyclists on preferred routes and the use of cycle-specific safety equipment on FORS accredited vehicles. These requirements will contribute to the objective of reducing the number of accidents on Brent’s roads involving cyclists.
3.4In line with standards in the London Plan, cycle parking design standards for all new building developments in Brent have been updated. The perception of bike theft is a significant barrier to cycling and so this output will contribute to the promotion of cycling as a safe and convenient activity. Additionally, the location of public cycle parking facilities in Brent is being clarified on the cycling pages of the Council’s website.
3.5The Council’s cycle training programme reached 285 adults and 956 children between April and December 2016. The figure for adults receiving training has so far exceeded the 2016/17 target (234). The figure for children is slightly below the anticipated number for the eight month period passed though the 2016/17 target is expected to be met with school cycle training programmes planned between January and March 2017.
3.6There has been a reduction in the proportion of road accidents involving cyclists from 12.3% in 2014 to 11.2% in 2015. Several of the completed actions described here may be attributable to this reduction which works towards the 2020/21 target of 8%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.