Brentwood Asset Development Programme

Approved Committee 3 papers

Policy, Projects and Resources Committee approved this item on Tuesday 19 September 2017. Below is the council's own wording, with the papers it was decided on.

Item116

Resolved

RESOLVED that: 1. The Committee approved a hybrid approach for securing the Councils Vision and Objectives. 2. Delegated authority be given to the Chief Executive in Consultation with Group Leaders or their appointed deputies ... view the full minutes text for item 116.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Policy, Projects and Resources Committee

Executive summary

1.1The purpose of this report is to update Members on progress made to date in taking forward the Council’s asset development programme and to outline next steps and issues that may arise. 1.2 The aim of the asset development programme will be to steer and manage development opportunities from the Council’s property asset base so as to deliver improved revenue income streams from the portfolio but at the same time securing the regeneration, economic development and housing objectives of the Council. 1.3 The project board has considered a range of options for securing returns from the portfolio and at this stage favours a hybrid approach which allows the Council to take forward smaller projects alone but shares risk on the more complicated projects. 1.4 Under a hybrid approach straightforward smaller sites are self-developed by the Council with more complex sites developed by a single joint venture development partner in accordance with the Council’s vision for each of those sites. This activity will be programmed over a number of years in accordance with business plans and cash flow requirements that will be agreed by Committee. 1.5 For a Hybrid approach to deliver successfully there will be a requirement for the Council to undertake development activity itself. It will need to resource the role and manage the related risks. In addition, it is crucial that the Council adequately resources its role as a partner to the activities of a partnership, either as shareholder to a new Company, or through an alternative governance arrangement. A common mistake by Councils is not to undertake this role with appropriate resource and skillsets such that the partnership either does not operate effectively, or the rewards between the partners are not appropriately shared. 1.6 The next stage in taking forward the project is to consult the market. This will identify market appetite for the options and assist in defining the scope of the approach the Council may wish to take forward and how it can be realised/procured. This will inform how the Council might engage with partners or indeed procure a Joint Venture development partner or investment partner. It will also inform how the Council may take forward self-development projects. As such this next stage of the work is critical in shaping the delivery of the entire programme over future years.

1.7The output of this next stage will be considered by the Project Board, comprising Cllr McKinlay, Cllr Kerslake, Phil Ruck, Steve Summers and John Chance in a check and challenge session, with the objective of developing a detailed recommendation to the Council’s Policy Performance and Resources Committee for how the project should be taken forward.

2. Recommendation(s)

2.1The committee approves a Hybrid approach for securing the Councils Vision and Objectives.

2.2That delegated authority be given to the Chief Executive in Consultation with Group Leaders or their appointed deputies to consult with the market to inform the next stage of project development.

2.3A further report be brought back to this committee’s November meeting with the Project Board’s detailed recommendations and action plan for taking forward this project.

2.4The committee approves that officers investigate the establishment of an appropriate investment vehicle or vehicles for the delivery of the Councils objectives. Such an investment vehicle will be subject to appropriate legal requirements.

2.5That progression of the development and delivery of the asset programme will be brought back to an appropriate future committee.

3. Introduction and Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Assets Initially ConsideredAppendix A 23 KB Download
PDF
OptionsAppendix B 277 KB Download
PDF
Brentwood Asset Development ProgrammeReport 129 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 21 attended
ML
Councillor Mrs Louise McKinlayChair, present
JK
Councillor John KerslakeVice-Chair, present
GB
Councillor Gareth BarrettCommittee Member, present
PF
Councillor Paul FaragherCommittee Member, present
CH
Councillor Chris HossackCommittee Member, present
RK
Councillor Roger KeebleCommittee Member, present
DK
Councillor David KendallCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
KP
Councillor Keith ParkerCommittee Member, present
BA
Councillor Barry AspinellCommittee Member, in attendance
TB
Councillor Thomas BridgeCommittee Member, in attendance
JC
Councillor Jon ClokeCommittee Member, in attendance

All 21 on the meeting page

More from Brentwood Policy, Projects and Resources Committee

All decisions
MeetingDecisionOutcome
18 Sep 2018 2018/19 General Fund Revenue, Housing Revenue Account, Capital Budget Monitoring and Treasury Activity UpdateRESOLVED UNANIMOUSLY: 1. To agree the projected outturn position for 2018/19 of the Council’s General Fund Revenue bu... Agreed Open
18 Sep 2018 Department for Communities and Local Government (MHCLG) Pilot Programme for 75% Business Rates Retention - 2019/20RESOLVED UNANIMOUSLY: 1. Members note the content of the report and its potential implications for the forthcoming bu... Agreed Open
18 Sep 2018 Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on... Approved Open
18 Sep 2018 Feasibility Study for Parking on Housing GreensRESOLVED UNANIMOUSLY: 1. To instruct officers to identify possible sites for parking on Housing Greens and undertake ... Decided Open
18 Sep 2018 Leisure StrategyThat Members agree the and action plan at Appendix A. Reasons for Recommendation As part of the Council’s due diligen... Agreed Open