RESOLVED UNANIMOUSLY that: 1. The Committee approves the appointment of an external specialist company to complete a full stock condition survey of the housing assets, anticipated to cost in the region of £200,000, a £10,000 discretion to be allowed. 2. The Committee approves Officers arranging to tender the works using the Council procurement process and that delegated authority be awarded to the Head of Housing in Consultation with the Head of Paid Service and Section 151 Officer to award the contract – in line with the timetable set in point 4.16 of the report. Reasons for Recommendation To enable BBC to maintain its responsibilities and fulfil its obligations as a landlord. Until a full survey of all stock was available, asset management decisions were based on current officer knowledge or reaction to component failure. It was important that investment decisions were informed by a sound understanding of the condition of the Council’s properties. Whilst staff had an awareness of condition, an externally validated assessment was seen as essential. It is vital that the Council had up to date information about condition of the HRA stock in order to support its investment decisions each year. The risks in not having this information included the failure to provide adequate resources to tackle repairs and maintenance that subsequently led to the need for replacement at a much higher cost. For short to medium term financial planning purposes a full stock condition survey (100%) was considered necessary. This would provide a sound baseline position and a high level of confidence in the future allocation of investment across the stock. The result of the survey would be used ... view the full minutes text for item 271.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Environment and Housing Management Committee
Executive summary
1.1As part of the Housing transformation programme Officers have identified that Brentwood Borough Council currently holds limited stock condition data on its HRA assets.
1.2It is proving problematic to appropriately identify properties that fail the Decent Homes standard and which require Capital investment, which means the Council is not delivering value for money. It is essential that the Council has robust property intelligence on all its properties to ensure that informed investment decisions are selecting properties for capital works or planned maintenance.
1.3The best approach is considered to be the employment of an external provider to undertake a 100% stock condition survey and produce a report including a future programme of Capital works and stock options.
1.4Production of robust condition survey data will enable us to quantify our current and future liability with confidence. Ensuring there are no significant unidentified maintenance liabilities leading to urgent reactive replacements at increased cost.
1.5Increasing the bank of real data makes cost and condition data increasingly accurate. This will give greater confidence in the accuracy of our Decent Homes statistical return.
1.6The cost of the survey, with all associated works, is estimated to be c.£200K. 2. Recommendation(s)
2.1The Committee is asked to approve the appointment of an external specialist company to complete a full stock condition survey of the housing assets, this is in the region of £200K.
2.2The Committee is asked to approve Officers to arrange to tender the works using the Council procurement process and that delegated authority be awarded to the Head of Housing in Consultation with the Head of Paid Service and Section 151 Officer to award the contract – in line with the timetable set in 4.16.
3. Introduction and Background
3.1This report outlines the need for the complete condition survey of dwellings held within the Housing Revenue Account (HRA).
3.2Historically, stock condition data has been collected on a piece meal basis. However, this has not been transferred into a database, is currently stored in paper format and does not influence work programmes . Most of these would now be considered out of date as components have either deteriorated and been replaced in their entirety or had significant repairs.
3.3This approach has led to programmes being generated by individuals as opposed to a systematic approach. In turn, this has resulted in numerous items being replaced too frequently and more often than not prematurely. This has obvious consequences and has shown significant impact on spend levels over the term.
3.4This situation also leads to a reactive approach whereby components have failed but this is not known until the failure occurs. i.e. boiler failure; where systems are obsolete and past due for replacement.
3.5The stock survey will provide condition information which can be used to plan investment in the housing stock and thereby maintain properties in good condition. The stock condition information will be uploaded to and held on our Keystone Asset Management (KAM) database provided by Keystone Asset Management Solutions, one of the market leaders in this field.
3.6Each surveyed property will be assessed against, amongst other things, the Governments national standard for Decent Homes. This standard is basic and does not cover the full range of maintenance activities required to properly maintain a property. It is framed in such a way that a number of grounds of failure may need to exist before the property itself fails. 3.7 In summary, there are four broad criteria which are: (see appendix A)
Criterion A - meets the current statutory minimum standard for housing Criterion B - is in a reasonable state of repair Criterion C- has modern facilities Criterion D - provides a reasonable degree of thermal comfort
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Housing Management Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Street Care Updates and ActionsRESOLVED UNANIMOUSLY that: 1. The Committee agreed to the Chief Executive writing to the ECC Cabinet Member for Highw...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.