RESOLVED that Cabinet: (1) Note the five year Capital Programme position (as detailed within Table 1 of the report). (2) Agree to recommend to Full Council the Capital Programme 2020/21 – 2024/25 as set out in Appendix 1 of the report and that the Chief Officers be authorised to take all the necessary actions for implementation of the programmes. (3) Agree to recommend to Full Council the changes to the existing Capital Programme in relation to additions of new projects as set out in Appendix 1 of the report. (4) Agree that the Director of Finance be authorised to make the necessary adjustments to the Capital Programme to account for the final 2019/20 outturn position and any associated programme slippage. (5) Agree to recommend to Full Council the Capital Strategy, Investment Strategy, Treasury Management Strategy and Minimum Revenue Provision Policy as detailed in Appendices 3 – 6 of the report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Six Appendix 1: Detailed Capital Programme Appendix 2: Pipeline Schemes Appendix 3: Capital Strategy 2020/21 No. of Appendices: Appendix 4: Investment Strategy 2020/21 Appendix 5: Treasury Management Strategy2020/21 Appendix 6: Minimum Revenue Provision (MRP) Statement 2020/21
Background Papers: None
Flora Osiyemi Head of Finance (Capital, Treasury & Commercial) Email: [email protected] Tel: 020 8937 2998 Contact Officer(s): Daniel Omisore (Name, Title, Contact Details) Deputy Director of Finance Email: [email protected] Tel: 020 8937 3057 1.0 Purpose of the Report
1.1The purpose of this report is to set out the Council’s Capital Programme budget including new capital bids proposed for the medium term financial planning period 2020/21 to 2024/25.
2.0Recommendation(s)
That Cabinet:
2.1Note the five year Capital Programme position (Table 1);
2.2Agree to recommend to full Council the Capital Programme 2020/21 – 2024/25 as set out in Appendix 1 and that the Chief Officers be authorised to take all the necessary actions for implementation of the programmes;
2.3Agree to recommend to full Council the changes to the existing Capital Programme in relation to additions of new projects as set out in Appendix 1;
2.4Agree that the Director of Finance be authorised to make the necessary adjustments to the Capital Programme to account for the final 2019/20 outturn position and any associated programme slippage; and
2.5Agree to recommend to full Council the Capital Strategy, Investment Strategy, Treasury Management Strategy and Minimum Revenue Provision Policy in Appendices 3 – 6.
3.0Background and overview
3.1The Capital Programme is a key part of the overall budget setting process. It is focused on supporting the delivery of the Council’s statutory responsibility in relation to ensuring there are sufficient school places available for children and young people whilst, investing in new affordable housing and in our existing housing stock, town centres, public realm and community facilities across Brent.
3.2A key element of the Council’s successful financial strategy has been to expand the capital investment programme and enable it to deliver substantial revenue savings over the medium term financial planning (MTFP) period. For example, the £12.5m investment in the Digital Strategy implementation is expected to generate savings of £4.2m over the five-year period.
3.3The Capital and Investment Strategies (Appendix 3 & 4) provide further details on the overall capital strategy, which sets out how capital investment supports the delivery of the Council’s objectives. It sets out the main objectives for the Council over the Medium Term Financial Plan (MTFP) period 2020/21 – 2024/25. 3.4 Until recently the Council has utilised internal cash resources to fund the elements of the Capital Programme in lieu of borrowing, this has kept the interest costs low as it delays the requirement to undertake new external borrowing. Looking ahead borrowing will be undertaken for specific schemes and prioritised where it can have a net positive impact on the revenue budget and there is a clear repayment plan for the capital.
3.5The Capital Programme schemes which are funded using a combination of external grants and borrowing will only be undertaken once the external funding is secure; amounts of council borrowing shown are indicative. Table 1 shows the Council will require c£471m of borrowing over the 5 year period to fund the Capital Programme of which the interest costs will be charged to the revenue capital financing budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.