Expansion of Uxendon Manor & Elsley Primary Schools - Design & Build Contract Update

Noted Executive 1 paper

Cabinet noted this item on Monday 11 February 2019. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED that: i) Cabinet noted the current status and contractual position with Lakehouse Contracts Ltd on the two design and build contracts for Uxendon Manor Primary School and for Elsley Primary School. ii) Cabinet noted the activities being undertaken to secure completion of the works at Uxendon Manor Primary School under the Parent Company Guarantee. iii) Cabinet delegated authority to the Strategic Director of Resources in consultation with the Director of Legal and HR Services and Chief Finance Officer to terminate the high value works contract for Uxendon Manor Primary School in the event that reliance on the Parent Company Guarantee is not practicable or Officers conclude reliance on the Parent Company Guarantee/s is not in the Council’s interest. iv) Cabinet noted that officers were reviewing procurement options for the outstanding works at both schools should it not be practicable or appropriate to secure further works under the Parent Company Guarantee at Uxendon Manor Primary School or under the existing contract at Elsley Primary School. v) Cabinet approved the waiving of contract standing orders to permit a quote process or direct award to select an alternative contractor for Uxendon Manor Primary School and for Elsley Primary School should other procurement options not permit works to be completed by September 2019. vi) Cabinet noted that subject to recommendation v) above, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts should it be required using powers delegated under the Constitution. vii) Cabinet noted that Officers would review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited and/or parent company as described in Appendix 1 to the report from the Strategic Director of Resources.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report provides Cabinet with an update on the contractual position on the design and build contracts for the expansions of Uxendon Manor and Elsley Primary Schools and seeks authority to undertake certain actions to ensure completion of those works.

2.0Recommendation(s)

That Cabinet: 2.1 Note the current status and contractual position with Lakehouse Contracts Ltd on the two design and build contracts for Uxendon Manor Primary School and for Elsley Primary School.

2.2Note the activities being undertaken to secure completion of the works at Uxendon Manor Primary School under the Parent Company Guarantee.

2.3Delegate authority to the Strategic Director of Resources in consultation with the Director of Legal and HR Services and Chief Finance Officer to terminate the high value works contract for Uxendon Manor Primary School in the event that reliance on the Parent Company Guarantee is not practicable or Officers conclude reliance on the Parent Company Guarantee/s is not in the Council’s interest.

2.4Note that Officers are reviewing procurement options for the outstanding works at both schools should it not be practicable or appropriate to secure further works under the Parent Company Guarantee at Uxendon Manor Primary School or under the existing contract at Elsley Primary School.

2.5Approve waiving contract standing orders to permit a quote process or direct award to select an alternative contractor for Uxendon Manor Primary School and for Elsley Primary School should other procurement options not permit works to be completed by September 2019.

2.6Note that subject to Recommendation 2.5 above, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts should it be required using powers delegated under the Constitution.

2.7Note that Officers will review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited and/or parent company as described in Appendix 1.

3.0Detail

3.1Status of Works and Contractual Position

Uxendon Manor Primary School

3.2The Council entered into a design and build contract with Lakehouse Contracts Limited (“Lakehouse Contracts”) for Uxendon Manor Primary School as part of the Phase 3 Primary School Expansion Programme on 26 January 2017. The contract was subsequently executed on 15 January 2018 at a value of £6,548,332.83.

3.3Completion of the new buildings was due to be delivered under the contract for 10 August 2018 with project practical completion on 26 October 2018. Extension of time claims presented by the contractor (and approved by the Council’s Employers Agent) revised these dates to 8 October 2018 and 8 February 2019 respectively.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Expansion of Uxendon Manor & Elsley Primary Schools: Design & Build Contract UpdateReport 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 12 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
AA
Councillor Amer Agha MB BS, MSc, PHCM Lead Member for Schools, Employment and SkillsCommittee Member, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Public Health, Culture and LeisureCommittee Member, present
TM
Councillor Tom Miller Lead Member for Community SafetyCommittee Member, apologies
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, apologies
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Highways and PlanningCommittee Member, present
PA
Councillor Parvez AhmedCouncillor, in attendance
JL
Councillor Janice LongCouncillor, in attendance

On this subject at Brent

Search all
  1. Expansion of Uxendon Manor & Elsley Primary Schools - Design & Build Contract UpdateThis decision
  2. Uxendon Manor Primary School Expansion ProjectNoted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies