RESOLVED : 1. To agree the amendments to the Strategic Risk Register, as shown in Appendix A (of the report), and that the risk scores recorded for each risk accurately represents the current status of each risk with the exception of risks 5 and 11 which should be raised to “red”. 2. To agree the risk exposure changes, as shown in Appendix B (of the report), to the Operational Risks. Reasons for Recommendation Risk Management continued to be embedded quarterly within the Senior Management Team reports, where Service Heads discussed the top-level risks for their service areas to ensure that the risks were updated to reflect the ongoing changes. In addition, the Risk & Insurance Officer would continue to work with risk managers to maintain the good progress to date and further develop a consistent application of risk management considerations across all operations of the Council.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The report updates members of the Regulatory & Governance Committee on the status of the Council’s 2018/19 Strategic Risk Register and the progress being made across Services in delivering Operational Risk Registers.
2. Recommendation(s)
2.1To agree the amendments to the Strategic Risk Register, as shown in Appendix A, and that the risk scores recorded for each risk accurately represents the current status of each risk.
2.2To agree the risk exposure changes, as shown in Appendix B, to the Operational Risks
3. Introduction and Background
3.1The governance arrangements set out in the ‘Insurance & Risk Management Strategy’ and terms of reference of committees from our constitution require the Regulatory & Governance Committee to review the strategic risks every quarter.
3.2The strategic and operational risk registers are monitored quarterly by the Corporate Leadership Board (CLB) who consider the risks, the mitigations and agrees the content. It is the responsibility of the Regulatory & Governance Committee to review the strategic risks and confirm they are confident that the risks associated within this register are those which are strategic and relevant to the organisation at this point in time and the considered future. 4. Issue, Options and Analysis of Options
Strategic Risks
4.1In accordance with the Council’s Insurance and Risk Management Strategy, risk owners have reviewed their risks and risk scores and updated them for the coming financial year 2018-19.
4.2Attached to this report at Appendix A is a summary showing the current status of each risk and any movement in risk score compared with previous monitoring periods, together with explanatory commentary on the key issues for each risk.
4.3As a result of the current risk review three scores have increased, two risk scores have decreased and one risk has been removed. The remaining scores have remained unchanged, totaling 13 Strategic Risks on the register.
4.4The risk where the risk score has increased is as follows:
Amber risk RSK10 – Failure to spend capital receipts (Row No.5) This risk has increased due to an increase in capital receipts for 2019/20.
Yellow Risk RSK5 – Information Management and Security (Row No.10) RSK15 has now been incorporated into RSK5 and the risk score has been adjusted to reflect this and the potential financial impact to the Council.
Yellow Risk RSK10 – Commercial Activities (Row. No 9) The Risk has increased due to the Council approving to borrow up to £30m to provide a Loan facility to SAIL, and the potential financial impact.
4.5The risk where the risk score has decreased are as follows:
Green risk RSK4 – Organisational Capacity (Row No.11) This risk has decreased following two additional senior appointments for Director of Operations and Director of Strategic Planning.
Amber Risk RSK2 – Local development Plan (Row No.4) The Council have now received a response from the state that the Local Plan will not be subject to Government Intervention. Work remains on course to deliver the plan and the score has been adjusted accordingly. 4.6 The risk which has been removed is as follows:
RSK15 – The General Data Protection Regulations GDPR has been adopted by virtue of the Data Protection Act 2018 and accordingly this Risk has now been incorporated within RSK5 – Information Management & Security of the Strategic Risk Register, which deals with data protection.
Risk Matrix
4.7The thirteen risks are plotted on the risk matrix in Table 1. The current assessment identifies that three risks will remain in the red area of the risk matrix. Table 1 – Risk Matrix
5 10 15 20 25 RSK1 Definite
4 8 12 16 20 RSK11 RSK12 Likely Very Likelihood / Probability
3 6 9 12 15 RSK3 RSK2 RSK10 Likely
2 4 6 8 10 RSK5 RSK13 RSK7 Likely Less
RSK8
1 2 3 4 5 RSK14 RSK4 Unlikely
RSK9
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.