RESOLVED that : 1. To agree the revised Insurance & Risk Management Strategy. 2. To agree the amendments to the Strategic Risk Register, as shown in Appendix B of the report, and that the risk scores recorded for each risk accurately represents the current status of each risk. 3. To agree the risk exposure changes and the new risks, as shown in Appendix C of the report to the Operational Risks. Reason for Recommendation Risk Management continued to be embedded quarterly within the Senior Management Team reports, where Service Heads discussed the top level risks for their service areas to ensure that the risks were updated to reflect the ongoing changes. In addition, the Risk & Insurance Officer would continue to work with risk managers to maintain the good progress to date and further develop a consistent application of risk management considerations across all operations of the Council.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The report updates members of the Audit Committee on the status of the Council’s 2017/18 Strategic Risk Register and the progress being made across Services in delivering Operational Risk Registers.
Recommendations
2.1To agree the revised Insurance & Risk Management Strategy
2.2To agree the amendments to the Strategic Risk Register, as shown in Appendix B, and that the risk scores recorded for each risk accurately represents the current status of each risk.
2.3To agree the risk exposure changes and the new risks, as shown in Appendix C, to the Operational Risks
3. Introduction and Background
3.1The governance arrangements set out in the ‘Insurance & Risk Management Strategy’ require the Audit Committee to review the strategic risks every quarter and the operational risks every six months.
3.2The strategic and operational risk registers are monitored quarterly by the Corporate Leadership Board (CLB) who consider the risks, the mitigations and agrees the content. It is the responsibility of the Audit Committee to review the strategic risks and confirm they are confident that the risks associated within this register are those which are strategic and relevant to the organisation at this point in time and the considered future. 4. Issue, Options and Analysis of Options
Insurance & Risk Management Strategy
4.1The annual review of the Insurance and Risk Management Strategy has been carried out and is attached at Appendix A. It now includes guidance on self-funding for insurance purposes.
Strategic Risks
4.2In accordance with the Council’s Insurance and Risk Management Strategy, risk owners have reviewed their risks and risk scores and updated them for the coming financial year 2017-18. These were discussed and agreed by CLB on 11 September 2017.
4.3Attached to this report at Appendix B is a summary showing the current status of each risk and any movement in risk score compared with previous monitoring periods, together with explanatory commentary on the key issues for each risk.
4.4As a result of the current risk review one risk has decreased and twelve risk scores have remained unchanged.
4.5The risk where the risk score has reduced is as follows:
Yellow risk RSK5 – Information Management and Security (Row No. 10) This risk has reduced following the PPR Committee formally adopting the policies. The newly adopted policies will be rolled out along with DPA training to all staff by the end of September 2017.
4.6There has been one new risk added to the Strategic Risk Register:
Amber risk RSK15 – Non-compliance by existing third party contractors to the council with the principles of the Data Protection Act 1998. (row 5) This has been given a risk score of 15; 3 = likelihood, 5 = Impact Risk Matrix
4.7The fourteen risks are plotted on the risk matrix in Table 1. The current assessment identifies that two risks will remain in the red area of the risk matrix.
Table 1 – Risk Matrix Definite
5 10 15 20 25
4 8 12 16 20 Likely Very Likelihood / Probability
3 6 9 12 15 Likely
2 4 6 8 10 Likely Less Unlikely
1 2 3 4 5
Negligible Minor Moderate Significant Major Negative Impact / Severity
No. Risk No. Risk
1 Finance Pressures 9 Lack of strategic Direction
2 Local Development Plan 10 Failure to Spend Capital Receipts
3 Disaster Recover/Continuity Planning 11 Roll out of Universal Credit Extension of Right to Buy to registered 4 Organisational Capacity 12 provider tenants 5 Information Management and Security 13 Failure to deliver key Corporate Projects
6 Risk longer required 14 Failure of Democratic Services
7 Commercial Activities 15 Data Protection Act 1998
8 Contract/Partnership Failure Operational Risks
4.8Operational risk management is concerned with reviewing those risks that are faced in the day-to-day delivery of services, particularly where effective management of those risks could result in a reduction in insurance claims and related costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Strategic and Operational Risk ReviewRESOLVED : To agree the amendments to the Strategic Risk Register, as shown in Appendix A (of the report), and that t...
Internal Audit Progress Report 2017/18RESOLVED UNANIMOUSLY that: The Committee receives and notes the contents of the reports. Reasons for Recommendation T...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.