Renewal of Communal Gas Central Heating, Hot and Boosted Cold Water Systems to Drake House
ApprovedCommittee1 paper
Environment and Housing Management Committee approved this item on Wednesday 9 December 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY that 1. Committee approved Option 4: to replace all communal systems. 2. Council Officers be requested to arrange to tender the works using the Council procurement process (timetable outlined in point 4.13) and delegated authority be awarded to the to the Head of Housing in consultation with the Head of Paid Service and Section 151 Officer to award the contract. Reasons for Recommendation To enable BBC to maintain its responsibilities and fulfil its obligations as a landlord. It adopted a “spend to save” approach which saw high initial investment with significant long term gains due to reduced fuel use as a consequence of system run time and reduced frequency of unscheduled maintenance visits. The approach allowed the residents to manage and review their individual energy and water consumption. At the moment, the residents paid a heating charge which was divided over all flats irrespective of how much energy they used. Going forward residents would only pay for the energy they used and would be able to have full control of the heating in their properties. Water meters would also be fitted to each property which would reduce residents’ costs as they would only pay for the water that they consumed.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Environment and Housing Management Committee
Executive summary
1.1The communal gas central heating, hot and boosted cold water systems at Drake House are considered beyond economic repair.
1.2System components are obsolete, do not meet current regulations and are failing with increased regularity. It is proving problematic to maintain adequate system functionality within reasonable cost levels.
1.3A report on the system failures and the best approach for renewal has been commissioned and produced. This suggests that the systems are replaced in their entirety with modern components meeting all current regulations.
1.4The cost of renewal of the systems, with all associated works, is estimated to be c.£470K.
2. Recommendation(s)
2.1The Committee is asked to approve 4.8 recommendation Option 4.
2.2Council Officers arrange to tender the works using the Council procurement process see timetable outlined in 4.13 delegated authority be awarded to the be awarded to the Head of Housing in Consultation with the Head of Paid Service and Section 151 Officer to award the contract.
1 3. Introduction and Background
3.1This report outlines the need for the replacement of the gas fired heating, hot and cold water systems at Drake House.
3.2Over the last year or so there have been repeated notifications of system faults and failures leading to reduced service or loss to individual dwellings. Each time the repairing organisation has indicated that the system is obsolete and is past due for replacement.
3.3In September 2015, a report was commissioned to undertake a survey of the existing system, identify its failures and outline the possible alternatives.
4. Issue, Options and Analysis of Options
4.1A Design Feasibility Study has been completed by Watts Consultancy Limited . The report has identified the problems with the current system, discusses the options available and suggests the type of replacement. These are outlined below.
Options considered
1 Replace individual components, on a when failed basis, and continue to maintain the existing systems for a prolonged period. 2 Replace/upgrade individual elements of the systems. 3 Complete renewal of all system components including upgrading to current standards and the introduction of individual control and metering. 4 Replace and improve the current systems in entirety
4.3The first option is uneconomical in the short to medium term. The majority of the system components are old, obsolete and/or inadequate. Sourcing these is difficult, time consuming and, may soon prove impossible. This places increased pressure on the ‘back up’ systems, leads to longer periods of service downtime, and leaves residents with insufficient heat or hot water.
2 4.4 There is an imbalance in the heating system. Some residents experience ‘cold spots’ within their dwelling whilst others feel the heat is more than sufficient with the controls set low. The existing controls do not meet current standards.
4.5Further, significant sections of the infrastructure pipework are in poor condition and the hot services are inadequately insulated.
4.6The second option is uneconomical in the medium to long term. Although replacing individual items will improve the system it will only do so in part, with components that are outmoded. Ultimately, the whole will need to be replaced.
4.7A third option is to switch from the existing gas fired system to an electric heating and hot water system. This has increased installation and operating costs and will not prove energy efficient.
4.8The fourth option is to replace and improve the current systems in entirety. This, in turn, has two further options:
Replace all communal systems. Renew the boosted cold water supply but introduce individual heating and hot water systems allowing localised control.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Housing Management Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Street Care Updates and ActionsRESOLVED UNANIMOUSLY that: 1. The Committee agreed to the Chief Executive writing to the ECC Cabinet Member for Highw...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.