RESOLVED : 1. That the Council enter into negotiations with the developer, Bellway Homes concerning the provision of appropriate consideration for the loss of the land to the highway. 2. That subject to these negotiations, the Council agreed the track and path as indicated in the report be reconstructed and completed under the terms of the s106 agreement for the development of Mascalls Park and for that cyclepath to be adopted by the Highway Authority - Essex County Council for its future maintenance and protection. REASON FOR DECISION To ensure that the Councils Assets are properly managed.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1This report considers the widening, re- construction and adoption of the existing footpath as a shared footpath and cycletrack leading from the Mascalls Park Development to Greensleeves Drive.
2. Recommendation(s)
2.1That the Council enter into negotiations with the developer, Bellway Homes concerning the provision of appropriate consideration for the loss of the land to highway.
2.2That subject to these negotiations, the Council agrees for the track and path as indicated in this report be reconstructed and completed under the terms of the s106 agreement for the development of Mascalls Park and for that cyclepath to be adopted by the Highway Authority - Essex County Council for its future maintenance and protection.
3. Introduction and Background
3.1Members will be aware of the Bellway Homes development at Mascalls Park for 75 residential dwellings situated in Mascalls Lane north of its junction with Warley Hill.
3.2Members will also be aware that the development is subject to an s106 agreement between the Council, Bellway Homes and Essex County Council. 3.3 The s106 agreement sets out the planning requirement for the development and includes requirements in terms of highways and is contained in the Appendix A.
3.4Schedule one of the agreement sets out the requirements of the associated highway works and includes for the construction of a 3 metres wide cyclepath/footpath link between the estate road serving the development and Greensleeves Drive, Clements Park to the north of the site, including lighting, drainage and measures to prevent its use by motorised vehicles.
3.5There are restrictions in the agreement that restrict occupation of the development (no more than 35 residential dwellings) until the cyclepath has been completed.
3.6The agreement also covers the Highway Works Agreement which deals with the construction of the highway works to adoptable standards.
3.7The developer has not sort the approval of the Council to carry out these works but would appear to have relied on the Councils assumed approval through the agreement and officers are now being pressed for permission to commence these works.
4. Issue, Options and Analysis of Options
4.1Whilst the development has passed through the planning stage and the s106 agreement has been signed by all three parties, it relates to the planning aspects of the development and does not provide agreement from the land owner to works outside the development site.
4.2No discussion regarding compensation has taken place with the developer regarding the loss of the land to highway.
4.3The land on which the cyclepath passes is land in the ownership of the Council under title EX633106 and is a path/track currently in existence although in various states of maintenance and indeed width.
4.4The land is currently heavily wooded in nature and unlikely to be used as developable land but kept as public open space.
4.5For the track to be made into a cyclepath as shown in the Appendix B would negate any maintenance to the track in the foreseeable future. In addition, for the cyclepath to be formally adopted by the Highway Authority - Essex County Council, would remove all responsibility for the cyclepath from the Council. 4.6 Within the highway adoption process, the land upon which the highway is placed remains in the ownership of the land owner and the highway is added to the Queens Highway for members of the public to have the right to pass and repass in accordance with the Highways Act. The responsibility for the maintenance and protection of the highway becomes the responsibility of the Highway Authority - Essex County Council.
Consultation
5.1No formal consultation has been undertaken regarding the proposed refurbishment.
6. References to Corporate Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
14 Ongar Road, Brentwood - Lease RenewalRESOLVED UNANIMOUSLY that: 1. Members were asked to approve the granting of a new lease to Brentwood & District Menta...
2,4,6 & 8 Harewood Road, Pilgrims HatchRESOLVED : 1. That pursuant to Section 122 Local Government Act 1972 the land at 2,4 and 6/8 Harewood Road shown on t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.