RESOLVED 1. To agree the charging rates detailed in paragraphs 5.5, 5.8 and 5.9, as the basis for the production of the Council’s Community Infrastructure Levy Preliminary Draft Charging Schedule. 2. To approve the Preliminary Draft Charging Schedule document as set out in Appendix B of the report, for a six week public consultation.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1This report updates members on progress preparing the Council’s Community Infrastructure Levy (CIL) and the proposed first stage of consultation, the Preliminary Draft Charging Schedule.
1.2Viability appraisals have been carried out in relation to residential and commercial development to inform suggested charging rates. Members are requested to agree these rates and areas as the basis for public consultation.
Recommendations
2.1To agree the charging rates detailed in paragraphs 5.5, 5.8 and 5.9, as the basis for the production of the Council’s Community Infrastructure Levy Preliminary Draft Charging Schedule.
2.2To approve the Preliminary Draft Charging Schedule document, as set out in Appendix B, for a six week public consultation.
3. Introduction and Background
3.1The CIL is a statutory charge which allows Councils to require mandatory financial contributions from various forms of development within their area, in order to help fund supporting infrastructure.
3.2It effectively replaces much of the existing process of planning obligations known as ‘Section 106’ agreements. CIL monies are pooled into one fund, there is no time constraint for the spending of monies collected and it can be used on any infrastructure needed to support new development across the Borough. Whilst ‘Section 106’ agreements will be used and negotiated to secure site specific related infrastructure e.g. affordable housing and to mitigate the direct impacts of individual developments. Since April 2015 the use of ‘Section 106’ agreements have been limited to five contributions, for an item of infrastructure that is not intended to be funded by the levy.
3.3Before a CIL Charging Schedule can be adopted it must be subject to two rounds of formal consultation followed by an independent examination. The first formal stage towards the adoption of a Charging Schedule is the production of the Preliminary Draft Charging Schedule for consultation set out the consultation requirements including persons who are a resident or carrying on business in the area.
3.4The second stage is the publication of a final Draft Charging Schedule for representations during a period of at least four weeks. During this period any person may request to be heard by the examiner.
3.5At examination in pubic, the examiner will approve, modify or reject the Draft Charging Schedule. Once any recommended modifications have been addressed by the Council it may then proceed to adopt the Charging Schedule by a resolution of Ordinary Council. If the Council adopts CIL, it becomes the collector of CIL and is therefore responsible for the delivery of CIL, as a charging authority.
3.6The Council will also need to publish a list of infrastructure projects or types of infrastructure intended to be funded or part-funded by the levy (known as the Regulation 123 list). This will be informed by the Infrastructure Delivery Plan which provides a basis for identifying the priorities for future infrastructure funding.
3.7The CIL Regulations set certain requirements about who the charging authority should consult on a Preliminary Draft Charging Schedule including persons who are resident or carrying out business in the area. No minimum length of consultation is stipulated in the regulations, however, in line with the Council’s Statement of Community Involvement (SCI) a six-week period is proposed. 4. Issue, Options and Analysis of Options
4.1The economic viability assessments that accompany the Preliminary Draft Charging Schedule have been prepared by appointed specialist consultants (Nationwide CIL Service, Heb Property Consultants, and Gleeds Property and Construction). The viability assessment work informs the setting of a charging schedule.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.