RESOLVED to: 1. Agree to Option 1A as set out in section 17.6 of the report and methods to relocate out of the Town Hall while construction work is undertaken. 2. Delegate authority to the Chief Executive and Section 151 Officer in consultation with the Leader, Deputy Leader and the Leaders of the Opposition groups to make decisions at the appropriate procurement points. 3. Agree that reports would be provided to Policy, Finance and Resources Committee to enable monitoring of the progress of the project and report as appropriate to Council of any major financial variances for the duration of the project. Reasons for recommendations Although Option 1A was not the most economically advantageous, it considered the future risk against likely return. The housing market was strong and there appeared to be no indication that it would alter for the foreseeable future. Option 1A also relocated the services out of the building during construction works to reduce the health and safety risk, speed up the process, reduce costs and accelerate the likely point at which the Council would start to generate income. It moved the project on to a firm decision which could then be worked up into full specification and the procurement process with delegated authority to the Chief Executive, section 151 Officer and Deputy Chief Executive in conjunction with the Leader, Deputy Leader and opposition leaders.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report of: Greg Campbell, Project and Programme Manager
Wards Affected: All
This report is: Public
1. Executive Summary 1.1 This report asks Members to consider the options within this report, supported by the business case attached at Appendix A, to determine whether to remodel the Town Hall to: form a service delivery Hub, including the transformation of front and back office Council service space and delivery; develop commercial or residential lease accommodation on the second and third floor of the Town Hall building
1.2Both business options are financially viable. However, they require an investment and are based on a long term financial plan. Both options will realise a saving against the current revenue expenditure of the Town Hall after the third year of delivery dependent on the decision taken.
1.3Further, the Council will continue to work with groups to seek early adopters and revenue where appropriate.
2. Recommendations 2.1 Agree to Option 1A as set out in section 17.6 of the report and methods to relocate out of the Town Hall while construction work is undertaken
2.2Delegate authority to the Chief Executive and Section 151 Officer in consultation with the Leader, Deputy Leader and the Leaders of the Opposition groups to make decisions at the appropriate procurement points.
2.3Agree that reports are provided to Policy, Finance & Resources Committee to enable monitoring of the progress of the project and report as appropriate to Council of any major financial variances for the duration of the project. 3. Introduction 3.1 This document seeks the Council’s approval of the business model for the future of the Town Hall. This will set the parameters and scope of the finances, which in turn will enable progression to the specification, procurement and implementation processes to begin. This report and the supporting business case at Appendix A sets out the two options.
4. Background Summary 4.1 Since 2010, the Council has reviewed a number of options for the redevelopment of the Town Hall. This has led to decisions by Council at committees, most recently at Ordinary Council in June 2016, to seek to: Create a service delivery hub Reduce expenditure, and Create revenue streams.
4.2This will be achieved by significant remodelling of the Town Hall and making better use of space by reducing the Council service footprint, leading to reduced running costs, and by the creation of a Service Delivery Hub, which will create revenue streams and enhance the customer experience.
4.3Those agreeing in principle to join the Hub so far are listed below: Job Centre Plus Essex Police Mind ECC Citizens Advice Brentwood Council for Voluntary Services
4.4Working together, Essex and Brentwood councils are committing to consider opportunities to expand the use of the Hub through the deployment of services to the Hub. This work is considering services both County led or locally led in order that Brentwood residents continue to benefit from the most efficient service
4.5Although both organisations accept there is much to discuss, the main focus will be based upon: A willingness to work together A need to add value and achieve value for the services A desire to enhance the customer experience
4.6Brentwood Council is presently working with the Police who are seeking relocation to the Town Hall lower ground space. It is anticipated that contracts should be signed during the coming weeks and preparations for their relocation are being made.
4.7The Ordinary Council meeting held in June 2016 agreed to progress the Hub and bring to this meeting a business case that would enable the project to move to the specification, procurement and implementation stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies