Resolved
RESOLVED UNANIMOUSLY : 1. To note the progress made to date. REASON FOR DECISION To advise Members on the progress made to date.
Asset and Enterprise Committee noted this item on Friday 27 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED UNANIMOUSLY : 1. To note the progress made to date. REASON FOR DECISION To advise Members on the progress made to date.
1.1This report considers the progress made towards the refurbishment and transformation of the Old House into flats.
2. Recommendation(s)
2.1That Members note the progress made to date
3. Introduction and Background
3.1Members will recall the decision of the Ordinary Council meeting held on 10th December 2014 that:
• Based on the Business Case presented, Members proceed with the damp, bat and structural surveys to support the proposal to convert Old House to residential units.
• Subject to no material changes to the financial viability arising from the survey works, to agree the appointment of consultants to undertake detailed designs in conjunction with English heritage and the Essex County Council Historic Buildings Adviser, leading to the preparation of contract documents to maximise the number of units achievable on the site.
• Following successful listed building consent and Planning approval, authority be given to the Leader of the Council, the Chair of the Asset and Enterprise Committee and the Acting Chief Executive, to undertake a tender process and to appoint a suitable contractor to complete the refurbishment of the property and on completion, instruct letting agents to market the property.
• Subject to the approval of this project, members endorsed the borrowing requirement of £1,080,000 and that until the budget for 2015/16 is finalised, provision for the year 1 borrowing costs will be assumed to be funded from the General Fund Working balance.
4. Issue, Options and Analysis of Options
4.1Members will be pleased to note that since the Ordinary Council meeting held on 10th December 2014, officers have carried out a tender process leading to the appointment of 'Cornish Architects' of London to lead on the project.
4.2Since the appointment of the architects officers have also appointed the design team consisting of:
• Quantity Surveyors Goring Berry LLP • Services Consultant Mendick Waring Ltd • Structural Engineers. Morton Partnership ltd
4.3A full refurbishment and demolition Asbestos Survey has been commissioned through Spectra Analysis Services Ltd and the report is awaited.
4.4Planning Pre-Application advice has been requested by the Architects prior to submitting the project for full Planning permission with Listed Building consent.
4.5Draft preliminary services drawings have been developed and applications made to the utility companies for the provision of these services.
4.6Further discussions have taken place with the Quantity Surveyor regarding the tendering process leading to the preferred contractor. New EU procurement rules (The Public Contracts Regulations 2015 that came into force on 26th February 2015 no longer permit the use of Pre Qualification Questionnaires)
4.7Damp and Bat surveys have yet to be commissioned and additional quotations have now been sought. 4.8 A Construction (Design and Management) regulations (CDM) consultant will need to be appointed for the project. CDM regulations place duties on the Client, Designer and Contractor with regard to construction projects.
5.1No formal consultation has been undertaken regarding the proposed refurbishment
6. References to Corporate Plan
6.1Value for Money: policies that invest in key services to create opportunity for all, provide better value for Brentwood’s taxpayers and enhance the Borough’s infrastructure whilst modernising and transforming Brentwood Borough Council. We will re-prioritise and focus our resources and be innovative in our approach.
6.2Our Borough: Policies which promote our environment, support sustainable growth, and safeguard our high quality environment including heritage and countryside. We will provide responsive, accessible and forward thinking services for vulnerable residents, supporting people back into work and providing good quality housing making Brentwood our residents’ Borough of Choice.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Old HouseReport | 38 KB | DownloadRead as text |
Follow Asset and Enterprise Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Mar 2015 | 14 Ongar Road, Brentwood - Lease RenewalRESOLVED UNANIMOUSLY that: 1. Members were asked to approve the granting of a new lease to Brentwood & District Menta... | Approved | Open |
| 27 Mar 2015 | 2,4,6 & 8 Harewood Road, Pilgrims HatchRESOLVED : 1. That pursuant to Section 122 Local Government Act 1972 the land at 2,4 and 6/8 Harewood Road shown on t... | Approved | Open |
| 27 Mar 2015 | Warley Training Centre - Sale and AcquisitionRESOLVED : 1. That delegated authority be given to the Chief Executive/Interim Chief Executive to approve and enter i... | Approved | Open |
| 27 Mar 2015 | Action Plan UpdateRESOLVED UNANIMOUSLY : 1. That Members note the report REASON FOR DECISION For Members to note the report. | Noted | Open |
| 27 Mar 2015 | Asset Policies (Acquisition/Disposal /Less than Best Consideration)RESOLVED UNANIMOUSLY : 1. That the policies, relating to the Acquisition, General Disposals and Disposals at less tha... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.