19.1 That Cabinet approve further investment of £7.5m (total investment £31.5m), to deliver the Scheme. 19.2 Cabinet agreed to delegate authority to the Strategic Director of Resources, in consultation with the Portfolio Lead Member for Property to award the works contract to the successful tenderer following a procurement process, for the reasons detailed in paragraph 3.5 of the report from the Strategic Director of Resources. 19.3 Cabinet approved the procurement of the works contract through a framework as outlined in 3.5 of the report from the Strategic Director of Resources. . 19.1 That Cabinet approve further investment of £7.5m (total investment £31.5m), to deliver the Scheme. 19.2 Cabinet agreed to delegate authority to the Strategic Director of Resources, in consultation with the Portfolio Lead Member for Property to award the works contract to the successful tenderer following a procurement process, for the reasons detailed in paragraph 3.5 of the report from the Strategic Director of Resources. 19.3 Cabinet approved the procurement of the works contract through a framework as outlined in 3.5 of the report from the Strategic Director of Resources.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1In April 2016, Cabinet approved £24m capital investment on a notional scheme of 125 units for this site. The project team has developed the proposals and will soon be in a position to submit a full planning application. Subject to planning, the scheme is due to deliver 149 units, an increase of 24 homes. Total Scheme costs are £31.5m. An additional capital investment of £7.5m is required to deliver the enlarged scheme.
Recommendations
2.1That Cabinet approve further investment of £7.5m (total investment £31.5m), to deliver the Scheme.
2.2That Cabinet delegate authority to the Strategic Director of Resources, in consultation with the Portfolio Lead Member for Property to award the works contract to the successful tenderer following a procurement process, for the reasons detailed in paragraph 3.5.
2.3That Cabinet approve procurement of the works contract through a framework as outlined in 3.5.
3.0Detail
3.1Background Delivery of this Scheme will reduce the council’s dependency on bed and breakfast and care homes. The Scheme will provide 149 new council owned homes and a replacement community centre.
Mix
Temporary New Community Total Accommodation Accommodation Centre (“TA”) for Independent Living (“NAIL”) 2b3p 62 1b1p 57 1 2b4p 7 3b5p 23 Total 92 57 1 150
3.2The financial model assumes that NAIL is affordable housing (i.e. Local Housing Allowance levels), but that the TA is set no higher than 80% of market rent, (including service charge).
NPV £3.9m IRR (60 Yrs.) 6.43% Discounted Payback Period (3.5%) 26 Years Gross Yield 6.71% Net Yield 5.43% Construction Period 3 Years
3.3The Scheme aligns with; the Strategic Property Plan 2015-2018, Brent’s corporate plan 2015/16, Temporary Accommodation reform plan April 2016, New Accommodation for Independent Living as per the 2016 update.
3.4Timescales
Milestone Date Planning submission June 2017 Cabinet approval June 2017 Contractor tendering July 2017 Tenders received November 2017 Build contract executed February 2018 Start on Site May 2018 Completion Phase One (TA and Community January 2020 Centre) Decant Knowles House February 2020 Completion phase two (NAIL) July 2021
All dates are provisional.
3.5Procurement
3.5.1 To identify and select the most suitable procurement route, consideration has been given to the following issues and criteria; The Council requires that a firm price and agreed programme are obtained from the contractor before commitment can be provided to commence works on site; Where possible and practical, risk should be transferred to the Contractor.
3.5.2 The recommendation is to procure the project through a single stage design & build approach. The key benefits of this approach for Knowles House are:
This addresses Brent’s concerns over two stage tendering as this approach may lead to loss of competition and increased tender costs; Reduces the time period for the procurement process; Passes risk to the contractor; The procurement process can begin quickly and utilise the available planning drawings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.