CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Brentwood Borough Council
Policy, Finance and Resources Committee, Monday 2 November 2015 at 7.00pm

Town Centre and Town Hall Projects

Agreed Finance 1 paper

Policy, Finance and Resources Committee agreed this item on Monday 2 November 2015. Below is the council's own wording, with the papers it was decided on.

Item210

Resolved

That Members agree to the actions and timescales incorporated in the report. REASON FOR RECOMMENDATION To ensure that the Corporate Plan 2016-2019 was supported by projects that delivered the necessary change.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Policy, Finance and Resources Committee

Executive summary

1.1This report provides the Policy, Finance and Resources (PFR) committee with an update on the key corporate projects of the Council. These are currently defined as: a) The Town Hall & Service Delivery Hub b) The Local Development Plan (LDP) c) The Town Centre (incorporating William Hunter Way) d) The Transformation Agenda of the Council

1.2The above is not an inclusive list and other projects may be incorporated as determined by the committee. However such projects are defined as being integral to the delivery of the revised Corporate Plan 2016-2019.

Recommendation

2.1That Members agree to the actions and timescales incorporated in the report.

3. Introduction and Background

3.1The Corporate Plan 2016-2019 is in the process of being approved by the appropriate committees. (PFR and then full Council) It is clear however, that the Council needs to ensure that key supporting corporate projects are in place, with correct governance to deliver the vision that is embedded in the Corporate Plan.

3.2The four projects referred to in 1.1 above are considered key for the following reasons. Project Validation The Town Hall & Will support the transformation of service Service Delivery Hub delivery, provide modern and effective customer services as well as increased utilisation of existing assets for the Council and partner organisations. The Local Development Will broaden the range of housing in the Plan (LDP) Borough and guide infrastructure delivery to meet the needs of our population now and in the future. The Town Centre Will promote the use of Council assets to (incorporating William promote sustainable development in the Hunter Way) Borough whilst supporting the future local economy. The Transformation This will explore alternative methods of service Agenda of the Council delivery, develop new ways of working for the Council and modernise service delivery, whilst delivering greater value for money.

4. Project Detail

4.1Town Hall and Service Delivery Hub

4.1.1 This project has two distinct elements. The works needed to the infrastructure of the Town Hall and the identification of services to be offered from the Town Hall – the “Service Delivery Hub”.

4.1.2 Brentwood Borough Council has begun work with partners to develop an outline business case for a service delivery hub in the Borough. It is anticipated that this will be available in January 2016. On the 13th October 2015, Brentwood Borough Council led a joint multi agency workshop with key partners including: a) Essex County Fire & Rescue Service b) Job Centre Plus c) Essex County Council including Libraries d) The Police e) NHS- Clinical Commissioning Group including Assets f) Citizens Advice Bureau g) Community Voluntary Services.

The Council will also be meeting with East of England Ambulance Service. 4.1.3 There was a consensus at the workshop that co-location with back office and front office would be beneficial for both the organisations involved and the customer. These benefits included but are not restricted to:

 Improve access for customers  Promote service integration  Develop collaborative working  Target integrated services at hard to reach groups  Secure financial savings by consolidating the public sector estate & property operations  Deliver for the informed residents with high expectations  Financial savings for each partner

4.1.4 The next stages, which have already begun, include follow up conversations with those who attended to confirm their involvement and the agreement to sign up to a Memorandum of Understanding, agreement of the draft project charter and governance arrangements, and begin drafting the outline business case. Information from each of the partners wishing to participate is being sought which will be used to support the outline business case to be ready in draft format in January 2016.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Town Centre and Town Hall ProjectsReport 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 25 attended
ML
Councillor Mrs Louise McKinlayChair, present
RH
Councillor Roger HirstVice-Chair, present
BA
Councillor Barry AspinellCommittee Member, present
GB
Councillor Gareth BarrettCommittee Member, present
GC
Councillor Graeme ClarkCommittee Member, present
PF
Councillor Paul FaragherCommittee Member, present
CH
Councillor Chris HossackCommittee Member, present
KP
Councillor Keith ParkerCommittee Member, present
WR
Councillor William RussellCommittee Member, present
CP
Chris PotterOfficer, expected
GC
Greg CampbellOfficer, present
CG
Chris GillOfficer, present

All 25 on the meeting page

On this subject at Brentwood

Search all
  1. Town Centre and Town Hall ProjectsThis decision
  2. Brentwood Town Centre Design Guide Supplementary Planning Document (SPD)Approved
  3. Town Centre Public Spaces Protection OrderApproved
  4. Town Centre Public Space Protection OrderDecided
  5. Town CentreDecided
  6. Brentwood Town Centre Action PlanAgreed

More from Brentwood Policy, Finance and Resources Committee

All decisions
MeetingDecisionOutcome
14 Mar 2017 Town Hall Remodelling - Temporary RelocationRESOLVED UNANIMOUSLY That delegated authority be given to the Chief Executive, S151 and Monitoring Officer in consult... Agreed Open
14 Mar 2017 Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ... Approved Open
14 Mar 2017 Herongate Village HallRESOLVED UNANIMOUSLY: 1. That the Committee approves that officers explore the various options for the future of . 2.... Approved Open
14 Mar 2017 Grass Verge BylawsRESOLVED UNANIMOUSLY That officers further investigate and prepare a report on the application of restrictions relati... Approved Open
14 Mar 2017 Forestry Management PlanRESOLVED UNANIMOUSLY That the Committee agrees to commission a study carried out by officers, for Brentwood Borough C... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies