London Borough of Brent
Cabinet, Monday 27 July 2026 at 10.00am

Bridge Park Complex Regeneration Proposals

Decided Executive 3 papers

AI summaryBrent Cabinet approves £53.50m for Phase 1 of the Bridge Park regeneration, including a new leisure centre with a learner pool, and endorses the wider masterplan for the Bridge Park and Unisys site.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew leisure centre in Phase 1, Adult Education in Phase 2
Money£53.50m Phase 1 capital budgetIncludes up to £39.00m Strategic CIL funding
What happens nextPlanning application expected October 2026Subject to DCMS appeal outcome on listing
Who it affectsStonebridge residents and Brent boroughLeisure, community, education and 1,157 new homes

What was decided

Cabinet agreed the revised leisure centre facility mix and a phased approach, with the leisure centre as Phase 1 and the Adult Education and Community Building as Phase 2. Report 2.3

Cabinet approved a revised Phase 1 capital budget of £53.50m and the use of up to £39.00m of Strategic Community Infrastructure Levy funding. Report 2.7, 2.8, 5.1

Cabinet approved the use of the SCAPE Construction Framework call off procedure and delegated authority to award pre construction and main works contracts to the Corporate Director for Neighbourhoods and Regeneration, in consultation with the Lead Member for Planning and Regeneration. Report 2.5, 2.6

Why

Strategic evidence, including Facilities Planning Model work and engagement with Sport England, identified a borough shortfall of around 650 square metres of water space and showed the new centre would raise the share of residents in higher deprivation areas within a 20 minute catchment from around 12% to about 80%.

The scheme supports Strategic Priority 5, A Healthier Brent, in the Borough Plan 2023 to 2027 and aligns with the Joint Health and Wellbeing Strategy 2022 to 2027 and the council's Active Wellbeing approach.

The wider site, developed with Stonebridge Real Estate Development, will also deliver 1,157 homes, a 234 room hotel, retail, community spaces and public realm, including a Bridge Park legacy garden.

What happens next

Officers will continue to liaise with the Department for Culture, Media and Sport on the appeal against the decision not to list the buildings and not to issue a Certificate of Immunity. Report 9.1

A hybrid planning application is expected to be submitted in autumn 2026, with determination targeted for July 2027, and a community engagement group will be set up to help shape Phase 2. Report 2.4, 4.3

Subject to planning approval, the council will run a two stage design and build procurement through the SCAPE Framework, with selection starting in February 2027 and works on site from April 2028. Report P83

The money

  • £53.50m Revised total Phase 1 capital budget, of which £7.66m had been spent by 31 March 2026 Report 2.7, 5.1
  • £39.0m Up to this amount of Strategic Community Infrastructure Levy funding for Phase 1 Report 2.8
  • £2.50m Borrowing included in the Phase 1 funding strategy Report 5.5
  • £35m Estimated value of the leisure centre main works contract, excluding VAT Report P83
  • £50.0m Total proposed investment strategy for Phase 1, including land sale, SCIL and borrowing Report 5.5
  • £0.25m Indicative annual revenue cost of the proposed £2.50m borrowing, expected to be covered by operational surplus Report 5.8
  • £0.20m Approximate current annual cost of securing the vacant Bridge Park Complex site Report 5.9

Options considered

  • Chosen: Revised facility mix including a learner or teaching pool alongside the main pool. Strategic evidence shows a borough water space shortfall and the learner pool improves programming flexibility, learn to swim capacity and inclusion
  • Chosen: Use of the SCAPE Construction Framework call off for the leisure centre main contractor. Considered the most cost effective route to market, with pre vetted suppliers experienced in leisure centre delivery
  • Chosen: Two stage design and build approach via SCAPE, with a Stage 2A alignment gateway before pre construction. Provides a clear value for money check point and reduces risk before committing to a full pre construction agreement
  • Chosen: Use of up to £39.00m of Strategic CIL for Phase 1. Sufficient SCIL is available within the £47.9m pipeline allocation for Bridge Park and Hillside Corridor, and the leisure centre meets Strategic CIL requirements Report 5.6, 5.7
  • Chosen: Phase 2 Adult Education and Community Building delivered as a separate, later phase. Allows Phase 1 to progress on an evidence led mix while a community engagement group refines the Phase 2 design Report 2.3

Implications

  • Financial: Revised Phase 1 capital budget of £53.50m is an increase of £0.18m from the budget previously approved by Full Council; £7.66m had been spent by 31 March 2026. Report 5.1
  • Financial: Annual revenue cost of about £0.25m from £2.50m of borrowing is expected to be offset by a management and operational surplus from the new centre. Report 5.8
  • Legal: Subject to planning approval, the Corporate Director may appropriate land under section 122 of the Local Government Act 1972 and use section 203 of the Housing and Planning Act 2016 to override easements and other rights. Report 2.10, 6.9, 6.10, 6.11
  • Equalities: A new Equality Impact Assessment is being initiated, with particular attention to children, disabled residents, older residents, women and girls, and residents in higher deprivation areas; the learner or teaching pool is intended to support inclusive access. Report 7.4, 7.5, 7.6
  • Climate: The new leisure centre is targeted at BREEAM Excellent, with air source heat pumps, connection to a district heat network and solar panels, and a car free site except for blue badge parking. Report P87, 8.1
  • Risk: There is a risk that the DCMS appeal overturns the decision not to list the existing buildings, which could affect the redevelopment timetable and costs. Report 9.1
  • Staffing: The report states there are no direct Human Resources implications from the recommendations, including TUPE and pensions. Report P85, 9.2

Who and where

  • Stonebridge residents and the wider Brent borough, who will use the new leisure centre and community facilities
  • Children, families, schools, disabled residents and less confident swimmers, who would benefit from the new learner or teaching pool Report 7.5
  • Users of the current Bridge Park Community Leisure Centre and Technology House, which are proposed for redevelopment Report P169
  • Local residents who may take part in the new community engagement group for Phase 2 and the Bridge Park Legacy Garden Report 2.4, 4.3
  • Future residents of the 1,157 homes proposed across the wider Bridge Park and Unisys masterplan Report P33
  • Stonebridge Real Estate Development, the council's development partner for the wider scheme

Timeline

  • August 2026: Target to complete RIBA 3 designs for the leisure centre Report P55
  • October 2026: Target date for submission of the hybrid planning application Report P55
  • February 2027 to April 2027: Selection period under the SCAPE Framework Report P83
  • May 2027 to July 2027: Feasibility or Stage 2A design and build period Report P83
  • July 2027: Target date for planning application determination Report P55
  • August 2027: Target to complete main contractor procurement Report P55
  • September 2027: Target to commence pre construction contract Report P83
  • March 2028: Target to complete RIBA 4 designs Report P55
  • April 2028: Target to start on site Report P55
  • March 2030: Target date for the works contract to practically complete Report P83
  • March 2031: Target end of contract, end of defects liability period Report P83

Plain English for the jargon

  • BREEAM Excellent: A high rating under the Building Research Establishment Environmental Assessment Method, used to certify the sustainability of buildings.
  • Certificate of Immunity: A notice confirming that a building will not be listed as a heritage asset for a set period, sought by a developer before submitting a planning application.
  • Facilities Planning Model (FPM): A Sport England modelling tool used to assess current and future demand for sports facilities such as swimming pools and sports halls.
  • RIBA Stages: The Royal Institute of British Architects' work stages from 0 to 7, covering preparation, design, construction and use of a building.
  • SCAPE Construction Framework: A public sector procurement framework used by councils to call off construction services from pre selected contractors.
  • Strategic Community Infrastructure Levy (SCIL): A local charge that developers pay to fund infrastructure needed because of new development, collected and allocated by the council.
  • Strategic Outcomes Planning Model (SOPM): A Sport England strategic tool used alongside the Facilities Planning Model to inform leisure and physical activity planning.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Cabinet
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report provides an update on the wider regeneration proposals for the Bridge Park Complex and Unisys site, including the development of a new leisure centre as part of the council-led elements of the scheme.

1.2The report seeks endorsement of recommendations for Cabinet consideration, including the revised leisure centre facility mix and phasing proposals. It also sets out the proposed funding strategy and outlines the pre- tender considerations for the procurement of the main contractor and several decisions to progress the development subject to planning permission.

1.3The revised leisure centre facility mix has been informed by current strategic evidence, including completed Facilities Planning Model (FPM) evidence, ongoing Strategic Outcomes Planning Model (SOPM) work, the emerging Built Facilities Strategy (BFS), independent commercial appraisal and engagement with Sport England.

2.0Recommendation(s)

That Cabinet:

2.1Note the current position on the Department for Culture, Media and Sport (DCMS) decision and awarding of the Certificate of Immunity for Bridge Park Community Leisure Centre and Technology House.

2.2Acknowledges the wider Bridge Park masterplan and the planning strategy for the site and agrees for the council to submit their elements of the planning application which will include the provision as set out in paragraphs 3.2.6 – 3.2.11.

2.3Agree the revised facility mix for the new leisure centre and the scheme delivery phasing proposals for the council-led development, with the leisure centre forming Phase 1 and the Adult Education and Community Building forming Phase 2, as set out in paragraphs 3.2.12 – 3.2.27.

2.4Notes the creation of a Community Engagement Group to refine the design and facility mix for Phase 2 of the council’s development.

2.5Approves the use of a call-off procedure under the SCAPE Construction Framework for the contracts for Phase 1 of the Bridge Park Regeneration Programme on the basis of the pre - tender considerations set out in paragraph 3.2.39 of the report.

2.6Delegates authority to award the pre-construction services and main works contracts to the Corporate Director, Neighbourhoods and Regeneration in consultation with the Lead Member for Planning and Regeneration.

2.7Approves a revised total capital budget of £53.50m to deliver Phase 1 of the Bridge Park regeneration. The capital budget for Phase 2 (Adult Education and Community Building) will follow in a separate paper in due course.

2.8Agrees the use of up to £39.00m of Strategic Community Infrastructure Levy funding for Phase 1 of the Bridge Park regeneration programme.

2.9Note that the Conditional Land Sale Agreement (CLSA) is contingent upon planning and financial condition and delegate authority to the Corporate Director Neighbourhoods and Regeneration in consultation with the Lead Member for Planning and Regeneration to finalise and complete the CLSA and enter into the final transfer agreement and any other ancillary documents that may be required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10a. Appendix 1: Bridge Park Regeneration Proposals Masterplan imagesAppendix 1.2 MB Download
PDF
10b. Appendix 2: Leisure Centre ImagesAppendix 300 KB Download
PDF
Bridge Park Complex Regeneration ProposalsReport 387 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
GG
Councillor Gwen Grahl Deputy Leader & Cabinet Member for Finance and ResourcesCommittee Member, present
TA
Councillor Tina Amadi Cabinet Member for Communities, Culture & Cost-of-Living SupportCommittee Member, present
LD
Councillor Liz Dixon Cabinet Member for Community Safety & Public HealthCommittee Member, present
RJ
Councillor Robert Johnson Cabinet Member for Housing, Homelessness & RentersCommittee Member, present
MK
Councillor Matt Kelcher Cabinet Member for Regeneration & PlanningCommittee Member, present
PK
Councillor Promise Knight Cabinet Member for Cleaner Streets, Transport & Public RealmCommittee Member, present
JR
Councillor Jake Rubin Cabinet Member for Children’s Services, Employment & Climate ActionCommittee Member, present
A
AdministratorOfficer, expected
KW
Kim WrightOfficer, expected
NC
Nigel ChapmanOfficer, expected
RC
Rachel CrossleyOfficer, expected

All 22 on the meeting page

On this subject at Brent

Search all
  1. Bridge Park Complex Regeneration ProposalsThis decision
  2. Future of Bridge Park Community Leisure CentreNoted
  3. New Bridge Park CentreApproved
  4. Bridge Park - Approval to Enter into the Conditional Land Sale AgreementAgreed
  5. Bridge Park Leisure Centre - Procurement of an Architectural Led Design TeamAgreed
  6. Bridge Park Redevelopment - to enter into Heads of TermsAgreed

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open