17.1 Cabinet noted the proposed highways maintenance programme for 2017-18 as detailed in Appendix B to the Cabinet report. 17.2 Cabinet agreed that any changes to this and future highways capital programmes, are approved by the Strategic Director of Regeneration and Environment in consultation with the Cabinet Member for Environment. 17.1 Cabinet noted the proposed highways maintenance programme for 2017-18 as detailed in Appendix B to the Cabinet report. 17.2 Cabinet agreed that any changes to this and future highways capital programmes, are approved by the Strategic Director of Regeneration and Environment in consultation with the Cabinet Member for Environment.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1In 2016/17 approximately £6.086 m will be spent improving the condition of Brent’s highways, including resurfacing of 11 miles of road and reconstructing 6 miles of pavement. This equates to 3.6% of the road network and 1.1% of the pavements. This investment includes £5.185m of Brent capital (an initial allocation of £3.55m followed by additional £2m, with £365k of footway works held over to 17/18) and £901k of TfL capital funding for Principal (A road) maintenance.
1.2During 2017/18 initially it is proposed to allocate £3.5m of Brent capital to maintain the highway network, plus £365k of footway works held over from 16/17, subject to approval of the Budget and Council Tax report to be submitted to Cabinet and Full Council in February 2017.
1.3In addition to £3.5m of Brent capital in 2017/18, TfL have confirmed funding of £0.886m of Principal Road (A-road) improvements. This is slightly less than the 2016/17 Principal road programme value of £0.901 m.
1.4This report sets out recommendations for how Brent’s £3.5m capital budget should be allocated during 2017/18 through a prioritised programme of:
Major and minor pavement reconstruction; Major Road resurfacing; Preventative maintenance; Improvements to the public realm, and Renewal of Road Markings
1.5This programme will be delivered using Brent’s Highway Asset Management Planning (HAMP) approach, which provides a systematic long term methodology for maintaining the borough’s highways. The HAMP approach, which was started in 2014/15, will deliver better value for money through adoption of a sensible and forward thinking maintenance plan.
1.6In line with public and member priorities further investment in the roads and pavement network will also be considered this year to improve our performance and reduce reliance on reactive maintenance. Future proposals and priorities to cover a medium term (up to 5 years) approach will see more miles of road maintained each year and our customers will have greater visibility as to the relative status of their roads.
1.7Investment is aimed to address the following; achieving greater equality in condition between footways and carriageways; accommodating members’ requests for regenerating High Streets by giving them greater priority, so improving their look and feel; and replacing slabs with asphalt when doing full footway renewals.
Recommendations
2.1That the Committee notes the proposed highways maintenance programme for 2017-18 as detailed in Appendix B.
2.2That any changes to this and future highways capital programmes, are approved by the Strategic Director of Regeneration & Environment in consultation with the Cabinet Member for Environment.
3.1Brent’s annual highways maintenance investment programme consists of Brent capital funding, which is used to fund the roads maintenance programme for local roads; capital funding provided by Transport for London, which is used to deliver principal (strategic) road maintenance
3.2By 31 March 2017, approximately £6.086m will have been spent on maintaining Brent’s highway infrastructure funded through £5.55m of Brent capital, and £0.901 million of principal road maintenance investment, with £365k of footway works held over to 17/18. Appendix A provides details of the works delivered, which will result in (amongst other things):
11 miles of roads being resurfaced; and 6 miles of footways being reconstructed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.