CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Cabinet, Monday 11 February 2019 at 4.00pm

Authority to award stage two contract for the redevelopment of Knowles House London NW10 3UN

Approved Executive 1 paper

Cabinet approved this item on Monday 11 February 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that: i) Cabinet provided approval to trigger the entry into the contract for Stage Two of the Two Stage design and build contract for the redevelopment of Knowles House to Wates Residential Ltd. ii) Cabinet noted the budget for the redevelopment of Knowles House as set out in Appendix 2 to the report from the Strategic Director of Resources. iii) Cabinet noted that the redevelopment of this site would reduce the number of people in unsuitable temporary accommodation in Brent.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report requests authority to trigger the award of the Stage Two of the two stage design and build contract for the redevelopment of Knowles House to Wates Residential Ltd for £28,588,687. The report outlines the progress and current position of the project since previous Cabinet approvals.

Recommendations

2.1That Cabinet give approval to trigger the entry into the contract for Stage Two of the Two Stage design and build contract for the redevelopment of Knowles House to Wates Residential Ltd.

2.2That Cabinet note the budget for the redevelopment of Knowles House as set out in Appendix 2.

2.3Approval of the redevelopment of this site will reduce the number of people in unsuitable temporary accommodation in Brent.

3.0Detail

3.1On 19th June 2017 Cabinet approved a capital investment for delivery of the Knowles House Scheme. Since the approval, GLA grant of £65m (to deliver a five year programme of affordable housing) has been awarded to Brent, part of which will be allocated to this scheme. The Knowles House Project Team also considered and amended the scheme specification to ensure that measures are put in place as part of the construction to minimise fire risks.

3.2In addition, the scheme was originally to be delivered in two phases but it has been recommended that it be delivered in one phase instead, for reasons detailed in this report. There remain some items of risk that are not quantifiable at this stage of the redevelopment, as the existing building is still occupied.

3.3Under a Delegated Authority Report dated 9th March 2018, approval to award contract to Wates Residential Ltd was obtained to enable the commencement of the Pre Construction Service Agreement (PCSA), being the Stage One of the Two Stage design and build contract (which commenced in May 2018), for the sum of £684,911. This has enabled the contractor to develop the design from a planning permission, to a full set of construction drawings, and to tender works packages to its sub-contractor supply chain. Based on that, a stage two (construction) contract sum of £28,588,687 (including Stage One cost) has been received from Wates Construction Ltd calculated on the basis of the current economic situation. It should be noted however that execution of the PCSA does not give Brent a legal obligation to enter into the main contract with Wates.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Authority to award stage two contract for the redevelopment of Knowles House London NW10 3UNReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 12 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
AA
Councillor Amer Agha MB BS, MSc, PHCM Lead Member for Schools, Employment and SkillsCommittee Member, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Public Health, Culture and LeisureCommittee Member, present
TM
Councillor Tom Miller Lead Member for Community SafetyCommittee Member, apologies
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, apologies
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Highways and PlanningCommittee Member, present
PA
Councillor Parvez AhmedCouncillor, in attendance
JL
Councillor Janice LongCouncillor, in attendance

On this subject at Brent

Search all
  1. Authority to award stage two contract for the redevelopment of Knowles House London NW10 3UNThis decision
  2. Authority to award a contract for a Single Delivery Partner for the South Kilburn Regeneration ProgrammeDecided
  3. Authority to Direct Award a Contract for Children's Public Health Services (0-19 years) Health Visiting and School NursingApproved
  4. Authority to delegate decision to Authorise Award of Contract(s) for (i)Transportation and Reprocessing of Co-Mingled Recycling Materials (Lot 1) & (ii) Reprocessing of Fibre Material (Lot 2).Noted
  5. Authority to Award Contract for Secure Cycle Parking - Bike Hangers & NestsApproved
  6. Authority to Award Contract for Temporary Recruitment Services (Managed Service Provider)Approved

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies