Policy, Finance and Resources Committee agreed this item on Tuesday 16 February 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Committee: 1. Agrees the proposed timeline for the preparation of the outlined in Table 1 of this report. 2. Agrees to establish a cross-party working group to focus on the design and requirements for the Town Centre Action Plan. This group will comprise 4 Conservatives, 2 Lib Dems and 1 Labour. The group will be chaired by Cllr John Kerslake. Reasons for Recommendation The future planning of Brentwood Town Centre requires a holistic approach to its development to maximise the benefit for local residents and businesses. To do this, the Council needs to appoint experienced planning and development consultants to help undertake this task. To make sure that the best consultants are appointed, a clear and detailed tender brief needs to be prepared to procure this work. By engaging the Design Council in this process, the Council will ensure that the initial tender brief and consultants subsequently appointed to develop the Action Plan will be of the highest calibre.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The Council’s Corporate Plan, “Vision for Brentwood” highlights the need to develop a Town Centre Action Plan to link key development opportunities, including William Hunter Way. The Action Plan should also to take into account the wider themes of quality of design, community/landowner engagement, heritage, economy, and the deliverability of the overall plan.
1.2In order to bring forward a high quality Action Plan for the Borough’s major town centre, it is proposed to appoint high quality planning and development consultants to help officers prepare the plan. To make sure the Council gets the right Plan and the best value for money, it has been agreed to work with one of the country’s leading experts in this field, the Design Council, to prepare a high quality tender brief for the work. This brief will be used to procure the consultancy for the Brentwood Town Centre Action Plan. A timeline for taking this forward has now been proposed to take the Action Plan forward as a key Council priority (see Table 1).
2. Recommendation(s)
That the Committee:
2.1Agrees the proposed timeline for the preparation of the Brentwood Town Centre Action Plan outlined in Table 1 of this report. 2.2 Agrees to establish a cross-party working group to focus on the design and requirements for the Town Centre Action Plan. This group will comprise 4 Conservatives, 2 Lib Dems and 1 Labour. The group will be chaired by Cllr John Kerslake. 3. Introduction and Background
3.1Although there have been consultation exercises in the past relating to specific sites in the town centre, such as William Hunter way, that Administration considers it more appropriate to develop a comprehensive Action Plan for the whole of Brentwood Town Centre.
3.2The purpose of the Action Plan will be to create a robust strategy for environmental, economic and social improvements to the town centre. To take this forward, the Council needs to begin by agreeing a clear and detailed brief for the preparation of the Action Plan. To do this, the Design Council, widely acknowledged as national experts in this field, will help prepare the brief.
3.3Once the brief is agreed, it is proposed to go out to tender to appoint planning and development consultants to take forward the preparation of a Brentwood Town Centre Action Plan. A proposed timetable for the appointment of consultants and the subsequent preparation of the Plan is outlined in Table 1 of this report.
3.4By getting additional capacity and expertise on board to help develop the brief and the final Action Plan, the Council can be assured that it will get value for money and a suitably robust and deliverable strategy for the Brentwood Town Centre to shape its development over the next 10 years.
4. Issue, Options and Analysis of Options
4.1In taking forward a comprehensive Action Plan for Brentwood Town Centre, there is a need to appoint external consultants with capacity and expertise in planning and property development. To make sure the most cost effective consultants are appointed, a clear and detailed planning brief needs to be prepared so that the final Action Plan reflects exactly what is needed for Brentwood Town Centre.
4.2By working in partnership with the Design Council, the Council will be assured to get a tender brief that will reflect its corporate ambitions for the preparation of the final Action Plan. A proposed timetable for the preparation of the initial tender brief and the subsequent Action Plan are outlined in Table 1. TABLE 1 Indicative Timelines (subject to input of the Design Council and the Consultants to be appointed):
1. Appointment of Design Council to help prepare brief– started Jan 2016
2. Inception Meeting and Site Walkabout with Design Council – completed Jan 2016
3. Strategic Visioning Workshop (key members and officers) – Feb 2016
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.