2017/18 Medium Term Financial Plan Mid Year Review
AgreedCommittee1 paper
Policy, Projects and Resources Committee agreed this item on Wednesday 29 November 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED to 1. Agree the Revised General Fund Position as shown in Table 6. 2. Agree the current Capital Programme position as shown in Table 7. 3. Agree the current HRA position as shown in Table 9. Reasons for Recommendation Effective financial management underpins all of the priorities for the Council and will enable the Council to operate within a sustainable budget environment.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Policy, Projects and Resources Committee
Executive summary
1.1The Medium Term Financial Plan (MTFP) sets out the key financial management principles and budget assumptions. It is then used as the framework for the detailed budget setting process to ensure that the Council’s resources are managed effectively in order to meet its statutory responsibilities and deliver the priorities of the Council, over the medium term.
Recommendations
2.1Agree the Revised General Fund Position as shown in Table 6.
2.2Agree the current Capital Programme position as shown in Table 7.
2.3Agree the current HRA position as shown in Table 9. 3. Introduction & Background
3.1On 1st March 2017 at Ordinary Council, The Medium Term Financial Plan was approved and the budgets for General Fund, HRA and Capital Programme were set for 2017/18 – 2020/21.
3.2On the 20th June 2017, Policy, Project and Resources Committee reported revised working balance positions following the 2016/17 outturn. And the capital programme was amended for any carried forwards/slippage to specific projects.
4. General Fund
4.1The General Fund Revenue position as approved on 1 March 2017 and the revised working balances as at 20 June 2017 is outlined in Table 1.
Table 1 – General Fund Revenue Revised Position as at 1 March 2017 2017/18 2018/19 2019/20
£’000 £’000 £’000 Total General Fund Net Expenditure 9,769 9,867 9,851 Total Funding (9,486) (8,360) (7,807) Funding Gap 283 1,537 2,044
Working Balance b/fwd 3,742 2,991 1,383 Less:- Funding Gap 283 1,537 2,044 Earmarked for WHW 350 Nil Nil Earmarked for Town Hall Project 118 71 Nil Working Balance c/fwd 2,991 1,383 (661)
4.2This position is an indication of what the Council has achieved since March 2015, when original 2017/18 closing working balances were predicated to be only £755k, compared to the above table that is now showing just under £3m, and within minimum reserve levels.
4.3This position also highlights, the challenges in which the Council still faces, if no further action is taken to reduce the funding gap. Finance Settlement 4.4 As detailed information on funding will not be available till late December 2017, the funding assumptions are as per those reported at the budget setting meeting on 1 March 2017. These are detailed in the paragraphs below.
Revenue Support Grant 4.5 As announced in December 2015, Revenue Support Grant (RSG) will be phased out entirely by 2019/20. This will ‘pave the way for the implementation of 100% business rate retention’ and will assess the main income streams available to local government.
Business Rate Retention
4.6The Council is currently part of the Essex Wide Pool for Business Rates in 2017/18. From 2018/19 the pool will consist of fifteen Essex local authorities including Essex County Council, Essex Fire Authority, one unitary and twelve Borough and District Councils. By pooling, any levy payments that would have been made to Central Government in relation to business rate growth can be saved and distributed to the members of the Pool. No additional income has been budgeted for in 2018/19 due to the uncertainty of the surplus that could be received.
4.7On 26th October 2017, The Council agreed to be part of a pilot “pool” submitted to DCLG by Essex County Council, for 100% Business Rates Retention in 2018/19, The outcome of the pilot bids are yet unknown, so no adjustments have been made to the medium term financial plan. The Council is expected to find out whether the Essex wide bid is successful before the Finance settlement is announced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Projects and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Asset Development Programme UpdateTo approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.